Question

We are evaluating a project that costs $924,000, has a four-year life, and has no salvage value. Assume that de...

We are evaluating a project that costs $924,000, has a four-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 87,600 units per year. Price per unit is $34.55, variable cost per unit is $20.80, and fixed costs are $756,000 per year. The tax rate is 35 percent, and we require a return of 13 percent on this project.

Requirement 1:

Calculate the base-case cash flow and NPV. (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).)

  Base-case cash flow $   
  NPV $   
Requirement 2:

What is the sensitivity of NPV to changes in the sales figure? (Do not round intermediate calculations.Round your answer to 3 decimal places (e.g., 32.161).)

  Sensitivity of NPV $   
Requirement 3:

If there is a 500-unit decrease in projected sales, how much would the NPV drop? (Do not round intermediate calculations. Input your answer as a positive value. Round your answer to 2 decimal places (e.g., 32.16).)

  NPV drop $   
Requirement 4:

What is the sensitivity of OCF to changes in the variable cost figure? (A negative amount should be indicated by a minus sign. Round your answer to 2 decimal places (e.g., 32.16).)

  Sensitivity of OCF $   
Requirement 5:

If there is $1 decrease in estimated variable costs, how much would the increase in OCF be? (Round your answer to the nearest whole dollar amount (e.g., 1,234,567).)

  Increase in OCF $   
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Compute the base case NPV and the cash flows in the following manner: 1 Requirement 1 2 Initial Cost 3 Life of the 924000 n y2 3 4 Requirement 1 Initial Cost Life of the Salvage value 924.000 Cost-Salvage valueyLife S231.000 8 Sales S34.55 Less: VariReduced sales figureby 10% -B2(1-10% 20.8 87600 C2-C3 756000 231000 -C4-C5-C6 0 C7-C8 C6 -C9+C10 Present -34.55#87600 -20.8The result will be as follows: 3026580 1822080 1204500 S756,000.00 S231,000.00 S217,500.00 $76,125.00 $141,375.00 S231,000.001 Old units 2 New Units 87600 -B1-500 Present Reduced sales 4 Sales 5 Less: Variable cost 6 Contribution 7 Less: Fixed costsThe result will be as follows: 1 Old units 2 New Units 87600 87100 Reduced sales Present 3026580 3009305 1822080 1204500 $756Requirement 4 Compute the sensitivity of OCF with respect to change in variable cost. Increase variable cost by 10% |-34.55#813 Old cash flows 4 New cashflows 5 Change in cash flows B11 C11 B13-B14 Percentage change in cash flows due 16 to 10% change

Add a comment
Know the answer?
Add Answer to:
We are evaluating a project that costs $924,000, has a four-year life, and has no salvage value. Assume that de...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • We are evaluating a project that costs $1,180,000, has a five-year life, and has no salvage...

    We are evaluating a project that costs $1,180,000, has a five-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 88,100 units per year. Price per unit is $34.80, variable cost per unit is $21.05, and fixed costs are $761,000 per year. The tax rate is 40 percent, and we require a return of 10 percent on this project Calculate the base-case operating cash flow and...

  • We are evaluating a project that costs $1,770,000, has a 6-year life, and has no salvage value. Assume that depreciatio...

    We are evaluating a project that costs $1,770,000, has a 6-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 87,000 units per year. Price per unit is $38.13, variable cost per unit is $23.35, and fixed costs are $824,000 per year. The tax rate is 23 percent, and we require a return of 9 percent on this project. a. Calculate the base-case operating cash flow...

  • We are evaluating a project that costs $1.446,000, has a six-year Me, and has no salvage...

    We are evaluating a project that costs $1.446,000, has a six-year Me, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 88,600 units per year. Price per unit is $35.05, variable cost per unit is $21.30, and fixed costs are $766,000 per year. The tax rate is 30 percent, and we require a return of 11 percent on this project Calculate the base-case operating cash flow and...

  • We are evaluating a project that costs $1,920,000, has a 6-year life, and has no salvage value. Assume that depreciation...

    We are evaluating a project that costs $1,920,000, has a 6-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 94,500 units per year. Price per unit is $38.43, variable cost per unit is $23.60, and fixed costs are $839,000 per year. The tax rate is 23 percent, and we require a return of 10 percent on this project. a. Calculate the base-case operating cash flow...

  • We are evaluating a project that costs $2,100,000, has a 7-year life, and has no salvage value. Assume that deprecia...

    We are evaluating a project that costs $2,100,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 98,600 units per year. Price per unit is $37.79, variable cost per unit is $23.90, and fixed costs are $857,000 per year. The tax rate is 24 percent, and we require a return of 10 percent on this project. a. Calculate the base-case operating cash flow...

  • We are evaluating a project that costs $2,160,000, has a 8-year life, and has no salvage...

    We are evaluating a project that costs $2,160,000, has a 8-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 90,900 units per year. Price per unit is $38.91, variable cost per unit is $24.00, and fixed costs are $863,000 per year. The tax rate is 21 percent, and we require a return of 11 percent on this project. a. Calculate the base-case operating cash flow...

  • We are evaluating a project that costs $1,800,000, has a 6-year life, and has no salvage...

    We are evaluating a project that costs $1,800,000, has a 6-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 87,300 units per year. Price per unit is $38.19, variable cost per unit is $23.40, and fixed costs are $827,000 per year. The tax rate is 24 percent, and we require a return of 9 percent on this project. a. Calculate the base-case operating cash flow...

  • We are evaluating a project that costs $2,130,000, has a 8-year life, and has no salvage...

    We are evaluating a project that costs $2,130,000, has a 8-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 90,600 units per year. Price per unit is $38.85, variable cost per unit is $23.95, and fixed costs are $860,000 per year. The tax rate is 25 percent, and we require a return of 11 percent on this project. 0:45 a. Calculate the base-case operating cash...

  • We are evaluating a project that costs $2,280,000, has a 8-year life, and has no salvage...

    We are evaluating a project that costs $2,280,000, has a 8-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 98,300 units per year. Price per unit is $39.15, variable cost per unit is $24.20, and fixed costs are $875,000 per year. The tax rate is 25 percent, and we require a return of 11 percent on this project. a. Calculate the base-case operating cash flow...

  • We are evaluating a project that costs $1,710,000, has a 6-year life, and has no salvage...

    We are evaluating a project that costs $1,710,000, has a 6-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 86,400 units per year. Price per unit is $38.01, variable cost per unit is $23.25, and fixed costs are $818,000 per year. The tax rate is 21 percent, and we require a return of 9 percent on this project. points Skipped eBook a. Calculate the base-case...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT