Pearl Products Limited
Production Budget
July August September October
Budgeted unit sales 37000 42000 52000 32000
Add: Desired units of ending finished goods inventory 12500 15000 10000 7500
Total needs 49500 57000 62000 39500
Less: Units of beginning finished goods inventory 11250 12500 15000 10000
Required production in units 38250 44500 47000 29500
3
Pearl Products Limited
Direct Materials Budget
July August September Third Quarter
Units of raw materials needed to meet production 114750 133500 141000 389250
Add: Desired units of ending raw materials inventory 66750 70500 44250 44250
Total units of raw materials needed 181500 204000 185250 433500
Less: Units of beginning raw materials inventory 56000 66750 70500 56000
Units of raw materials to be purchased 125500 137250 114750 377500
Workings:
Desired units of ending finished goods inventory
July = 2000+(42000*25%)= 12500
August = 2000+(52000*25%)= 15000
September = 2000+(32000*25%)= 10000
October = 2000+(22000*25%)= 7500
Units of raw materials needed to meet production:
July = 38250*3 = 114750
August = 44500*3 = 133500
September = 47000*3 = 141000
Desired units of ending raw materials inventory:
July = 133500*50% = 66750
August = 141000*50% = 70500
September = 29500*3*50%=44250
Add a comment
Know the answer?
Add Answer to:
show work! thank you! Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (CC) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following Inventory requirements: a. The finished goods Inventory on hand at the end of...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (CC) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic cen...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT