Question

The actual cost of direct labour per hour is​ $13.00. Two standard direct labour hours are allowed per finished good. Du...

The actual cost of direct labour per hour is​ $13.00. Two standard direct labour hours are allowed per finished good. During the current​ period, 2,000 finished goods were produced using​ 3,800 direct labour hours. The direct labour efficiency variance is​ $1,300, favourable. Which one of the following amounts is the standard direct labour rate per hour for the​ period?.

A.

​$6.50

B.

​$10.00

C.

​$13.00

D.

​$26.00

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer : A = $ 6.50

>> Standard Hours = 2 * 2000 = 4000 hours.

>> Labor Efficiency Variance = ( Standard Hours - Actual Hours ) * Standard Price.

>> $ 1300 = ( 4000 - 3800 ) * Standard Price.

>> Standard Price = $ 6.5

Add a comment
Know the answer?
Add Answer to:
The actual cost of direct labour per hour is​ $13.00. Two standard direct labour hours are allowed per finished good. Du...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • If the actual labour hours worked exceed the standard labour hours allowed, what type of variance...

    If the actual labour hours worked exceed the standard labour hours allowed, what type of variance will occur? Multiple Choice Favourable labour efficiency variance. ) Favourable labour rate variance. 0 Unfavourable labour efficiency variance. 0 Unfavourable labour rate variance. The standards for direct labour for a product are 2.5 hours at $8 per hour. Last month, 9,000 units of the product were made, and the labour efficiency variance was $8,000 favourable. What was the actual number of hours worked during...

  • If the actual labour hours worked exceed the standard labour hours allowed, what type of variance...

    If the actual labour hours worked exceed the standard labour hours allowed, what type of variance will occur? Multiple Choice Favourable labour efficiency variance. Favourable labour rate variance. Unfavourable labour efficiency variance. Unfavourable labour rate variance.

  • The standard cost of direct labor per hour is $15.00. Two and one half standard direct...

    The standard cost of direct labor per hour is $15.00. Two and one half standard direct labor hours are allowed per unit of finished goods. During the current period, 80 units were produced using 1,850 direct labor hours. The direct labor rate variance is $1,100 unfavorable. Calculate the actual cost of direct labor per hour. O A. $0.59 O B. $15.00 O C. $23.13 OD. $15.59

  • The actual cost of direct labor per hour is $8.00, and the budgeted cost of direct...

    The actual cost of direct labor per hour is $8.00, and the budgeted cost of direct labor per hoour is $7.50. Three budgeted direct labor hours are allowed for each finished unit. During the current period, 300 finished units were produced using 1,200 direct labor hours. Calculate the direct labor rate variance

  • 6 of 25 The standard cost of direct labor per hour is $14.50. Three standard direct...

    6 of 25 The standard cost of direct labor per hour is $14.50. Three standard direct labor hours are alloued per unit of finished goods. During the current period, 50 units were produced using 1,450 direct labor hours. The direct labor rate variance is $1,900 unfavorable. Calculate the actual cost of direct labor per hour. O 514.50 O $1.31 O S15.81 Three standard direct la unit of fin period, so 450 drect hours. The S29.00 riance is s Calculate

  • The following data for a pottery company pertain to the production of 2,000 clay pots during...

    The following data for a pottery company pertain to the production of 2,000 clay pots during July. Direct Materials (all materials purchased were used) Standard cost: $6.00 per kilogram of clay Total actual cost: $11,200 Standard cost allowed for units produced was $12,000 Materials efficiency variance was $240 unfavourable Direct Manufacturing Labour: Standard cost is 2 pots per hour at $24.00 per hour Actual cost per hour was $24.50 Actual labour was 972 hours What is the direct manufacturing labour...

  • answere 17 to 20 The following labour standards have been established for a particular product: Standard...

    answere 17 to 20 The following labour standards have been established for a particular product: Standard labour hours per unit of output Standard labour rate 7.5 hours $15.25 per hour The following data pertain to operations concerning the product for the last month: Actual hours worked Actual total labour cost Actual output 9,600 hours $144,480 1,200 units 17) What was the labour rate variance for the month? a) $240 favourable. b) $240 unfavourable. c) $1,920 favourable. d) $1,920 unfavourable. 18)...

  • What was actual direct labor rate per hour? (AP) Standard direct labor hours for units produced...

    What was actual direct labor rate per hour? (AP) Standard direct labor hours for units produced (SQ) Actual direct labor hours worked (AQ) Direct labor efficiency variance, favorable (F) Total payroll 5,200 5,050 $ 9,750 $353,500

  • Mark: 19 (1 point for each question) 1) The unemployment rate is high in the city...

    Mark: 19 (1 point for each question) 1) The unemployment rate is high in the city in which a company has a factory. The company finds that they are able to pay new employees a lower wage per hour than when the unemployment rate was lower a year ago. Which variance is directly impacted? A) Materials price variance B) Materials efficiency variance C) Labour price variance D) Labour efficiency variance 2) Thomas Corporation produces stopwatches. According to company standards, it...

  • The records of Norton, Inc. show the following for July: Standard labor-hours allowed per unit of...

    The records of Norton, Inc. show the following for July: Standard labor-hours allowed per unit of output 1.8 Standard variable overhead rate per standard direct labor-hour $ 33 Good units produced 60,000 Actual direct labor-hours worked 109,000 Actual total direct labor $ 4,791,000 Direct labor efficiency variance $ 43,000 U Actual variable overhead $ 3,401,000 Required: Compute the direct labor and variable overhead price and efficiency variances.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT