Direct labor rate variance | ||||||
(Actual price - standard price)*actual hrs | ||||||
(x - 15)*1,850 = | 1,100U | |||||
1850x - | 27750 | = | 1,100 | |||
x | = | (27750+1100)/1850 | ||||
15.59459 | ||||||
answer) | option d | |||||
$15.59 | ||||||
The standard cost of direct labor per hour is $15.00. Two and one half standard direct...
6 of 25 The standard cost of direct labor per hour is $14.50. Three standard direct labor hours are alloued per unit of finished goods. During the current period, 50 units were produced using 1,450 direct labor hours. The direct labor rate variance is $1,900 unfavorable. Calculate the actual cost of direct labor per hour. O 514.50 O $1.31 O S15.81 Three standard direct la unit of fin period, so 450 drect hours. The S29.00 riance is s Calculate
The actual cost of direct labor per hour is $8.00, and the budgeted cost of direct labor per hoour is $7.50. Three budgeted direct labor hours are allowed for each finished unit. During the current period, 300 finished units were produced using 1,200 direct labor hours. Calculate the direct labor rate variance
The actual cost of direct labour per hour is $13.00. Two standard direct labour hours are allowed per finished good. During the current period, 2,000 finished goods were produced using 3,800 direct labour hours. The direct labour efficiency variance is $1,300, favourable. Which one of the following amounts is the standard direct labour rate per hour for the period?. A. $6.50 B. $10.00 C. $13.00 D. $26.00
The standard direct labor cost per unit for a company was $21 (= $14 per hour * 1.5 hours per unit). During the period, actual direct labor costs amounted to $136.500, 9.600 labor-hours were worked, and 5.600 units were produced. Required: Compute the direct labor price and efficiency variances for the period. (Indicate the effect of each varlance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select elther option.) Price variance Efficiency...
Harrangue Company's standard variable overhead rate is $6 per direct labor hour, and each unit requires 2 standard direct labor hours. During March, Harry recorded 6,000 actual direct labor hours, $37,000 actual variable overhead costs, and 2,900 units of product manufactured. What is the variable overhead efficiency variance for March for Harrangue? a.$2,200 (U) b.$1,200 (U) c.$600 (U) d.$2,200 (F) Synergy Manufacturing Company has a normal monthly activity of 7,500 units. Standard factory overhead rates are based on a normal...
The standard cost of product 5252 includes 1.90 hours of direct labor at $11.20 per hour. The predetermined overhead rate is $22.00 per direct labor hour. During July, the company incurred 4,000 hours of direct labor at an average rate of $11.40 per hour and $82,200 of manufacturing overhead costs. It produced 2,000 units. (a) Compute the total, price, and quantity variances for labor. Total labor variance $ Unfavorable or Favorable Labor price variance $ Unfavorable or Favorable Labor quantity...
4 The standard direct labor cost per unit for a company was $24 (= $16 per hour x 1.5 hours per unit). During the period, actual direct labor costs amounted to $157,400, 9,700 labor-hours were worked, and 5,700 units were produced. 4 Required: Compute the direct labor price and efficiency variances for the period. (Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select either option.) points...
A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22.000 hours at a total labor cost of $269,500. What is the total labor cost variance? Ο $2,000 unfavorable Ο $3,000 unfavorable Ο $5,500 unfavorable Ο $8,000 unfavorable. Ο ( 59.000 unfavorable. Georgia, Inc. has collected the following data on one of its products. The direct materials quantity variance is: Direct materials standard (4...
A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual units of product are as follows: Standard Costs Direct materials 2,240 kilograms @$8.60 Actual Costs Direct materials 2,300 kilograms The direct materials quantity variance is? Choose the correct answer below $413 favorable $516 unfavorable $516 favorable $413 unfavorable B. The following data relate to direct labor costs for the current period: Standard costs 7,200 hours at $11.30 Actual costs 6,400 hours at $10.80 What...
Flapjack Corporation had 7,921 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 984 units were actually produced. Labor standards were 7.4 hours per completed unit at a standard rate of $12.77 per hour. The direct labor rate variance is $6,099.17 unfavorable $6,099.17 favorable $8,177.70 unfavorable $8,177.70 favorable