Time line | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | |||
Cost of new machine | -725000 | ||||||||||
Initial working capital | -63000 | ||||||||||
=Initial Investment outlay | -788000 | ||||||||||
100.00% | |||||||||||
Savings | 211000 | 211000 | 211000 | 211000 | 211000 | 211000 | 211000 | ||||
-Depreciation | Cost of equipment/no. of years | -103571.429 | -103571.429 | -103571.429 | -103571.4 | -103571.4 | -103571.4 | -103571.429 | 1.164E-10 | =Salvage Value | |
=Pretax cash flows | 107428.5714 | 107428.5714 | 107428.5714 | 107428.57 | 107428.57 | 107428.57 | 107428.5714 | ||||
-taxes | =(Pretax cash flows)*(1-tax) | 81645.71429 | 81645.71429 | 81645.71429 | 81645.714 | 81645.714 | 81645.714 | 81645.71429 | |||
+Depreciation | 103571.4286 | 103571.4286 | 103571.4286 | 103571.43 | 103571.43 | 103571.43 | 103571.4286 | ||||
=after tax operating cash flow | 185217.1429 | 185217.1429 | 185217.1429 | 185217.14 | 185217.14 | 185217.14 | 185217.1429 | ||||
reversal of working capital | 63000 | ||||||||||
+Proceeds from sale of equipment after tax | =selling price* ( 1 -tax rate) | 75240 | |||||||||
+Tax shield on salvage book value | =Salvage value * tax rate | 2.79397E-11 | |||||||||
=Terminal year after tax cash flows | 138240 | ||||||||||
Total Cash flow for the period | -788000 | 185217.1429 | 185217.1429 | 185217.1429 | 185217.14 | 185217.14 | 185217.14 | 323457.1429 | |||
Discount factor= | (1+discount rate)^corresponding period | 1 | 1.1 | 1.21 | 1.331 | 1.4641 | 1.61051 | 1.771561 | 1.9487171 | ||
Discounted CF= | Cashflow/discount factor | -788000 | 168379.2208 | 153072.0189 | 139156.3808 | 126505.8 | 115005.27 | 104550.25 | 165984.6588 | ||
NPV= | Sum of discounted CF= | 184653.60 |
Kolby's Korndogs is looking at a new sausage system with an installed cost of $725,000. This cost will be depreciated s...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $725,000. The asset qualifies for 100 percent bonus depreciation and can be scrapped for $99,000 at the end of the project's 5-year life. The sausage system will save the firm $211,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $63,000. If the tax rate is 24 percent and the discount rate is 10 percent, what is...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $725,000. This cost will be depreciated straight-line to zero over the project’s 7-year life, at the end of which the sausage system can be scrapped for $99,000. The sausage system will save the firm $211,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $63,000. If the tax rate is 24 percent and the discount rate is...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $725,000. This cost will be depreciated straight-line to zero over the project’s 7-year life, at the end of which the sausage system can be scrapped for $99,000. The sausage system will save the firm $211,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $63,000. If the tax rate is 24 percent and the discount rate is...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $655,000. This cost will be depreciated straightline to zero over the project's five-year life, at the end of which the sausage system can be scrapped for $85,000. The sausage system will save the firm $183,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $35,000. If the tax rate is 22 percent and the discount rate is...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $730,00o. This cost will be depreciated straight-line to zero over the project's 7-year life, at the end of which the sausage system can be scrapped for $100,000. The sausage system will save the firm $213,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $65,000. If the tax rate is 25 percent and the discount rate is...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $750,000. This cost will be depreciated straight-line to zero over the project's 7-year life, at the end of which the sausage system can be scrapped for $104,000. The sausage system will save the firm $221,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $73,000. If the tax rate is 24 percent and the discount rate is...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $735,000. This cost will be depreciated straight-line to zero over the project's five-year life, at the end of which the sausage system can be scrapped for $105,000. The sausage system will save the firm $204,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $35,000. If the tax rate is 34 percent and the discount rate is...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $800,000. This cost will be depreciated straight-line to zero over the project's five- year life, at the end of which the sausage system can be scrapped for $95,000. The sausage system will save the firm $150,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $45,000. If the tax rate is 35 percent and the discount rate...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $720,000. The asset qualifies for 100 percent bonus depreciation and can be scrapped for $98.000 at the end of the project's 5-year life. The sausage system will save the firm $209,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $61,000. If the tax rate is 23 percent and the discount rate is 9 percent, what is...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $670,000 The asset qualities for 100 percent bonus depreciation and can be scrapped for $88.000 at the end of the project's 5-year life. The sausage system will save the firm $213,000 per year in pretax operating costs and the system requires an initial investment in net working capital of $41.000. If the tax rate is 23 percent and the discount rate is 11 percent, what is...