Production Budget | ||||||
July | august | September | October | |||
Expected sale units | 35,000 | 40,000 | 50,000 | 30,000 | ||
Add:ending inventory | 11000 | 13000 | 9000 | 7000 | ||
total needs | 46,000 | 53,000 | 59,000 | 37,000 | ||
less opening inventory | 10,000 | 11,000 | 13,000 | 9,000 | ||
total production required | 36,000 | 42,000 | 46,000 | 28,000 | ||
Direct materials budget | ||||||
July | august | September | total | |||
total production required | 36,000 | 42,000 | 46,000 | 124,000 | ||
cubic centimeters required per unit | 3 | 3 | 3 | 3 | ||
units of raw materials needed | 108000 | 126000 | 138000 | 372000 | ||
ending inventory | 63000 | 69000 | 42,000 | 42,000 | ||
total materials required | 171000 | 195000 | 180000 | 414000 | ||
less opening inventory | 54,000 | 63,000 | 69,000 | 108,000 | ||
total materials required | 117,000 | 132,000 | 111,000 | 306,000 | ||
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cub...
pearl products Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimeters (CC) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following Inventory requirements: a. The finished goods inventory on hand at the end...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: A. The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimeters (CC) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimeters (CC) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimeters (CC) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each month...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following Inventory requirements: a. The finished goods Inventory on hand at the end of...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...