Question

Optimal Obj. Value 48,450 Z = Reduced Cost Variable Value 25 0 X1 425 10 X2 150 0 X3 0 -45 X4 Slack and Surplus Dual Value Co

Use Computer Output 4. If you could increase the right hand side of one constraint by one unit, which one would you choose?

constraint 1

constraint 4

constraint 2

constraint 3

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans - Constraint 3

Reason = It has the highest dual value. So, with one unit increase, the objective function value will increase by 60

Add a comment
Know the answer?
Add Answer to:
Use Computer Output 4. If you could increase the right hand side of one constraint by one unit, which one would you cho...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT