Bristol Fabricators, Inc., produces air purifiers in batches. To manufacture a batch of the purifiers, Bristol Fabricators, I

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Production volume variance

= Actual - Budgeted

= (36,700/16,200)*15,000 - 36,700

= 33,981 - 36,700

= 2719 Favourable

​​​​​Option A is the answer

Add a comment
Know the answer?
Add Answer to:
Bristol Fabricators, Inc., produces air purifiers in batches. To manufacture a batch of the purifiers, Bristol...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Raposa, Inc., produces a special line of plastic toy racing cars.​ Raposa, Inc., produces the cars...

    Raposa, Inc., produces a special line of plastic toy racing cars.​ Raposa, Inc., produces the cars in batches. To manufacture a batch of the​ cars, Raposa,​ Inc., must set up the machines and molds. Setup costs are batchminus−level costs because they are associated with batches rather than individual units of products. A separate Setup Department is responsible for setting up machines and molds for different styles of car. Setup overhead costs consist of some costs that are variable and some...

  • Question 3 Magic Corporation (MC) produces special carbon fibre basketball hoops. These hoops are produced in...

    Question 3 Magic Corporation (MC) produces special carbon fibre basketball hoops. These hoops are produced in batches, where machines and moulds have to be set up for every batch Setup costs are batch-level costs because they are associated with batches rather than individual units of products. A separate Setup Department is responsible for setting up machines and moulds Setup overhead costs consist of some costs that are variable and some costs that are fixed with respect to the number of...

  • Bowser Products operates a small plant in New Mexico that produces dog food in batches of...

    Bowser Products operates a small plant in New Mexico that produces dog food in batches of 1,500 pounds. The product sells for $6 per pound. Standard costs for 2018 are: Standard direct labor cost = $15 per hour Standard direct labor hours per batch = 10 hours Standard price of material A = $0.35 per pound Standard pounds of material A per batch = 800 pounds Standard price of material B = $0.55 per pound Standard pounds of material B...

  • Serene Sound produces a high quality audio tape used in the recording industry.  Serene allocates variable overhead...

    Serene Sound produces a high quality audio tape used in the recording industry.  Serene allocates variable overhead to production at a rate of $12 per batch manufactured.  The company’s monthly fixed overhead costs average $72,000.  An average of 500 batches per month is considered normal.  During June, Serene produced 450 batches of audio tape and incurred actual overhead costs of $79,500. 1          Compute the following amounts: a          Total overhead applied to production in June amounted to $__________. b          Total overhead budgeted in June for the 450 batches...

  • Really need questions 6 and 7 answered... 8-37Activity-based costing, batch-level varlance analysis. Rae Steven Publishing Company...

    Really need questions 6 and 7 answered... 8-37Activity-based costing, batch-level varlance analysis. Rae Steven Publishing Company specializes in printing specialty textbooks for a small but profitable college market. Due to the high setup costs for each batch printed, Rae Steven holds the book requests until demand for a book is approximately 520. At that point Rae Steven will schedule the setup and production of the book. For rush orders, Rae Steven will produce smaller batches for an additional charge of...

  • z Cont. Batch costs Number of batches Engineering changes Number of engineering hours Total estimated manufacturing...

    z Cont. Batch costs Number of batches Engineering changes Number of engineering hours Total estimated manufacturing overhead for the year $196,000 $188,950 $3,600,200 Total estimated direct labor hours for the company for the year are 100,250 hours. The company is evaluating whether it should use an activity-based costing system in place of its traditional costing system. Additional information about production needed for the activity-based costing system follows: Zips Dees Total Direct labor hours 61,250 39,000 100,250 Batches 2,350 400 2,750...

  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity i...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 26 setups and 26,000 machine hours to manufacture 6,500 units for the year. Selected data for 2019 follow Budgeted fixed factory overhead: $ 54,600 178,000 Setup cost Other $232,600 $481,000 Total factory overhead cost incurred Variable factory overhead rate: $ 400 $6.00 30,000 34,500 Per setup Per machine hour Total standard machine hours allowed for the units manufactured Machine hours actually worked Actual total number...

  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 34...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 34 setups and 34,000 machine hours to manufacture 8,500 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 85,000 Other 186,000 $ 271,000 Total factory overhead cost incurred $ 485,000 Variable factory overhead rate: Per setup $ 400 Per machine hour $ 5.00 Total standard machine hours allowed for the units manufactured 27,000 hours Machine hours actually worked...

  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 40...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 40 setups and 40,000 machine hours to manufacture 8,000 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 76,800 Other 230,000 $ 306,800 Total factory overhead cost incurred $ 484,000 Variable factory overhead rate: Per setup $ 550 Per machine hour $ 4.00 Total standard machine hours allowed for the units manufactured 28,000 hours Machine hours actually worked...

  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 20...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 20 setups and 20,000 machine hours to manufacture 5,000 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 57,000 Other 184,000 $ 241,000 Total factory overhead cost incurred $ 491,000 Variable factory overhead rate: Per setup $ 800 Per machine hour $ 6.00 Total standard machine hours allowed for the units manufactured 24,000 hours Machine hours actually worked...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT