Net Present Value = PV of inflows - PV of outflows

and if NPV turns out to be positive, the project is viable.

Cumulative Discounting factor @ 14% for 10 years = 5.2161

PV OF OUTFLOW :

Initial Investment = Cost of acquiring land + Cost of construction of runway + cost of extended perimeter fence + cost of runway lights + cost of new snowplow

Initial Investment = $81,000 + $275,000 + $49,875 + $44,000 +$175,000

= $624,875

Annual Outflow = Annual cost of maintaining highway = additional operation cost of snowplow

= $22,000 + $15,500

= 37,500

PV of Annual Outflows = Annual Outflow * Cumulative discounting factor

= $37,500 * 5.2161

=$195,603.75

PV of Net Outflows = Initial cost + PV of annual outflows

= $624,875 + $195,603.75

= $820,478.75

PV OF INFLOW :

Initial Inflow = Sale proceeds from old snowplow

= $17,500

Annual Incremental revenue for landing fees = $55,000

Annual additional tax revenue for country = $90,000

Annual Inflows = Increment landing revenue + additional tax revenue

   = $55,000 + $90,000

= $145,000

PV of Annual Inflows = Annual Inflow * Cumulative Discounting Factor

= $145,000 * 5.2161

= $756,334.50

PV of Inflows = Initial inflow + PV of Annual Inflows

= $17,500 + $756.334.50

= $773,834.50

NPV of project = PF of Inflows - PV of Outflows

= $773,834.50 - $820,478.75

= -$46,644.25

The Country Board of Representatives should not approve the runway considering the runway.

3 (a) : The data used in analysis that is likely to be most uncertain is the increment in the annual revenue of the country in the form of landing charges and additional tax revenues.

3 (b) : The data used in analysis that is likely to be least uncertain is the Total Initial cost for Construction of Runway.

Add a comment
Know the answer?
Add Answer to:
Washington county’s board Required information The following information applies to the questions displayed below.] Washington County's...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.] Washington County’s Board of Representatives...

    Required information [The following information applies to the questions displayed below.] Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 61,500 Cost of runway construction 310,000...

  • Required information [The following information applies to the questions displayed below.] Washington County’s Board of Representatives...

    Required information [The following information applies to the questions displayed below.] Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 88,500 Cost of runway construction 300,000...

  • 2 Requiredi (The following information applies to the questions displayed belowj Washington County's Board of Representatives...

    2 Requiredi (The following information applies to the questions displayed belowj Washington County's Board of Representatives is considering the construction of a longer runway at the county airport Currently, the airport can h airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below Part 2 of 2 only private aircraft and small commuter jets. A new, long runway would enable the 10 points Cost of runway construction 238,000 16,967 36,000 18,e00...

  • Required Information [The following information apples to the questions displayed below. Washington County's Board of Representatives...

    Required Information [The following information apples to the questions displayed below. Washington County's Board of Representatives Is considering the construction of a longer runway at the county alrport. Currently, the alrport can handle only private alrcraft and small commuter jets. A new, long runway would enable the airport to handle the midsize Jets used on many domestic flights. Data pertinent to the board's decision appear below Cost of acquiring additional land for runway Cost of runway construction Cost of extending...

  • Washington County's Board of Representatives is considering the construction of a longer runway at the county...

    Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of runway lights Annual cost of maintaining new...

  • Required information The following information applies to the questions displayed below] Washington County's Board of Representatives...

    Required information The following information applies to the questions displayed below] Washington County's Board of Representatives is considering the construction of a longer runway at the county airport Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below Cost of runway construction 230,eee 16,967 36,000 18,000 35,000 Cost of extending perimeter fence...

  • Washington County's Board of Representatives is considering the construction of a longer runway at the county...

    Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A. new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of runway lights Annual cost of maintaining new...

  • Washington County's Board of Representatives is considering the construction of a longer runway at the county...

    Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of runway lights Annual cost of maintaining new...

  • Washington County's Board of Representatives is considering the construction of a longer runway at the county...

    Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of runway lights Annual cost of maintaining new...

  • Washington County's Board of Representatives is considering the construction of a longer runway at the county...

    Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. $ 67,500 260,000 10,804 35,000 17,500 32,500 Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT