Net Present Value = PV of inflows - PV of outflows
and if NPV turns out to be positive, the project is viable.
Cumulative Discounting factor @ 14% for 10 years = 5.2161
PV OF OUTFLOW :
Initial Investment = Cost of acquiring land + Cost of construction of runway + cost of extended perimeter fence + cost of runway lights + cost of new snowplow
Initial Investment = $81,000 + $275,000 + $49,875 + $44,000 +$175,000
= $624,875
Annual Outflow = Annual cost of maintaining highway = additional operation cost of snowplow
= $22,000 + $15,500
= 37,500
PV of Annual Outflows = Annual Outflow * Cumulative discounting factor
= $37,500 * 5.2161
=$195,603.75
PV of Net Outflows = Initial cost + PV of annual outflows
= $624,875 + $195,603.75
= $820,478.75
PV OF INFLOW :
Initial Inflow = Sale proceeds from old snowplow
= $17,500
Annual Incremental revenue for landing fees = $55,000
Annual additional tax revenue for country = $90,000
Annual Inflows = Increment landing revenue + additional tax revenue
= $55,000 + $90,000
= $145,000
PV of Annual Inflows = Annual Inflow * Cumulative Discounting Factor
= $145,000 * 5.2161
= $756,334.50
PV of Inflows = Initial inflow + PV of Annual Inflows
= $17,500 + $756.334.50
= $773,834.50
NPV of project = PF of Inflows - PV of Outflows
= $773,834.50 - $820,478.75
= -$46,644.25
The Country Board of Representatives should not approve the runway considering the runway.
3 (a) : The data used in analysis that is likely to be most uncertain is the increment in the annual revenue of the country in the form of landing charges and additional tax revenues.
3 (b) : The data used in analysis that is likely to be least uncertain is the Total Initial cost for Construction of Runway.
Washington county’s board Required information The following information applies to the questions displayed below.] Washington County's...
Required information [The following information applies to the questions displayed below.] Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 61,500 Cost of runway construction 310,000...
Required information [The following information applies to the questions displayed below.] Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 88,500 Cost of runway construction 300,000...
2 Requiredi (The following information applies to the questions displayed belowj Washington County's Board of Representatives is considering the construction of a longer runway at the county airport Currently, the airport can h airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below Part 2 of 2 only private aircraft and small commuter jets. A new, long runway would enable the 10 points Cost of runway construction 238,000 16,967 36,000 18,e00...
Required Information [The following information apples to the questions displayed below. Washington County's Board of Representatives Is considering the construction of a longer runway at the county alrport. Currently, the alrport can handle only private alrcraft and small commuter jets. A new, long runway would enable the airport to handle the midsize Jets used on many domestic flights. Data pertinent to the board's decision appear below Cost of acquiring additional land for runway Cost of runway construction Cost of extending...
Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of runway lights Annual cost of maintaining new...
Required information The following information applies to the questions displayed below] Washington County's Board of Representatives is considering the construction of a longer runway at the county airport Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below Cost of runway construction 230,eee 16,967 36,000 18,000 35,000 Cost of extending perimeter fence...
Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A. new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of runway lights Annual cost of maintaining new...
Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of runway lights Annual cost of maintaining new...
Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of runway lights Annual cost of maintaining new...
Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. $ 67,500 260,000 10,804 35,000 17,500 32,500 Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of...