1.
Compute the initial cost as follows:
Amount | |
Cost of acquiring additional land for runway | $67,500 |
+ Cost of runway construction | $260,000 |
+ Cost of extending perimeter fence | $10,804 |
+ Cost of runway lights | $35,000 |
+ Cost of new snowplow | $130,000 |
- Sale of old snowplow | ($13,000) |
New initial outlay for long runway | $490,304 |
________________________________________________________
2.
Compute the annual net cost or benefit from the runway as follows:
Amount | |
Annual incremental revenue from landing fees | $32,500 |
Add: Additional tax revenue for the county | $88,000 |
Less: Annual cost of maintaining new runway | ($17,500) |
Less: Extra annual operating cost of new plow | ($9,000) |
Annual benefit of the runway | $94,000 |
_____________________________________________________________________
3.
Compute IRR of the project as follows using the spreadsheet as follows:
Working as follows:
Washington County's Board of Representatives is considering the construction of a longer runway at the county...
Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of runway lights Annual cost of maintaining new...
Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of runway lights Annual cost of maintaining new...
Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of runway lights Annual cost of maintaining new...
Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of runway lights Annual cost of maintaining new...
Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A. new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction Cost of extending perimeter fence Cost of runway lights Annual cost of maintaining new...
2 Requiredi (The following information applies to the questions displayed belowj Washington County's Board of Representatives is considering the construction of a longer runway at the county airport Currently, the airport can h airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below Part 2 of 2 only private aircraft and small commuter jets. A new, long runway would enable the 10 points Cost of runway construction 238,000 16,967 36,000 18,e00...
Required Information [The following information apples to the questions displayed below. Washington County's Board of Representatives Is considering the construction of a longer runway at the county alrport. Currently, the alrport can handle only private alrcraft and small commuter jets. A new, long runway would enable the airport to handle the midsize Jets used on many domestic flights. Data pertinent to the board's decision appear below Cost of acquiring additional land for runway Cost of runway construction Cost of extending...
Washington county’s board Required information The following information applies to the questions displayed below.] Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new. long runway would enable the airport to handle the midsize jets used on many domestic filights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction...
Required Informetion (The following information apples to the questions displayed below Washington County's Board of Representatives is considering the construction of a longer runway at the county airport Currently, the airport can handle only private aircraft and small commuter jets. A new. long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below cost of acquiring additional land for runway Cost of ruway construction Cost of extending...
Required information The following information applies to the questions displayed below] Washington County's Board of Representatives is considering the construction of a longer runway at the county airport Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below Cost of runway construction 230,eee 16,967 36,000 18,000 35,000 Cost of extending perimeter fence...