Question

Read the scenario. You are the financial manager of a firm that is contemplating investing $25,000...

Read the scenario.

You are the financial manager of a firm that is contemplating investing $25,000 in a new project that you expect will generate cash flows of $10,000 per year for five years and then $15,000 per year for another two years. At the end of seven years you expect to sell the project's assets for $50,000. You believe that you should earn at least 14% to compensate the shareholders for the project's risk.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Amount to be paid is NPV of Project,

So,

NPV = -25,000 + 10,000/(1.14) + 10,000/(1.14)2 + 10,000/(1.14)3 + 10,000/(1.14)4 + 10,000/(1.14)5 + 15,000/(1.14)6 + 65,000/(1.14)7

NPV = $42,141

Add a comment
Know the answer?
Add Answer to:
Read the scenario. You are the financial manager of a firm that is contemplating investing $25,000...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Read the scenario. You are the financial manager of a firm that is contemplating investing $25,000...

    Read the scenario. You are the financial manager of a firm that is contemplating investing $25,000 in a new project that you expect will generate cash flows of $10,000 per year for five years and then $15,000 per year for another two years. At the end of seven years you expect to sell the project's assets for $50,000. You believe that you should earn at least 14% to compensate the shareholders for the project's risk. What is the Profitability Index?

  • Read the scenario. You are the financial manager of a firm that is contemplating investing $25,000...

    Read the scenario. You are the financial manager of a firm that is contemplating investing $25,000 in a new project that you expect will generate cash flows of $10,000 per year for five years and then $15,000 per year for another two years. At the end of seven years you expect to sell the project's assets for $50,000. You believe that you should earn at least 14% to compensate the shareholders for the project's risk. Explain the process for evaluating...

  • Read the scenario. You are the financial manager of a firm that is contemplating investing $25,000 in a new project that...

    Read the scenario. You are the financial manager of a firm that is contemplating investing $25,000 in a new project that you expect will generate cash flows of $10,000 per year for five years and then $15,000 per year for another two years. At the end of seven years you expect to sell the project's assets for $50,000. You believe that you should earn at least 14% to compensate the shareholders for the project's risk. What is the most that...

  • Read the scenario. You are the financial manager of a firm that is contemplating investing $25,000 in a new project that...

    Read the scenario. You are the financial manager of a firm that is contemplating investing $25,000 in a new project that you expect will generate cash flows of $10,000 per year for five years and then $15,000 per year for another two years. At the end of seven years you expect to sell the project's assets for $50,000. You believe that you should earn at least 14% to compensate the shareholders for the project's risk. Is this project consistent with...

  • Read the scenario. You are the financial manager of a firm that is contemplating investing $25,000...

    Read the scenario. You are the financial manager of a firm that is contemplating investing $25,000 in a new project that you expect will generate cash flows of $10,000 per year for five years and then $15,000 per year for another two years. At the end of seven years you expect to sell the project's assets for $50,000. You believe that you should earn at least 14% to compensate the shareholders for the project's risk. Answer the following questions: Explain...

  • Read the scenario. You are the financial manager of a firm that is contemplating investing in...

    Read the scenario. You are the financial manager of a firm that is contemplating investing in a new project that you expect will generate cash flows of $10,000 per year for five years and then $15,000 per year for another two years. At the end of seven years you expect to sell the project's assets for $50,000. You believe that you should earn at least 14% to compensate the shareholders for the project's risk. Answer the questions. Answer the following...

  • A firm is considering a project that will generate perpertual after-tax cash flows of 25,000 per...

    A firm is considering a project that will generate perpertual after-tax cash flows of 25,000 per year beginning next year. The project has the same risk as the firm's overall operations. Equity cost 15%and debt cost 6% on an after-tax basis. The firm's D/E ratio is 1.2. What is the most the firm can pay for the project and still earn its required return?

  • You must analyze a potential new product-a caulking compound that Cory Materials' R&D people developed for use in the residential construction industry. Cory's marketing manager thinks t...

    You must analyze a potential new product-a caulking compound that Cory Materials' R&D people developed for use in the residential construction industry. Cory's marketing manager thinks they can sell 115,000 tubes per year at a price of $3.25 each for 3 years, after which the product will be obsolete. The required equipment would cost $150,000, plus another $25,000 for shipping and installation. Current assets (receivables and inventories) would increase by $35,000, while current liabilities (accounts payable and accruals) would rise...

  • Q1. Inatech is contemplating two different projects and decides to perform a financial analysis to determine...

    Q1. Inatech is contemplating two different projects and decides to perform a financial analysis to determine which is more financially lucrative. Project A and B have the cash flows as shown and Inatech uses a required rate of return of 10% and an inflation rate of 4%. Compute the payback in years and the net present value for both projects and offer advice as to the best course of action. (4 marks) Yearl A B 0 -$100.000|-$400,000 $20,000 $75,000 2....

  • You have spent $25,000 researching a location for a new restaurant. The restaurant requires an im...

    You have spent $25,000 researching a location for a new restaurant. The restaurant requires an immediate capital expenditure of $300,000, which can be depreciated over 30 years. You also expect to incur an immediate working capital expenditure of $100,000, which can be recovered at the end of the project, in 30 years. You expect the new restaurant to generate $150,000 per year in annual revenues for the life of the project and have annual operating costs of $75,000. After 30...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT