During August, Leming Inc. worked on two jobs. Data relating to these two jobs follow:
Job 64 |
Job 65 |
|
Units in each order | 50 | 80 |
Units sold | 50 | -- |
Materials requisitioned | $3,560 | $785 |
Direct labor hours | 410 | 583 |
Direct labor cost | $6,720 | $9,328 |
Overhead is assigned on the basis of direct labor hours at a rate of $11. During August, Job 64 was completed and transferred to Finished Goods. Job 65 was the only unfinished job at the end of the month.
Required: | |
1. | Calculate the per-unit cost of Job 64. |
2. | Compute the ending balance in the work-in-process account. |
3. | Prepare the Aug. 31 journal entries reflecting the completion and sale on account of Job 64. The selling price is 175% of cost. Refer to the chart of accounts for account titles. Round all journal entry amounts to the nearest dollar. |
1. Calculate the per-unit cost of Job 64.
The per-unit cost of Job 64 is .
2. Compute the ending balance in the work-in-process account.
The ending balance in the work-in-process account is .
3. Prepare the Aug. 31 journal entries reflecting the completion and sale on account of Job 64. The selling price is 175% of cost. Refer to the Chart of Accounts for the exact wording of account titles. Round all journal entry amounts to the nearest dollar.
PAGE 1
GENERAL JOURNAL
DATE | ACCOUNT | POST. REF. | DEBIT | CREDIT | |
---|---|---|---|---|---|
1 |
|||||
2 |
|||||
3 |
|||||
4 |
|||||
5 |
|||||
6 |
Answer:
1) Per unit cost of job 64 = (3,560+6,720+(410*11))/50= $295.8 per unit |
2) Ending work in process account = (785+9,328+(583*11)) = $16,526 |
3) GENERAL JOURNAL | |||
Date | Account and explanation | debit($) | credit($) |
Aug. 31 | Finished goods($295.8*50) | 14,790 | |
Work in process | 14,790 | ||
(To record completion of Job 64) | |||
Aug. 31 | Account Receivable (14,790*175%) | 25,882.50 | |
Sales revenue | 25,882.50 | ||
(To record sales of Job 64) | |||
Aug. 31 | Cost of goods sold | 14,790 | |
Finished goods | 14,790 | ||
(To record cost of goods sold for Job 64) |
During August, Leming Inc. worked on two jobs. Data relating to these two jobs follow: Job...
During March, Aragon Company worked on three jobs. Data relating to these three jobs follow: Job 78 Job 79 Job 80 230 210 210 210 Units in each order Units sold Materials requisitioned Direct labor hours $1,029 $2.289 $1,656 253 231 378 Direct labor cost $ 2,783 $3,234 $3,478 Overhead is assigned on the basis of direct labor hours at a rate of $7.30 per direct labor hour. During March, Jobs 78 and 79 were completed and transferred to Finished...
Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow: Job 78 Job 79 Job 80 Units in each order 270 250 330 Units sold — 250 — Materials requisitioned $1,620 $1,300 $3,729 Direct labor hours 297 275 528 Direct labor cost $2,970 $3,575 $4,224 Overhead is assigned on the basis of direct labor hours at a rate of $7.60 per...
Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow: Job 78 Job 79 Job 80 Units in each order 120 210 280 Units sold — 210 — Materials requisitioned $816 $1,092 $2,800 Direct labor hours 132 231 476 Direct labor cost $1,980 $3,696 $3,903 Overhead is assigned on the basis of direct labor hours at a rate of $9.20 per direct labor hour. During March, Jobs 78 and...
Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow: Job 78 Job 79 Job 80 Units in each order 260 200 200 Units sold 200 Materials requisitioned $1,664 $1,180 $2,140 Direct labor hours 286 220 360 Direct labor cost $4,290 $3,300 $3,096 Overhead is assigned on the basis of direct labor hours at a rate of $8.30 per direct labor hour. During March, Jobs 78 and 79 were...
Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow: Job 78 Job 79 Job 80 Units in each order 110 160 290 Units sold — 160 — Materials requisitioned $770 $720 $3,161 Direct labor hours 121 176 493 Direct labor cost $1,573 $2,816 $4,141 Overhead is assigned on the basis of direct labor hours at a rate of $7.60 per...
Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow: Job 78 Job 79 Job 80 Units in each order 120 210 230 Units sold — 210 — Materials requisitioned $912 $945 $2,553 Direct labor hours 132 231 391 Direct labor cost $1,584 $3,927 $3,206 Overhead is assigned on the basis of direct labor hours at a rate of $7.50 per direct labor hour. During March, Jobs 78 and...
Unit Cost, Ending Work-in-Process Inventory, Journal Entries During August, Skyler Company worked on three jobs. Data relating to these three jobs follow: Job 39 Job 40 Job 41 Units in each order 60 100 80 Units sold — 100 — Materials requisitioned $700 $690 $800 Direct labor hours 360 400 200 Direct labor cost $1,944 $2,440 $1,220 Overhead is assigned on the basis of direct labor hours at a rate of $2.20 per direct labor hour. During August, Jobs 39...
Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow: Job 78 Job 79 Job 80 Units in each order 200 180 220 Units sold — 180 — Materials requisitioned $1,560 $990 $2,400 Direct labor hours 220 200 400 Direct labor cost $3,000 $3,000 $3,300 Overhead is assigned on the basis of direct labor hours at a rate of $8.40 per...
Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow: Job 78 Job 79 Job 80 Units in each order 220 150 290 Units sold — 150 — Materials requisitioned $1,364 $795 $3,422 Direct labor hours 242 165 464 Direct labor cost $2,420 $2,310 $4,454 Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow: Job 78 Job...
The following account appears in the ledger prior to recognizing the jobs completed in August: Work in Process Balance, August 1 $ 60,000 Direct materials 325,000 Direct labor 462,000 Factory overhead 210,000 Jobs finished during August are summarized as follows: Job 210 $197,800 Job 216 240,000 Job 224 160,000 Job 230 364,000 Required: A. Journalize the entry on Aug. 31 to record the jobs completed. Refer to the Chart of Accounts for exact wording of account titles. B. Determine the...