Question

nvest in Project 1 because it has the higher IRI. Invest in Project 2 because it has the higher NPV 8 I projects below. The cash flows as well as the NPV and IRR t 13 Consider the two projects below 1or the two projec 10 percent. ts are given. For both projects, the required rate of return is Cash Flows Year Project 1 Project 2 4 36 0175 NPV 14.12 19.53 IRR (%) 16.37 15.02 1 2 3 100 36 36 36 -100 0 What discount rate would result in the same NPV for both projects? A A rate between 0.00 percent and 10.00 percent. B A rate between 10.00 percent and 15.02 percent. C A rate between 15.02 percent and 16.37 percent.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Option b is correct

NPV A = NPV B

NPV= C0+ CF1/(1+r)^1 + CF2/(1+r)^2 …………CFn/(1+r)^n

Hence

-100 + 36/(1+r)^1 + 36/(1+r)^2+ 36/(1+r)^3 + 36/(1+r)^4 = -100+ 175/(1+r)^4

36/(1+r)^1 + 36/(1+r)^2+ 36/(1+r)^3 + 36/(1+r)^4 = 175/(1+r)^4

This implies:

PMT = -36, N=4, FV = 175 and we have to find the Rate.

Find I/Y in financial calculator

As 13.16%

Add a comment
Know the answer?
Add Answer to:
nvest in Project 1 because it has the higher IRI. Invest in Project 2 because it...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 8) Project A has an internal rate of return (IRR) of 15 percent. Project B has...

    8) Project A has an internal rate of return (IRR) of 15 percent. Project B has an IRR of 14 percent. Both projects have a required retum of 12 percent. Which of the following statements is MOST correct? A) Project A must have a higher NPV than Project B. B) Both projects have a positive net present value (NPV) C) Project B has a higher profitability index than Project A. D) If the required return were less than 12 percent,...

  • Clifford Company is choosing between two projects. The larger project has an initial cost of $100,000,...

    Clifford Company is choosing between two projects. The larger project has an initial cost of $100,000, annual cash flows of $30,000 for 5 years, and an IRR of 15.24%. The smaller project has an initial cost of $50,000, annual cash flows of $16,000 for 5 years, and an IRR of 16.63%. The projects are equally risky. Which of the following statements is CORRECT? Since the smaller project has the higher IRR, the two projects’ NPV profiles will cross, and the...

  • Project A has an internal rate of return (IRR) of 15 percent. Project B has an...

    Project A has an internal rate of return (IRR) of 15 percent. Project B has an IRR of 14 percent. Both projects have a cost of capital of 12 percent. Which of the following statements is most correct? Question 3 options: Both projects have a positive net present value (NPV). Project A must have a higher NPV than Project B. If the cost of capital were less than 12 percent, Project B would have a higher IRR than Project A....

  • Isaac has analyzed two mutually exclusive projects that have 3-year lives. Project A has an NPV...

    Isaac has analyzed two mutually exclusive projects that have 3-year lives. Project A has an NPV of $81,406, a payback period of 2.48 years, and an IRR of 9.31 percent. Project B has an NPV of $82,909, a payback period of 2.57 years, and an IRR of 9.22 percent. The firm’s cost of capital is 9.15 percent and required payback period is 2.8 years. Isaac must make a recommendation and justify it in 15 words or less. What should his...

  • Your firm is considering two projects with the following cash flows: Cash flows from project B...

    Your firm is considering two projects with the following cash flows: Cash flows from project B (£000) (500) 200 250 170 25 30 Year Cash flows from project A (£000) 0(500) 167 180 160 100 100 4 1. Calculate the ARR and payback rule 2. If the appropriate discount rate is 12%, rank the two projects 3. Which project is preferred if you rank by IRR? 4. Calculate the discount rate (r) for which the NPVs of both projects are...

  • You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has...

    You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has an initial outlay of $10,000, an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an initial outlay of $15,000, an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, and the projects have different lives. If the projects are repeatable, then: You should do both...

  • You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has...

    You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has an initial outlay of $10,000, an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an initial outlay of $15,000, an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, and the projects have different lives. If the projects are repeatable, then: You should do both...

  • #1 Questions a) to e) refer to two projects with the following cash flows: Year Project...

    #1 Questions a) to e) refer to two projects with the following cash flows: Year Project B Project A -$200 -$200 80 100 100 100 a) If the opportunity cost of capital is 10%, which of these projects is worth pursuing? Explain. b) Suppose that you can choose only one of these projects. Which would you choose? The discount rate is still 10%. Justify your reasoning. c) Which project would you choose if the opportunity cost of capital were 16%?...

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Assuming the projects are independent, which one(s) would you recommend? -Select-Only Project M would be accepted because NPV(M) > NPV(N).Only Project N would be accepted because NPV(N) > NPV(M).Both projects would be accepted since both...

  • 5) (15 pts total) Consider the cash flows and Project B Section 2 Problems sider the...

    5) (15 pts total) Consider the cash flows and Project B Section 2 Problems sider the cash flows from two mutually exclusive projects, Project A Year Cash Flow (Proj A) -200 20 120 160 Cash Flow (Proj B) -200 140 100 40 a) (5 pts) Construct NPV profiles for each project and graph them (one graph - both profiles). b) (5 pts) Compute the crossover rate e (5 pts) Briefly explain the conflict that arises between the NPV and the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT