3(b) A City government is planning to build a Light Rail Tunnel in the Central Business District (CBD). The funds have to be borrowed at an interest rate of 12%. For the tunnel to serve its function forever, the following funds will be required. .The construction contractor will require $500 million at beginning of year 1 and another 200 million at the end of year 2 when the construction will end. For routine maintenance, $100,000/year (end of year payment, forever) will be required after the tunnel will be open for service in year 3. . S1 million every 10 years for repairs. These repair bills will be paid as end of year payments. What is the total present worth of the costs of building, maintaining, and repairing the tunnel?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Consider the given problem here the rate of return is given by, “r=12%=0.12”. Now, the building cot is given by “$500 million” at the beginning and “$200 million” at the end of the year 2. So, the present value of the building cost is given by.

=> PV(building) = $500 + $200/1.12^2 = $500 + $200/1.12^2 = 659.438776 million = $659,438,776.

Now, the maintenance cost is given by “$100,000 per year” will be required after the tunnel will be open for the service that is after the year 3. Now, if the cost will require after the year one, => the present value will be “$100,000/0.12”. But here it will require after the “3rd year”, => the present value of maintenance cost is given by.

=> PV(maintenance) = $100,000 /0.12 - $100,000/1.12 - $100,000/1.12^2 = $833,333.3333 - $89,285.7143 - $79,719.3877 = $664,328.23.

Now, the repairing cost is “$1 million every 10 years”. So, the present value will be.

=> PV(Repair) = ($1/1.12^10 + $1/1.12^20 + $1/1.12^30 + $1/1.12^40 + ……..), infinite geometric series.

=> PV(Repair) = $1/1.12^10*(1 + $1/1.12^10 + $1/1.12^20 + ……..).

=> PV(Repair) = $1/1.12^10*[1 /1- ( $1/1.12^10)] = $1/1.12^10*[1.12^10 /1.12^10 - 1].

=> PV(Repair) = $1*[1 /1.12^10 - 1] = $0.474868034 million = $474,868.034.

So, the present worth of the cost of building, maintaining and repairing is given by.

=> Present Worth = $659,438,776 + $664,328 + $474,868 = $660,577,972.

Add a comment
Know the answer?
Add Answer to:
3(b) A City government is planning to build a Light Rail Tunnel in the Central Business...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3(b) A City government is planning to build a Light Rail Tunnel in the Central Business...

    3(b) A City government is planning to build a Light Rail Tunnel in the Central Business District (CBD). The funds have to be borrowed at an interest rate of 12%. For the tunnel to serve its function forever, the following funds will be required. .The construction contractor will require $500 million at beginning of year 1 and another 200 million at the end of year 2 when the construction will end. For routine maintenance, $100,000/year (end of year payment, forever)...

  • 2. A large city uses certain governmental-type funds (General, Special Revenue, Debt Service, and Capital Projects)...

    2. A large city uses certain governmental-type funds (General, Special Revenue, Debt Service, and Capital Projects) and proprietary-type funds (Internal Service and Enterprise). State the fund or funds that would be used to record the following transactions 1. The city sent property tax bills to all taxpayers. Most of the taxes were to be used to finance the day-to-day activities of the city. A portion of the tax, however, was levied for the specific purpose of financing operations of the...

  • A major city in Eastern Canada is planning to build a new wastewater treatment plant to...

    A major city in Eastern Canada is planning to build a new wastewater treatment plant to accommodate the increasing water consumption of the city, Plant construction will start in 2018 and is going to take five years at a cost of $30 million per year. After construction is completed, the cost of operation, maintenance is expected to be $2 million for the first year, and to increase by 1% per year thereafter. The salvage/scrap value of the wastewater treatment plant...

  • THIS PROBLEM IS ABOUT ACCOUNTING FOR GOVERNMENTAL AND NONPROFIT ORGANIZATIONS! The City of Duluth has been...

    THIS PROBLEM IS ABOUT ACCOUNTING FOR GOVERNMENTAL AND NONPROFIT ORGANIZATIONS! The City of Duluth has been authorized to build a new library estimated to cost $8,000,000. A bond issue is to provide the funds to construct the building. The attached transactions took place during the fiscal year ending June 30, 20X3 that related to the capital projects fund which was established to account for the construction of the new library. The fund does not enter the budget in the accounting...

  • What rates should be charged? Downtown Parking Authority In January a meeting was held in the office of the mayor of Oa...

    What rates should be charged? Downtown Parking Authority In January a meeting was held in the office of the mayor of Oakmont to discuss a unicipal parking facility. The participants included the mayor, the traffic proposca the administrator of Oakmont's Downtown Parking Authority, the city planner, and the finance director. The purpose of the meeting was to consider a report Richard Stockton, executive assistant to the Parking Authority's administrator, concerning estimated costs and revenues for the proposed facility. Mr. Stockton's...

  • What additional information, if any, should be obtained before making a final decision? Downtown Parking Authority In J...

    What additional information, if any, should be obtained before making a final decision? Downtown Parking Authority In January a meeting was held in the office of the mayor of Oakmont to discuss a unicipal parking facility. The participants included the mayor, the traffic proposca the administrator of Oakmont's Downtown Parking Authority, the city planner, and the finance director. The purpose of the meeting was to consider a report Richard Stockton, executive assistant to the Parking Authority's administrator, concerning estimated costs...

  • Playgrounds and Performance: Results Management at KaBOOM! (A) We do this work because we want to...

    Playgrounds and Performance: Results Management at KaBOOM! (A) We do this work because we want to make a difference in the world; how can we go further faster? - Darell Hammond, CEO and co-founder, KaBOOM! Darell Hammond stepped onto the elementary school playground and took a long, slow look around. It was 8 a.m. on an unusually warm fall day in 2002 and the playground was deserted, but Hammond knew the children would start arriving soon to admire their new...

  • A) Analyze the need for managing change in the case attached. B) How would you distribute...

    A) Analyze the need for managing change in the case attached. B) How would you distribute change roles you would consider if you were a decision maker in the project? Note: Not more than 100 Words. Complexities of Large-Scale Technology Project Failure: A Forensic Analysis of the Seattle Popular Monorail Authority Introduction History shows that large scale innovative technology projects, financed with public funds, are fraught with dangers and often fail to deliver the product or the results promised at...

  • Please read the article and answer about questions. You and the Law Business and law are...

    Please read the article and answer about questions. You and the Law Business and law are inseparable. For B-Money, the two predictably merged when he was negotiat- ing a deal for his tracks. At other times, the merger is unpredictable, like when your business faces an unexpected auto accident, product recall, or government regulation change. In either type of situation, when business owners know the law, they can better protect themselves and sometimes even avoid the problems completely. This chapter...

  • I need help with my very last assignment of this term PLEASE!!, and here are the instructions: After reading Chapter T...

    I need help with my very last assignment of this term PLEASE!!, and here are the instructions: After reading Chapter Two, “Keys to Successful IT Governance,” from Roger Kroft and Guy Scalzi’s book entitled, IT Governance in Hospitals and Health Systems, please refer to the following assignment instructions below. This chapter consists of interviews with executives identifying mistakes that are made when governing healthcare information technology (IT). The chapter is broken down into subheadings listing areas of importance to understand...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT