Department R had 4,900 units in work in process that were 63% completed as to labor and overhead at the beginning of the period. During the period, 37,300 units of direct materials were added, 40,100 units were completed, and 2,100 units were 37% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. The first-in, first-out method is used to cost inventories. The number of equivalent units of production for conversion costs for the period was
a.37,790
b.42,690
c.47,100
d.40,100
Answer:
Option a) is correct. i.e 37,790 units
CALCULATE NO OF EQUIVALENT UNIT OF PRODUCTION FOR CONVERSION COST UNDER FIFO METHOD : | |||
WHOLE UNIT | % | EQUIVALENT UNIT | |
BEGINNING WIP | 4,900 | 37% | 1,813 |
UNIT STARTED & COMPLETED(40100-4900) | 35,200 | 100% | 35,200 |
ENDING WIP | 2,100 | 37% | 777 |
TOTAL | 37,790 | ||
Department R had 4,900 units in work in process that were 63% completed as to labor...
Department R had 4,600 units in work in process that were 64% completed as to labor and overhead at the beginning of the period. During the period, 32,700 units of direct materials were added, 34,500 units were completed, and 2,800 units were 30% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. The first-in, first-out method is used to cost inventories. The number of equivalent units of...
Department R had 4,200 units in work in process that were 74% completed as to labor and overhead at the beginning of the period. During the period, 35,900 units of direct materials were added, 37,900 units were completed, and 2,200 units were 26% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. The first-in, first-out method is used to cost inventories. The number of equivalent units of...
Department A had 4,600 units in work in process that were 64% completed as to labor and overhead at the beginning of the period, 30,500 units of direct materials were added during the period, 32,300 units were completed during the period; and 2,800 units were 37% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. The first-in, first-out method is used to cost inventories. The number of...
1. Department F had 4,000 units in Work in Process that were 40% completed at the beginning of the period at a cost of $11,600. Of the $11,600, $7,600 was for material and $4,000 was for conversion costs. 14,000 units of direct materials were added during the period at a cost of $31,500. 15,000 units were completed during the period, and 3,000 units were 75% completed at the end of the period. All materials are added at the beginning of...
Department E had 4,000 units in work in process that were 40% completed at the beginning of the period at a cost of $12,500. During the period, 14,000 units of direct materials were added at a cost of $28,700 and 15,000 units were completed. At the end of the period, 3,000 units were 75% completed. All materials are added t the beginning of the process. Direct labor was $32,450, and factory overhead was $18,710. The number of equivalent units of...
Department E had 4,000 units in Work in Process that were 40% completed at the beginning of the period at a cost of $12,500. 14,000 units of direct materials were added during the period at a cost of $28,700. 15,000 units were completed during the period, and 3,000 units were 75% completed at the end of the period. All materials are added at the beginning of the process. Direct labor was $32,450 and factory overhead was $18,710. The number of...
Question 6 1 pts Department E had 4.000 units in Work in Process that were 40% completed at the beginning of the period at a cost of $12.500. 14.000 units of direct materials were added during the period at a cost of $28.700. 15.000 units were completed during the period. and 3.000 units were 75% completed at the end of the period. All materials are added at the beginning of the process. Direct labor was $32,450 and factory overhead was...
Department A had 4,100 units in Work in Process that were 65% completed at the beginning of the period at a cost of $6,600. During the period, 25,900 units of direct materials were added at a cost of $56,980, and 28,000 units were completed. At the end of the period, 2,000 units were 26% completed. All materials are added at the beginning of the process. Direct labor was $25,300 and factory overhead was $4,800. The cost of the 2,000 units...
Department A had 5,000 units of work in process that were 60% completed at the beginning of the period; 31,000 units were completed and transferred during the period; and 2,000 units were 80% completed at the end of the period. All materials were added at the beginning of the process. Determine the number of equivalent units for (a) direct materials and (b) conversion.
1) 2) 3) Department S had no work in process at the beginning of the period. It added 12,600 units of direct materials during the period at a cost of $88,200; 9,450 units were completed during the period, and 3,150 units were 22% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. Direct labor was $55,300 and factory overhead was $8,900 The total cost of units completed...