Question

A project requires a cost of $39,400 today and yields cash flows for 3 years as...

A project requires a cost of $39,400 today and yields cash flows for 3 years as follows. When will the project pay back? Year 1 2 3 Cash flow $12,800 $21,800 $10,000 A) between 1 to 2 B) between 2 to 3 C) This investment never pays back

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Year Cash flows Cumulative Cash flows
0 (39400) (39400)
1 12800 (26600)
2 21800 (4800)
3 10000 5200

Payback period=Last period with a negative cumulative cash flow+(Absolute value of cumulative cash flows at that period/Cash flow after that period).

=2+(4800/10,000)

=2.48 years

Hence the correct option is:

B) between 2 to 3

Add a comment
Know the answer?
Add Answer to:
A project requires a cost of $39,400 today and yields cash flows for 3 years as...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT