Req 1. | ||||||||
Pre-determined OH (based on DLH) | ||||||||
Total Overheads (210000+90000+75000+150000) | 525000 | |||||||
Divide: Total DLH | 20000 | |||||||
OH rate per DLH | 26.25 | |||||||
Oh allocated to Job: | ||||||||
DLH used in Job: | 375 | |||||||
OH rate per DLH | 26.25 | |||||||
Total Ohh allocated gto job | 9843.75 | |||||||
Total Cost of Job: | ||||||||
Material | 5000 | |||||||
Labour | 7500 | |||||||
OH allocated | 9843.75 | |||||||
Total Cost of Job: | 22343.75 | |||||||
Selling Bid price: | ||||||||
Total cost of Job | 22343.75 | |||||||
Add: markup @ 30% | 6703.125 | |||||||
Selling Bid price: | 29046.88 | |||||||
Req 2. | ||||||||
STATEMENT SHOWING ACTIVITY RATE OF ACTIVITY POOL | ||||||||
Activity | Total | Expected | Activity | |||||
ACTIVITY COST POOL | Measures | Overheads | Activity | Rate | ||||
Maintenance | MH | 210000 | 10000 | 21.00 | ||||
Material Handling | Moves | 90000 | 2000 | 45.00 | ||||
Setups | Setups | 75,000 | 100 | 750.00 | ||||
Inspection | Inspections | 150,000 | 4,000 | 37.50 | ||||
Oh allocated: | ||||||||
Activity | Rate | Activity | OH allocated | |||||
Maintenance | 21 | 150 | 3150 | |||||
Material Handling | 45 | 4 | 180 | |||||
Setups | 750 | 2 | 1500 | |||||
Inspection | 37.5 | 3 | 112.5 | |||||
Total Overheads | 4942.5 | |||||||
Total Cost of Job: | ||||||||
Material | 5000 | |||||||
Labour | 7500 | |||||||
OH allocated | 4942.5 | |||||||
Total Cost of Job: | 17442.5 | |||||||
Selling Bid price: | ||||||||
Total cost of Job | 17442.5 | |||||||
Add: markup @ 30% | 5232.75 | |||||||
Selling Bid price: | 22675.25 | |||||||
The Activivty based costing provides the most competitive bid price. | ||||||||
our categories of overhead. The expected overhead costs for each category for Maintenance Materials handing 26....
Summer Manufacturing has four categories of overhead. The four categories and expected overhead costs for each category for next year are listed as follows: Maintenance $255,000 Materials handling 125,000 Setups 30,000 Inspection 105,000 Currently, overhead is applied using a predetermined overhead rate based upon budgeted direct labor hours. 100,000 direct labor hours are budgeted for next year. The company has been asked to submit a bid for a proposed job. The plant manager feels that obtaining this job would result...
Calculator Summer Marvufacturing has four categories of overhead. The four categories and expected overhead costs for each category for next year are listed as follows: Maintenance Materials handling Setups Inspection $255.000 125.000 30,000 105,000 Currently, overhead is applied using a predetermined overhead tate based upon budgeted direct later hours. 100.000 direct labor hours we budgeted for next year The company has been asked to submit a bid for a proposed job. The plant manager feels that in this job would...
XYZ Company has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: Maintenance $420,000 Inspection $600,000 The plant currently applies overhead using direct labor hours and expected capacity of 100,000 direct labor hours. The following data has been assembled for use in developing a bid for a proposed job. Bid prices are equal to the full manufacturing cost plus a 30 percent markup. Direct materials $3,500 Direct labor $6,500 Machine...
. Graham Company has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: Maintenance Inspection $900,000 1,500,000 The plant currently applies overhead using direct labor hours and expected capacity of 100,000 direct labor hours. The following data has been assembled for use in developing a bid for a proposed job. Additionally, the total expected machine hours for all jobs during the year are 100,000, and the total expected number of...
The Lislevand plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: Maintenance $121645 Inspection $184402 The plant’s expected capacity is 88283 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job. Direct materials $? Direct labour $5650 Machine hours 410 Number of inspections 9 Direct labour hours 749 Total expected machine hours for all jobs during the year is...
A company has identified the following overhead costs and cost drivers for the coming year: (CIA adapted) Overhead Item Machine setup Inspection Material handling Engineering Cost Driver Budgeted Cost Number of setups $ 20,000 Number of inspections 130,000 Number of material moves 80,000 Engineering hours 50,000 Budgeted Activity Level 200 6,500 8,000 1,000 Budgeted direct labor cost was $100,000 and budgeted direct material cost was $280,000. The following Information was collected on three jobs that were completed during the year:...
A company has identified the following overhead costs and cost drivers for the coming year: Budgeted Overhead Item Cost Driver Budgeted Cost Activity Level Machine setup Number of setups $ 12,000 150 Inspection Number of inspections 85,000 4,250 Material handling Number of material moves 66,000 5,500 Engineering Engineering hours 11,000 550 Budgeted direct labor cost was $87,000 and budgeted direct material cost was $241,600. The following information was collected on...
The Molotov plant of Kaboom Industries has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: Maintenance $50,000 Inspection $97,000 Machine Hours 49,000 hrs The plant currently applies overhead using machine hours. The following data have been assembled for use in developing a bid for a proposed job: Direct materials $500 Direct labor $2,000 Machine hours 500 Number of inspections 4 Direct labor hours 800 Using machine hours to assign...
Ponder Ltd. has two categories of overhead: Maintenance and Shipping. Expected costs and activity levels for these categories for 20x2 are as follows: Maintenance $375870 24088 machine hours Shipping $722452 1908 shipments In developing a bid for a proposed job, Ponder has assembled the following data: Direct materials $2748 Direct labour (at $7/hour) $12185 Machine hours 6268 Number of shipments 9 Using activity-based costing and the appropriate cost drivers, what is the total cost of the potential job? Select one:...
Calculate the total amount paid by the local construction
company
for the 5,000 windows.
The estimated manufacturing overhead costs for Watts Window Company for 2010 are listed below: Work space $3,000,000 Quality control inspections ..... 1,000,000 Electric power 400,000 Materials handling 1,200,000 Machine setups 700,000 Watts Company assigns overhead costs to products using an activity based costing system. The following information pertains to the activity based cost drivers and overhead costs: Type of cost Activity based cost driver Work space...