Question

Ponder Ltd. has two categories of overhead: Maintenance and Shipping. Expected costs and activity levels for...

Ponder Ltd. has two categories of overhead: Maintenance and Shipping. Expected costs and activity levels for these categories for 20x2 are as follows:

Maintenance

$375870

24088 machine hours

Shipping

$722452

1908 shipments


In developing a bid for a proposed job, Ponder has assembled the following data:

Direct materials

$2748

Direct labour (at $7/hour)

$12185

Machine hours

6268

Number of shipments

9


Using activity-based costing and the appropriate cost drivers, what is the total cost of the potential job?

Select one:

a. $27162

b. $116147

c. $45503

d. $101214

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Correct answer---------b. $116147

Working

Potential job
Direct material $              2,748.00
Direct labor   $            12,185.00
Overheads $        1,01,213.89
Total Cost   $        1,16,146.89

.

Cost assigned to Potential job
Activity name Activity Rates Activity ABC Cost
(A) (B) (A x B)
Maintenance $           15.60                  6,268.00 $         97,806.09
Shipping $        378.64                           9.00 $           3,407.79
Total Overheads assigned $      1,01,213.89

.

Calculation of Activity rates
Activity Cost Pool Activity driver Overhead Cost (A) Expected Activity (B) Activity rate (A/B)
Maintenance Number of machine hour $     3,75,870.00 24088 $             15.60 Per machine hour
Shipping Number of shipment $     7,22,452.00 1908 $          378.64 Per shipment
Add a comment
Know the answer?
Add Answer to:
Ponder Ltd. has two categories of overhead: Maintenance and Shipping. Expected costs and activity levels for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Lislevand plant has two categories of overhead: maintenance and inspection. Costs expected for these categories...

    The Lislevand plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: Maintenance $121645 Inspection $184402 The plant’s expected capacity is 88283 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job. Direct materials $? Direct labour $5650 Machine hours 410 Number of inspections 9 Direct labour hours 749 Total expected machine hours for all jobs during the year is...

  • . Graham Company has two categories of overhead: maintenance and inspection. Costs expected for these categories...

    . Graham Company has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: Maintenance Inspection $900,000 1,500,000 The plant currently applies overhead using direct labor hours and expected capacity of 100,000 direct labor hours. The following data has been assembled for use in developing a bid for a proposed job. Additionally, the total expected machine hours for all jobs during the year are 100,000, and the total expected number of...

  • XYZ Company has two categories of overhead: maintenance and inspection. Costs expected for these categories for...

    XYZ Company has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: Maintenance $420,000 Inspection $600,000 The plant currently applies overhead using direct labor hours and expected capacity of 100,000 direct labor hours. The following data has been assembled for use in developing a bid for a proposed job. Bid prices are equal to the full manufacturing cost plus a 30 percent markup. Direct materials $3,500 Direct labor $6,500 Machine...

  • The Molotov plant of Kaboom Industries has two categories of overhead: maintenance and inspection. Costs expected...

    The Molotov plant of Kaboom Industries has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: Maintenance $50,000 Inspection $97,000 Machine Hours 49,000 hrs The plant currently applies overhead using machine hours. The following data have been assembled for use in developing a bid for a proposed job: Direct materials $500 Direct labor $2,000 Machine hours 500 Number of inspections 4 Direct labor hours 800 Using machine hours to assign...

  • our categories of overhead. The expected overhead costs for each category for Maintenance Materials handing 26....

    our categories of overhead. The expected overhead costs for each category for Maintenance Materials handing 26. Stanford Corporation has f next year are as follows: $210,000 90,000 75,000 150,000 Setups Inspection The company has been asked to submit a bid for a proposed job. The plant manacer mbanufacturing this job would result in new business in future years. Bids are usually based upon full manufacturing cost plus 30 percent. Estimates for the proposed job are as follows: Direct materials Direct...

  • Summer Manufacturing has four categories of overhead. The four categories and expected overhead costs for each...

    Summer Manufacturing has four categories of overhead. The four categories and expected overhead costs for each category for next year are listed as follows: Maintenance $255,000 Materials handling 125,000 Setups 30,000 Inspection 105,000 Currently, overhead is applied using a predetermined overhead rate based upon budgeted direct labor hours. 100,000 direct labor hours are budgeted for next year. The company has been asked to submit a bid for a proposed job. The plant manager feels that obtaining this job would result...

  • Calculator Summer Marvufacturing has four categories of overhead. The four categories and expected overhead costs for...

    Calculator Summer Marvufacturing has four categories of overhead. The four categories and expected overhead costs for each category for next year are listed as follows: Maintenance Materials handling Setups Inspection $255.000 125.000 30,000 105,000 Currently, overhead is applied using a predetermined overhead tate based upon budgeted direct later hours. 100.000 direct labor hours we budgeted for next year The company has been asked to submit a bid for a proposed job. The plant manager feels that in this job would...

  • Buyer, Inc. uses activity based costing with two categories of overhead: maintenance and inspections. Overhead rates...

    Buyer, Inc. uses activity based costing with two categories of overhead: maintenance and inspections. Overhead rates for the coming year are as follows: Activity Cost Driver Activity Overhead Rate Maintenance Machine Hours $32/MH Inspection Number of Inspections $500/inspection Use the following data to estimate the total product cost of the potential job: Direct materials $6,000 Direct labor $16,000 Machine-hours 400 Number of inspections 4 Direct labor-hours 800

  • Merry Co. has two major categories of manufacturing overhead: material handling and quality control. The costs...

    Merry Co. has two major categories of manufacturing overhead: material handling and quality control. The costs expected for these categories for the coming year are as follows: Material handling $120,000 Quality inspection 200,000 The plant currently applies overhead based on direct labor hours. The estimated direct labor hours are 80,000 per year. The plant manager is asked to submit a bid and assembles the following data on a proposed job: Direct materials $4,000 Direct labor (2,000 hours) 6,000 What is...

  • Bonita Inc. has identified the following overhead costs and cost drivers for next year. Overhead Item...

    Bonita Inc. has identified the following overhead costs and cost drivers for next year. Overhead Item Expected Cost Cost Driver Expected Actual Transactions Setup costs $87,912 No. of setups 396 Ordering costs 46,800 No. of orders 3,900 Maintenance costs 125,000 Machine hours 25,000 Power 26,495 Kilowatt hours 75,700 The following are two of the jobs completed during the year: Job 700 Job 701 Direct materials $1,200 $600 Direct labour $890 $420 Units completed 250 100 Direct labour hours 40 20...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT