Question

Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Delta) that will require...

Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Delta) that will require an initial investment of $1,450,000. Blue Llama Mining Company has been basing capital budgeting decisions on a project’s NPV; however, its new CFO wants to start using the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because percentages and returns are easier to understand and to compare to required returns. Blue Llama Mining Company’s WACC is 7%, and project Delta has the same risk as the firm’s average project.

Year 1 $275,000
Year 2 $400,000
Year 3 $450,000
Year 4 $425,000

Which of the following is the correct calculation of project Delta’s IRR?

2.55%

2.68%

2.04%

2.29%

If this is an independent project, the IRR method states that the firm should Accept or Reject

If the project’s cost of capital were to increase, how would that affect the IRR?

The IRR would not change.

The IRR would increase.

The IRR would decrease.

1 0
Add a comment Improve this question Transcribed image text
Answer #1

The IRR can be calculated as :

( $1,450,000) + $2,75,000/( 1+ IRR) ^1 + $4,00,000/(1 +IRR)^2 + 4,50,000/(1 + IRR)^3 + 4,25,000/( 1+IRR)^4

= 2.55%

So,the correct option is option A.

The firm should reject this project as the IRR is less than the WACC.

The IRR would not change as the IRR assumes that the cash flows are reinvested at the IRR at not at the cost of capital.

So, the correct option is option A

Add a comment
Answer #2

SOLUTION :


At IRR, cash flows are discounted at IRR and NPV = 0


Let IRR be k in decimals.


So,


NPV = 0 = - Investment + Sum of CFn / (1 + k^n)  for n = 1 to 4

=> 0 = - 1450000 + 275000/(1+k) + 400000/(1+k)^2 + 450000/(1+k)^3 + 425000/(1+k)^4

By trial and error. k = 0.025514 = 2.5514% = 2.55% approx. 


Hence, IRR = 2.55% : FIRST OPTION  (ANSWER).


Project should be rejected as WACC > IRR (ANSWER)


IRR is the rate at which if discounted, NPV is zero. So, in IRR calculation cost of capital does not come into play. Hence, IRR will not change. (ANSWER)

answered by: Tulsiram Garg
Add a comment
Know the answer?
Add Answer to:
Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Delta) that will require...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Delta) that will require...

    Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Delta) that will require an initial investment of $1,500,000. Blue Llama Mining Company has been basing capital budgeting decisions on a project's NPV; however, its new CFO wants to start using the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because percentages and returns are easier to understand and to compare to required returns. Blue Llama Mining Company's WACC is...

  • Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require...

    Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require an initial investment of $900,000. Blue Llama Mining Company has been basing capital budgeting decisions on a project’s NPV; however, its new CFO wants to start using the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because returns in percentage form are easier to understand and compare to required returns. Blue Llama Mining Company’s WACC is...

  • Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require...

    Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require an initial investment of $800,000. Blue Llama Mining Company has been basing capital budgeting decisions on a project’s NPV; however, its new CFO wants to start using the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because returns in percentage form are easier to understand and compare to required returns. Blue Llama Mining Company’s WACC is...

  • Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Delta) that will require...

    Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Delta) that will require an initial Investment of $1,600,000 Blue Llama Mining Company has been basing capital budgeting decisions on a project's NPV; however, its new CFO wants to start using the IRR method for capital budgeting dedsions. The CFO says that the IRR is a better method because percentages and returns are easier to understand and to compare to required returns. Blue Llama Mining Company's WACC is...

  • Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require...

    Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require an initial investment of $800,000. Blue Llama Mining Company has been basing capital budgeting decisions on a project's NPV; however, its new CFO wants to start using the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because returns in percentage form are easier to understand and compare to required returns. Blue Llama Mining Company's WACC is...

  • Consider the following case: Blue Llama Mining Company is evaluating a proposed capital budgeting project (project...

    Consider the following case: Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Delta) that will require an initial investment of $1,500,000. Blue Llama Mining Company has been basing capital budgeting decisions on a project's NPV; however, its new CFO wants to start using the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because percentages and returns are easier to understand and to compare to required returns. Blue Llama...

  • Consider the following case: Blue Llama Mining Company is evaluating a proposed capital budgeting project (project...

    Consider the following case: Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Delta) that will require an initial investment of $1,500,000. Blue Llama Mining Company has been basing capital budgeting decisions on a project's NPV; however, its new CFO wants to start using the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because percentages and returns are easier to understand and to compare to required returns. Blue Llama...

  • should accept/reject Blue Ulama Mining Company is evaluating a proposed capital budgeting project (project Delta) that...

    should accept/reject Blue Ulama Mining Company is evaluating a proposed capital budgeting project (project Delta) that will require an IMUS Investment Or $1,40UUUU The company has been basing capital budgeting decisions on a project's NPV; however, its new CFO wants to start using the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because percentages and returns are easier to understand and to compare to required returns. Blue Llama Mining Company's WACC is...

  • Blue Pencil Publishing is evaluating a proposed capital budgeting project (project Delta) that will require an...

    Blue Pencil Publishing is evaluating a proposed capital budgeting project (project Delta) that will require an initial investment of $1,450,000. Blue Pencil Publishing has been basing capital budgeting decisions on a project's NPV; however, its new CFO wants to start using the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because percentages and returns are easier to understand and to compare to required returns. Blue Pencil Publishing's WACC is 8%, and project...

  • Falcon Freight is evaluating a proposed capital budgeting project (project Delta) that will require an initial...

    Falcon Freight is evaluating a proposed capital budgeting project (project Delta) that will require an initial investment of $1,600,000. Falcon Freight has been basing capital budgeting decisions on a project’s NPV; however, its new CFO wants to start using the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because percentages and returns are easier to understand and to compare to required returns. Falcon Freight’s WACC is 9%, and project Delta has the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT