Skysong Supply Company, a newly formed corporation, incurred the
following expenditures related to Land, to Buildings, and to
Machinery and Equipment.
Abstract company’s fee for title search | $598 | |||
Architect’s fees | 3,646 | |||
Cash paid for land and dilapidated building thereon | 100,050 | |||
Removal of old building |
$23,000 |
|||
Less: Salvage |
6,325 |
16,675 | ||
Interest on short-term loans during construction | 8,510 | |||
Excavation before construction for basement | 21,850 | |||
Machinery purchased (subject to 2% cash discount, which was not taken) | 63,250 | |||
Freight on machinery purchased | 1,541 | |||
Storage charges on machinery, necessitated by noncompletion of | ||||
building when machinery was delivered | 2,507 | |||
New building constructed (building construction took 6 months from | ||||
date of purchase of land and old building) | 557,750 | |||
Assessment by city for drainage project | 1,840 | |||
Hauling charges for delivery of machinery from storage to new building | 713 | |||
Installation of machinery | 2,300 | |||
Trees, shrubs, and other landscaping after completion of building | ||||
(permanent in nature) | 6,210 |
Determine the amounts that should be debited to Land, to Buildings,
and to Machinery and Equipment. Assume the benefits of capitalizing
interest during construction exceed the cost of implementation.
Company uses net method to record discount. (Please
leave spaces blank if there is no answer. Do not enter zeros in
those spaces.)
Land |
Buildings |
Machinery and Equipment |
Other |
|
Abstract company’s fee for title search |
$ |
$ |
$ |
$ |
Architect’s fees |
||||
Cash paid for land and old building |
||||
Removal of old building |
||||
Interest on short-term loans during construction |
||||
Excavation before construction for basement |
||||
Machinery purchased |
||||
Freight on machinery purchased |
||||
Storage charges on machinery |
$ |
$ |
$ |
$ |
New building constructed |
||||
Assessment by city for drainage project |
||||
Hauling charges |
||||
Installation of machinery |
||||
Trees, shrubs, and other landscaping |
||||
Solution :-
Land | Buildings | Machinery and Equipment | Other | |
Abstract company’s fee for title search | $598 | |||
Architect’s fees | $3,646 | |||
Cash paid for land and old building | $100,050 | |||
Removal of old building |
= $23,000 - $6,325 = $16,675 |
|||
Interest on short-term loans during construction | $8,510 | |||
Excavation before construction for basement | $21,850 | |||
Machinery purchased |
= $63,250 * [ 100 % - 2% ] = $63,250 * 98% = $61,985 |
= 63,250 * 2% = $1,265 |
||
Freight on machinery purchased | $1,541 | |||
Storage charges on machinery | $2,507 | |||
New building constructed | $557,750 | |||
Assessment by city for drainage project | $1,840 | |||
Hauling charges | $713 | |||
Installation of machinery | $2,300 | |||
Trees, shrubs, and other landscaping | $6,210 | |||
= $598 + $100,050 + $16,675 + $1,840 + $6,210 = $125,373 |
= $3,646 + $8,510 + $21,850 + $557,750 = $591,756 |
= $61,985 + $1,541 + $2,300 = $65,826 |
= $1,265 + $2,507 + $713 = $4,485 |
Skysong Supply Company, a newly formed corporation, incurred the following expenditures related to Land, to Buildings,...
Sheridan Supply Company, a newly formed corporation, incurred the following expenditures related to Land, to Bulldings, and to Machinery and Equipment. Abstract company's fee for title search Architet's fees Cash paid for land and dilapidated building thereon Removal of old building $1,014 6,182 169,650 $39,000 Less: Salvage Interest on short-term loans during construction Excavation before construction for basement Machinery purchased (subject to 2% cash discount, which was not taken) Freight on machinery purchased Storage charges on machinery, necessitated by noncompletion...
Flint Supply Company, a newly formed corporation, incurred the following expenditures related to Land, to Buildings, and to Machinery and Equipment. Abstract company’s fee for title search $1,118 Architect’s fees 6,816 Cash paid for land and dilapidated building thereon 187,050 Removal of old building $43,000 Less: Salvage 11,825 31,175 Interest on short-term loans during construction 15,910 Excavation before construction for basement 40,850 Machinery purchased (subject to 2% cash discount, which was not taken) 118,250 Freight on machinery purchased 2,881 Storage...
CALCULATOR PRINIER VERSION BACK NEX $24,000 Exercise 10-05 Waterway Supply Company, a newly formed corporation, incurred the following expenditures related to Land, to Buildings, and to Machinery and Equipment Abstract company's fee for title search 5624 Architect's fees 3,304 Cash paid for land and dilapidated building thereon 104,400 Removal of old building Lass: Salvage 5.600 17,400 Interest on short-term loans during construction 8,880 Excavation before construction for basement 22.300 Machinery purchased (subject to 2% cash discount, which was not taken)...
E10-5 (Treatment of Various Costs) Ben Sisko Supply Company, anewly formed corporation, incurred the following expenditures related to Land, to Buildings, and toMachinery and Equipment. Abstract company’s fee for title search $ 520 Architect’s fees 3,170 Cash paid for land and dilapidated building thereon 87,000 Removal of old building $20,000 Less: Salvage 5,500 14,500 Interest on short-term loans during construction 7,400 Excavation before construction for basement 19,000 Machinery purchased (subject to 2% cash discount, which was nottaken) 55,000 Freight on...
ed to Instructie Prepare the 510-7 warehou building how it should be reported. newly formed corporation, incurred the ST0-(L01,3) (Treatment of Various Costs) Ben Sisko Supply Company Equipment mg expenditures related to Land, to Buildings, and to Machinery and $ 520 Abstract company's fee for title search 3,170 Architect's fees 87,000 Cash paid for land and dilapidated building thereon $20,000 Removal of old building 5,500 14,500 Less Salvage 7.400 Interest on short-term loans during construction 19,000 Excavation before construction for...
ed to Instructie Prepare the 510-7 warehou building how it should be reported. newly formed corporation, incurred the ST0-(L01,3) (Treatment of Various Costs) Ben Sisko Supply Company Equipment mg expenditures related to Land, to Buildings, and to Machinery and $ 520 Abstract company's fee for title search 3,170 Architect's fees 87,000 Cash paid for land and dilapidated building thereon $20,000 Removal of old building 5,500 14,500 Less Salvage 7.400 Interest on short-term loans during construction 19,000 Excavation before construction for...
S (LO1.. Exec zon, Incurred the (LO 1, 2) (Treatment of Various Costs) Ben Sisko Supply Company, a newly formed corpora incurred the following expenditures related to Land, to Buildings, and to Machinery and Equipment Abstract company's fee for title search Exer $ 520 3,170 87,000 5,500 Architect's fees Cash paid for land and dilapidated building the con Removal of old building Less: Salvage $20.000 Interest on short-term loans during construction Excavation before construction for basement Machinery purchased (subject to...
E10.5 (LO 1, 2) (Tre tion, incurred the fol 1.2) (Treatment of Various Costs) Ben Sisko Supply Company, a newly formed corpora rred the following expenditures related to Land, to Buildings, and to Machinery and Equipment. Abstract company's fee for title search Architect's fees $ 520 Cash paid for land and dilapidated building thereon 3,170 Removal of old building 87,000 $20,000 Less: Salvage 5,500 14,500 Interest on short-term loans during construction 7,400 Excavation before construction for basement 19,000 Machinery purchased...
SASA Company made the following expenditures in connection with the construction of its new soccer facility: Architect’s fees $ 8,000 Cash paid for land and old building 130,000 Removal of old building 19,000 Survey to site the new building 6,000 Excavation for construction of basement 1,500 Machinery purchased 71,000 Storage charges on machinery because building was not ready when machinery was delivered 500 Freight on machinery purchased 1,500 Hauling charges to deliver machinery from storage to new building 500 Construction...
Consider each of the items below. Place the proper letter in the blank space provided to indicate the account or accounts to be debited when recording each transaction using the preferred accounting treatment. A. Land B. Land Improvements C. Building D. Machinery and Equipment E. Expense _____ 1. Cash paid for land and old building. _____ 2. Removal of old building. _____ 3. Architect’s fees. _____ 4. Interest cost of short term loans during construction. _____ 5. Purchase price for...