SASA Company made the following expenditures in connection with
the construction of its new soccer facility:
Architect’s fees |
$ 8,000 |
Cash paid for land and old building |
130,000 |
Removal of old building |
19,000 |
Survey to site the new building |
6,000 |
Excavation for construction of basement |
1,500 |
Machinery purchased |
71,000 |
Storage charges on machinery because building was not ready when machinery was delivered |
500 |
Freight on machinery purchased |
1,500 |
Hauling charges to deliver machinery from storage to new building |
500 |
Construction costs of new building |
612,000 |
Landscaping |
6,500 |
Installation of machinery |
8,500 |
REQUIRED:
Prepare a schedule showing the amounts to be recorded as Land,
Building, Machinery and Equipment, and Expenses.
Schedule Showing amount recorded as Land , Building , Machinery - SASA Company | |||
Particular | Land | Building | Machinery |
Architects Fee | $8,000.00 | ||
Cash Paid For Land and old Building | $130,000.00 | ||
Removal Of Old Building | $19,000.00 | ||
Survey to Site The New Building | $6,000.00 | ||
Excavation for Construction of Basement | $1,500.00 | ||
Machinery Purchased | $71,000.00 | ||
Storage Charges On Machinery | $500.00 | ||
Fright On Machinery Purchased | $1,500.00 | ||
Hauling Charges To Delivery Machine | $500.00 | ||
Construction Costs Of New Building | $612,000.00 | ||
Landscaping | $6,500.00 | ||
Installation Of Machinery | $8,500.00 | ||
Total Capitalization | $155,500.00 | $627,500.00 | $82,000.00 |
SASA Company made the following expenditures in connection with the construction of its new soccer facility:...
Skysong Supply Company, a newly formed corporation, incurred the following expenditures related to Land, to Buildings, and to Machinery and Equipment. Abstract company’s fee for title search $598 Architect’s fees 3,646 Cash paid for land and dilapidated building thereon 100,050 Removal of old building $23,000 Less: Salvage 6,325 16,675 Interest on short-term loans during construction 8,510 Excavation before construction for basement 21,850 Machinery purchased (subject to 2% cash discount, which was not taken) 63,250 Freight on machinery purchased 1,541 Storage...
Sheridan Supply Company, a newly formed corporation, incurred the following expenditures related to Land, to Bulldings, and to Machinery and Equipment. Abstract company's fee for title search Architet's fees Cash paid for land and dilapidated building thereon Removal of old building $1,014 6,182 169,650 $39,000 Less: Salvage Interest on short-term loans during construction Excavation before construction for basement Machinery purchased (subject to 2% cash discount, which was not taken) Freight on machinery purchased Storage charges on machinery, necessitated by noncompletion...
Flint Supply Company, a newly formed corporation, incurred the following expenditures related to Land, to Buildings, and to Machinery and Equipment. Abstract company’s fee for title search $1,118 Architect’s fees 6,816 Cash paid for land and dilapidated building thereon 187,050 Removal of old building $43,000 Less: Salvage 11,825 31,175 Interest on short-term loans during construction 15,910 Excavation before construction for basement 40,850 Machinery purchased (subject to 2% cash discount, which was not taken) 118,250 Freight on machinery purchased 2,881 Storage...
E10-5 (Treatment of Various Costs) Ben Sisko Supply Company, anewly formed corporation, incurred the following expenditures related to Land, to Buildings, and toMachinery and Equipment. Abstract company’s fee for title search $ 520 Architect’s fees 3,170 Cash paid for land and dilapidated building thereon 87,000 Removal of old building $20,000 Less: Salvage 5,500 14,500 Interest on short-term loans during construction 7,400 Excavation before construction for basement 19,000 Machinery purchased (subject to 2% cash discount, which was nottaken) 55,000 Freight on...
CALCULATOR PRINIER VERSION BACK NEX $24,000 Exercise 10-05 Waterway Supply Company, a newly formed corporation, incurred the following expenditures related to Land, to Buildings, and to Machinery and Equipment Abstract company's fee for title search 5624 Architect's fees 3,304 Cash paid for land and dilapidated building thereon 104,400 Removal of old building Lass: Salvage 5.600 17,400 Interest on short-term loans during construction 8,880 Excavation before construction for basement 22.300 Machinery purchased (subject to 2% cash discount, which was not taken)...
ed to Instructie Prepare the 510-7 warehou building how it should be reported. newly formed corporation, incurred the ST0-(L01,3) (Treatment of Various Costs) Ben Sisko Supply Company Equipment mg expenditures related to Land, to Buildings, and to Machinery and $ 520 Abstract company's fee for title search 3,170 Architect's fees 87,000 Cash paid for land and dilapidated building thereon $20,000 Removal of old building 5,500 14,500 Less Salvage 7.400 Interest on short-term loans during construction 19,000 Excavation before construction for...
ed to Instructie Prepare the 510-7 warehou building how it should be reported. newly formed corporation, incurred the ST0-(L01,3) (Treatment of Various Costs) Ben Sisko Supply Company Equipment mg expenditures related to Land, to Buildings, and to Machinery and $ 520 Abstract company's fee for title search 3,170 Architect's fees 87,000 Cash paid for land and dilapidated building thereon $20,000 Removal of old building 5,500 14,500 Less Salvage 7.400 Interest on short-term loans during construction 19,000 Excavation before construction for...
E10.5 (LO 1, 2) (Tre tion, incurred the fol 1.2) (Treatment of Various Costs) Ben Sisko Supply Company, a newly formed corpora rred the following expenditures related to Land, to Buildings, and to Machinery and Equipment. Abstract company's fee for title search Architect's fees $ 520 Cash paid for land and dilapidated building thereon 3,170 Removal of old building 87,000 $20,000 Less: Salvage 5,500 14,500 Interest on short-term loans during construction 7,400 Excavation before construction for basement 19,000 Machinery purchased...
S (LO1.. Exec zon, Incurred the (LO 1, 2) (Treatment of Various Costs) Ben Sisko Supply Company, a newly formed corpora incurred the following expenditures related to Land, to Buildings, and to Machinery and Equipment Abstract company's fee for title search Exer $ 520 3,170 87,000 5,500 Architect's fees Cash paid for land and dilapidated building the con Removal of old building Less: Salvage $20.000 Interest on short-term loans during construction Excavation before construction for basement Machinery purchased (subject to...
Consider each of the items below. Place the proper letter in the blank space provided to indicate the account or accounts to be debited when recording each transaction using the preferred accounting treatment. A. Land B. Land Improvements C. Building D. Machinery and Equipment E. Expense _____ 1. Cash paid for land and old building. _____ 2. Removal of old building. _____ 3. Architect’s fees. _____ 4. Interest cost of short term loans during construction. _____ 5. Purchase price for...