Question

Lanyard Company uses a job-order costing system to account for product costs. The following information pertains to 2016: $14
1 0
Add a comment Improve this question Transcribed image text
Answer #1

C) $450,000

Explanation:

Material Placed into production $140,000
Add: Indirect Labor (applied on cost allocation base) $0
Add: Direct Labor $160,000
Add: Depreciation of factory building (not a part of finished goods inventory) $0
Add: Other Factory Overheads (applied on cost allocation base)

$0

Add: Factory Overheads (10,000 direct labor hours @ $ 18 per hour) $180,000
Total $480,000
Less: Increase in Work-in-process Inventory ($30,000)
Amount Debited to finished goods inventory $450,000

Note: To answer the question in correct spirit, year 2011 in the the question is assumed to be replaced with the year 2016. It is an error clearly evident from the facts of the question. If not assumed so, it will not be possible to solve the question with the given facts.

Add a comment
Know the answer?
Add Answer to:
Lanyard Company uses a job-order costing system to account for product costs. The following information pertains...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lanyard Company uses a job-order costing system to account for product costs. The following information pertains...

    Lanyard Company uses a job-order costing system to account for product costs. The following information pertains to 2014: Materials placed into production $170,000 Indirect labor 40,000 Direct labor (10,000 hours) 160,000 Depreciation of factory building 60,000 Other factory overhead 100,000 Increase in work-in-process inventory 20,000 Factory overhead rate is $20 per direct labor hour. 1. Refer to Figure 5-4. What is the total amount credited to Materials Inventory for Lanyard in 2014? 2. Refer to Figure 5-4. What is the...

  • Week 5 Job Costing The Fine Manufacturing Company uses job order costing system. The company uses...

    Week 5 Job Costing The Fine Manufacturing Company uses job order costing system. The company uses machine hours to apply overhead cost to jobs. At the beginning of 2019, the company estimated that 150,000 machine hours would be worked and $900,000 overhead cost would be incurred during 2012. The balances of raw materials, work in process (WIP), and finished goods at the beginning of 2012 were as follows: Raw materials: $40,000 Work in process: $30,000 Finished goods: $60,000 The Fine...

  • Problem for Job Order Costing Tiny Homes uses a job costing system to account for the...

    Problem for Job Order Costing Tiny Homes uses a job costing system to account for the individual prefabricated homes of January 1, its accounting records showed inventories as follows the individual prefabricated homes it builds. As Materials and supplies Work in process (Jobs 422 and 423) Finished goods (Job 421) $120,000 180,000 175,000 The work in process in ventory consisted of two jobs: Job# 422 423 Direct Materials $36,000 Direct Labor Manufacturing Overh $40,000 $20,000 $96,000 $36,000 $180,000 $76,000 $68,000...

  • Ecola Company uses a job order costing system. Manufacturing overhead is applied on the basis of...

    Ecola Company uses a job order costing system. Manufacturing overhead is applied on the basis of direct labor cost. Total manufacturing overhead was estimated to be $214,500 for the year; direct labor was estimated to total $195,000. (a) Calculate the predetermined overhead rate. (b) Calculate cost of goods manufactured. (c) Calculate the over- or underapplied overhead. (Input the amount as positive value.) (d) Calculate adjusted cost of goods sold. Raw Materials Inventory Work in Process Inventory Finished Goods Inventory (1/1)...

  • The Film Company uses a job-order costing system. The following information pertains to the company's activities...

    The Film Company uses a job-order costing system. The following information pertains to the company's activities for the month of December: On December 1, the company had two jobs in work in process as follows: Job 6 $20,000 and Job 8 $14,000 On December 1, the company had job in Finished Goods as follows: Job 10 $50,000 Jobs 12 and 13 were started during the month. Materials were purchased on account in December for $54,000 Materials were requisitioned for use...

  • The Film Company uses a job-order costing system. The following information pertains to the company's activities...

    The Film Company uses a job-order costing system. The following information pertains to the company's activities for the month of December: On December 1, the company had two jobs in work in process as follows: Job 6 $20,000 and Job 8 $14,000 On December 1, the company had job in Finished Goods as follows: Job 10 $50,000 Jobs 12 and 13 were started during the month. Materials were purchased on account in December for $54,000 Materials were requisitioned for use...

  • Furniture Company manufactures custom furniture only and uses a job order costing system to accumulate costs....

    Furniture Company manufactures custom furniture only and uses a job order costing system to accumulate costs. This is Corbanzo’s first year of operation. Actual direct materials and direct labor costs are accumulated for each job, but a predetermined overhead rate is used to apply manufacturing overhead costs to individual jobs. Manufacturing overhead is applied on the basis of direct labor hours. In computing a predetermined overhead rate, the controller estimated that manufacturing overhead costs for the year would be $200,000...

  • The Film Company uses a job-order costing system. The following information pertains to the company's activities...

    The Film Company uses a job-order costing system. The following information pertains to the company's activities for the month of December: On December 1, the company had two jobs in work in process as follows: Job 6 $20,000 and Job 8 $14,000 On December 1, the company had job in Finished Goods as follows: Job 10 $50,000 Jobs 12 and 13 were started during the month. A. Materials were purchased on account in December for $54,000 B. Materials were requisitioned...

  • The Film Company uses a job-order costing system. The following information pertains to the company's activities...

    The Film Company uses a job-order costing system. The following information pertains to the company's activities for the month of December: On December 1, the company had two jobs in work in process as follows: Job 6 $20,000 and Job 8 $14,000 On December 1, the company had job in Finished Goods as follows: Job 10 $50,000 Jobs 12 and 13 were started during the month. Materials were purchased on account in December for $54,000 Materials were requisitioned for use...

  • The Film Company uses a job-order costing system. The following information pertains to the company's activities...

    The Film Company uses a job-order costing system. The following information pertains to the company's activities for the month of December: On December 1, the company had two jobs in work in process as follows: Job 6 $20,000 and Job 8 $14,000 On December 1, the company had job in Finished Goods as follows: Job 10 $50,000 Jobs 12 and 13 were started during the month. A. Materials were purchased on account in December for $54,000 B. Materials were requisitioned...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT