Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $586,500 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:
Activity Cost Pool | Activity Measure | Estimated Overhead Cost | Expected Activity | ||
Machining | Machine-hours | $ | 195,000 | 10,000 | MHs |
Machine setups | Number of setups | $ | 67,500 | 150 | setups |
Product design | Number of products | $ | 79,000 | 2 | products |
General factory | Direct labor-hours | $ | 245,000 | 12,000 | DLHs |
Activity Measure | Product Y | Product Z |
Machine-hours | 6,500 | 3,500 |
Number of setups | 50 | 100 |
Number of products | 1 | 1 |
Direct labor-hours | 7,500 | 4,500 |
5. What is the activity rate for the Product Design activity cost pool?
6. What is the activity rate for the General Factory activity cost pool? (Round your answer to 2 decimal places.)
7. Which of the four activities is a batch-level activity?
a.General factory activity
b.Product design activity
c.Machine setups activity
d.Machining activity
8. Which of the four activities is a product-level activity?
a.Machining activity
b.Machine setups activity
c.General factory activity
d. Product design activity
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The...
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number of setups...
4) 5) 6) Hickory Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $614,400 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Estimated Expected Overhead Cost Activity $ 198,000 10,000 MHs $ a 86,400...
Hickory company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z.... -7 Homework Hickory Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $791,400 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y...
A) B) C) Hickory Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $614,400 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Estimated Expected Overhead Cost Activity $ 198,000 10,000 MHs $ a 86,400...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: (The total estimated overhead cost may not agree with the sum of allocated overhead costs to...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z. (The total estimated overhead cost may not agree with the sum of allocated overhead costs to...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $674,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 216,700 11,000...
Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 209,000 10,000 MHs...
Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 209,000 10,000 MHs...
Hickory Company manufactures two products--15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and 2. (The total estimated overhead cost may not agree with the sum of allocated overhead costs to...