HI
Here the cash flows are
Y 0 =- $148,400
Y1 = $42,500
Y2 = $82,300
Y3 = $46,200
IRR=?
For internal rate of return (IRR) we will use excel IRR function
IRR =IRR(cash flows)
IRR = IRR(-148,400, 42,500, 82300,46,200)
IRR = 7.33%, hence you should reject the project since it is less than 10%
THanks
A project has cash flows of -$148,400, $42,500, $82,300, and $46,200 for Years 0 to 3,...
A project has cash flows of –$148,400, $42,500, $87,300, and $43,200 for Years 0 to 3, respectively. The required rate of return is 11 percent. Based on the internal rate of return of ________ percent for this project, you should ________ the project. A.) 7.91; reject B.) 8.03; reject C.) 6.67; reject D.) 8.03; accept E.) 7.91; accept
A project has cash flows of −$152,000, $60,800, $62,300, and $75,000 for Years 0 to 3, respectively. The required rate of return is 13 percent. Based on the internal rate of return of _____ percent, you should _____ the project. Please give an exact answer.
Project A has a required return on 9.2 percent and cash flows of −$87,000, $32,600, $35,900, and $43,400 for Years 0 to 3, respectively. Project B has a required return of 12.7 percent and cash flows of −$85,000, $14,700, $21,200, and $89,800 for Years 0 to 3, respectively. Which project(s) should you accept based on net present value if the projects are mutually exclusive? Multiple Choice Accept both projects Accept either one, but not both Accept Project A and reject...
Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 11 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively Time 0 3 4 5 6 Cash Flow -1,040 140 460 660 660 260 660 Use the payback decision rule to evaluate this project; should it be accepted or rejected? Multiple...
Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively Time 0 1 4 5 6 Cash Flow -1,150 30 570 770 770 370 770 Use the discounted payback decision rule to evaluate this project; should it be accepted or rejected?...
Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 10 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively. Time 0 1 2 3 4 5 6 Cash Flow -1,050 150 450 650 650 250 650 Use the discounted payback decision rule to evaluate this project; should it be accepted...
Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively Time Cash Flow 0 1 2 3 4 5 6 -1,150 30570770770 370770 Use the NPV decision rule to evaluate this project, should it be accepted or rejected? Multiple Choice 0...
You are analyzing a project and have prepared the following
data: Year Cash Flow $169,000 $46,200 I$87,300 $41,000 I$39,000 1
12 4 Required payback period 2.5 years Required return 8.50% the
project. Based on the profitability index of 0.97; accept for this
project, you should 1.05; accept 1.18; accept 0.97; reject 1.05;
reject
Question 15 You are analyzing a project and have prepared the following data: Year Cash Flow $169,000 $46,200 $87,300 $41,000 $39,000 Required payback period 2.5 years Required...
A project has cash flows of -$119,000, $53,000, $60,200, and $33,000 for years 0 to 3, respectively. The required rate of return is 12 percent. Based on the net present value of ____, you should _____ the project.
Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 14 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively. Time Cash Flow 0 -960 1 160 2 440 3 640 4 640 5 240 6 640 Use the payback decision rule to evaluate this project; should it be accepted or...