Question

The table below provides the estimated end-of-year net cash flows that would be received from alternative projects Red and Bl

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a

Project Red
Discount rate 0.07
Year 0 1 2 3 4
Cash flow stream -200000 90000 70000 60000 40000
Discounting factor 1 1.07 1.1449 1.225043 1.310796
Discounted cash flows project -200000 84112.15 61140.71 48977.87 30515.808
NPV = Sum of discounted cash flows
NPV Project Red = 24746.54
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project Blue
Discount rate 0.07
Year 0 1 2 3 4
Cash flow stream -200000 40000 50000 60000 126000
Discounting factor 1 1.07 1.1449 1.225043 1.310796
Discounted cash flows project -200000 37383.18 43671.94 48977.87 96124.797
NPV = Sum of discounted cash flows
NPV Project Blue = 26157.78
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

b

Project Blue as it has higher NPV

c

Project Red
Discount rate 0.09
Year 0 1 2 3 4
Cash flow stream -200000 90000 70000 60000 40000
Discounting factor 1 1.09 1.1881 1.295029 1.4115816
Discounted cash flows project -200000 82568.81 58917.6 46331.01 28337.008
NPV = Sum of discounted cash flows
NPV Project Red = 16154.42
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project Blue
Discount rate 0.09
Year 0 1 2 3 4
Cash flow stream -200000 40000 50000 60000 126000
Discounting factor 1 1.09 1.1881 1.295029 1.4115816
Discounted cash flows project -200000 36697.25 42084 46331.01 89261.577
NPV = Sum of discounted cash flows
NPV Project Blue = 14373.83
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

d

Project red as it has higher NPV

Add a comment
Know the answer?
Add Answer to:
The table below provides the estimated end-of-year net cash flows that would be received from alternative...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • ZYZ Inc. is considering a project with the following cash flows: Year Cash Flow (CF) 0...

    ZYZ Inc. is considering a project with the following cash flows: Year Cash Flow (CF) 0 -$200,000 1 $30,000 2 $40,000 3 $50,000 4 $60,000 5 $70,000 If the discount rate is 5%, what is the NPV of the proposed project? Question 3 options: $11,572.99 $12,253.47 $21,009.43 $10,572.99

  • ZYZ Inc. is considering a project with the following cash flows: Year Cash Flow (CF) 0...

    ZYZ Inc. is considering a project with the following cash flows: Year Cash Flow (CF) 0 -$200,000 1 $30,000 2 $40,000 3 $50,000 4 $60,000 5 $70,000 If the discount rate is 5%, what is the NPV of the proposed project? Question 37 options: $11,572.99 $10,572.99 $21,009.43 $12,253.47

  • JC Warehouse Corporation has estimated the cash flows of Projects A, B, and C as follows.

    JC Warehouse Corporation has estimated the cash flows of Projects A, B, and C as follows.  YearProject AlphaProject BetaProject Delta0-$100,000-$200,000-$100,000170,000130,00075,000270,000130,00060,000 Suppose the company requires a 12 percent return on investment.1.1 Calculate the payback period for each of the three projects.1.2 Calculate the NPV for each of the three projects.1.3 Calculate the profitability index for each of the three projects.1.4 Suppose these three projects are independent and the company has an unlimited amount of funds. If the company makes decision based...

  • Each of two mutually exclusive projects involves an investment of $124,000. Net cash flows for the...

    Each of two mutually exclusive projects involves an investment of $124,000. Net cash flows for the projects are as follows: Year Project A Project B 1 60,000 57,000 2 62,000 64,000 3 40,000 47,000 A.    Calculate each project's payback period. (2 Points) B.    Compute the Net Present Value (NPV) of each project when the firm's cost of capital is 10 percent. (2 Points) C.    Internal Rate of Return (IRR) -Your choice; based on your answer to part (B). (2 Points) D.    Modified Internal Rate...

  • If an independent project with conventional, or normal, cash flows is being analyzed, the net present...

    If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars Year Project Y Project Z 800 -$1,500 -$1,500 0 $200 $900 1 600 Project Y $400 $600 2 $600 $300 400 $1,000 $200 4 Project Z 200 If the weighted average cost of capital...

  • If an independent project with conventional, or normal, cash flows is being analyzed, the net present...

    If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects W and X are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) 800 0 -$1,00 Year Project W -$1,000 1 $200 2 $350 $400 $600 Project x -$1,500 $350 $500 $600 $750 Project X Project W If the weighted average cost of capital (WACC) for each...

  • QUESTION 1 Star Industries is considering three alternative projects for the company's investment. The cash flows for three independent projects are as follows: Year 1 Project A ($50,000) $10,...

    QUESTION 1 Star Industries is considering three alternative projects for the company's investment. The cash flows for three independent projects are as follows: Year 1 Project A ($50,000) $10,000 $15,000 $20,000 $25,000 $30,000 Project B ($100,000) $25,000 $25,000 $25,000 $25,000 $25,000 Project C ($450,000) $200,000 $200,000 $200,000 a) If the discount rate for all three projects is 9.5 percent, calculate the profitability index (PI) of these three projects. Which project will be accepted if the projects are mutually exclusive? b)...

  • If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...

    If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) 800 Year Project Y Project Z 0 -$1,500 -$1,500 1 $200 $900 2 $400 $600 $600 $300 4 $1,000 $200 Project Y Project 2 If the weighted average cost of capital (WACC) for each project is...

  • 1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value...

    1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Blue Hamster Manufacturing Inc. is evaluating a proposed capital budgeting project (project Beta) that will require an initial investment of $2,750,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $375,000 Year 2 $425,000...

  • 1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value...

    1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Blue Hamster Manufacturing Inc. is evaluating a proposed capital budgeting project (project Beta) that will require an initial investment of $2,500,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $375,000 Year 2 $425,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT