Question

The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are addedWhole Units Direct Materials Conversion Inventory in process, January 1 Started and completed in January Transferred to finisInventory in process, January 1 balance To complete inventory in process, January 1 Cost of completed January 1 work in proce

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Karachi Carpet Company
Cost of Production Report-Cutting Department
For the Month Ended January 31
Unit Information
Units charged to production:
Inventory in process, January 1 9000
Received from weaving Department 138800
Total units accounted for by the Cutting Department 147800
Units to be assigned costs:
Equivalent Units
Whole Units Direct Materials Conversion
Inventory in process, January 1 9000 0 2250
Started and completed in January 131400 131400 131400
Transferred to Finished goods in January 140400 131400 133650
Inventory in process, January 31 7400 7400 2590
Total units to be assigned costs 147800 138800 136240
Cost Information
Costs per equivalent unit:
Direct Materials Conversion
Total costs for January in Cutting Department 1485160 544960
Total equivalent units 138800 136240
Cost per equivalent unit 10.70 4.00
Costs charged to production:
Direct Materials Conversion Total
Inventory in process, January 1 121725
Costs incurred in January 2030120
Total costs accounted for by the Cutting Department 2151845
Cost allocated to completed and partially completed units:
Inventory in process, January 1 balance 121725
To complete inventory in process, January 1 0 9000 9000
Cost of completed January 1 work in process 130725
Started and completed in January 1405980 525600 1931580
Transferred to Finished goods in January 2062305
Inventory in process, January 31 79180 10360 89540
Total costs assigned by the Cutting Department 2151845
2
Increase or Decrease Amount
Change in direct materials cost per equivalent unit Increase 0.10 =10.7-10.6
Change in conversion cost per equivalent unit Increase 0.10 =4-3.9
Add a comment
Know the answer?
Add Answer to:
The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all...

    The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process. Work in process, January 1, 9,000 units, 75% completed $109,125*     *Direct materials (9,000 × $8) $72,000     Conversion (9,000 × 75% × $5.5) 37,125 $109,125 Materials added during January from Weaving Department, 138,800 units $1,131,220 Direct labor for January 329,265 Factory overhead for January 402,435 Goods finished during January (includes goods in process, January 1), 140,400...

  • The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all...

    The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process. Work in process, January 1, 7,600 units, 75% completed $100,510*     *Direct materials (7,600 × $10.00) $76,000     Conversion (7,600 × 75% × $4.30) 24,510 $100,510 Materials added during January from Weaving Department, 117,200 units $1,183,720 Direct labor for January 225,997 Factory overhead for January 276,219 Goods finished during January (includes goods in process, January 1), 118,600...

  • The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all...

    The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process. Work in process, January 1, 13,400 units, 60% completed $165,356*     *Direct materials (13,400 × $9.40) $125,960     Conversion (13,400 × 60% × $4.90) 39,396 $165,356 Materials added during January from Weaving Department, 206,400 units $1,971,120 Direct labor for January 462,848 Factory overhead for January 565,702 Goods finished during January (includes goods in process, January 1), 208,800...

  • The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all...

    The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process. Work in process, January 1, 7,400 units, 60% completed $92,204* *Direct materials (7,400 × $10.6) $78,440 Conversion (7,400 × 60% × $3.1) 13,764 $92,204 Materials added during January from Weaving Department, 114,000 units $1,214,100 Direct labor for January 152,631 Factory overhead for January 186,549 Goods finished during January (includes goods in process, January 1), 115,400...

  • The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all...

    The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process. Work in process, January 1, 12,000 units, 80% completed $148,800*     *Direct materials (12,000 × $9.6) $115,200     Conversion (12,000 × 80% × $3.5) 33,600 $148,800 Materials added during January from Weaving Department, 184,800 units $1,783,320 Direct labor for January 274,421 Factory overhead for January 335,403 Goods finished during January (includes goods in process, January 1), 187,000...

  • Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for...

    Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process. $108,650 Work in process, January 1, 8,200 units, 65% completed *Direct materials (8,200 x $10.00) Conversion (8,200 x 65% * $5.00) $82,000 26,650 $108,650 Materials added during January from Weaving Department, 126,400 units $1,276,640 Direct labor for January 276,794 Factory overhead for January 338,303 Goods finished during January (includes goods in...

  • Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for...

    Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process. Work in process, January 1, 14,000 units, 75% completed $168,000* *Direct materials (14,000 x $7.80) $109,200 Conversion (14,000 x 75% * $5.60) 58,800 $168,000 Materials added during January from Weaving Department, 215,600 units $1,714,020 Direct labor for January 525,344 Factory overhead for January 642,086 Goods finished during January (includes goods in...

  • Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for...

    Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process. Work in process, January 1, 14,000 units, 75% completed $168,000* *Direct materials (14,000 x $7.80) $109,200 Conversion (14,000 x 75% * $5.60) 58,800 $168,000 Materials added during January from Weaving Department, 215,600 units $1,714,020 Direct labor for January 525,344 Factory overhead for January 642,086 Goods finished during January (includes goods in...

  • Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for...

    Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process. Work in process, January 1, 7,800 units, 65% completed $105,495*     *Direct materials (7,800 × $10.6) $82,680     Conversion (7,800 × 65% × $4.5) 22,815 $105,495 Materials added during January from Weaving Department, 120,000 units $1,278,000 Direct labor for January 243,453 Factory overhead for January 297,553 Goods finished during January (includes goods in...

  • Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for...

    Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process. Work in process, January 1, 10,800 units, 60% completed $107,136* * Direct materials (10,800 x $8) $86,400 Conversion (10,800 X 60% X $3.2) 20,736 $107,136 Materials added during January from Weaving Department, 166,400 units $1,347,840 243,718 Direct labor for January Factory overhead for January 297,878 Goods finished during January (includes goods...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT