Question

Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...

Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products:

Activity Cost Pool Activity Rate
Setting up batches $ 59.46 per batch
Processing customer orders $ 72.90 per customer order
Assembling products $ 4.15 per assembly hour

Data concerning two products appear below:

Product K91B Product F65O
Number of batches 87 58
Number of customer orders 37 51
Number of assembly hours 491 898

How much overhead cost would be assigned to Product K91B using the activity-based costing system? (Round your intermediate calculations and final answers to 2 decimal places.)

Multiple Choice

  • $9,907.97

  • $89,171.73

  • $5,173.02

  • $136.51

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans. : Overhead cost that would be assigned to Product K91B using the Activity based costing system = Setting up batches rate per batch* number of batches + processing cost per customer order * number of customer orders + Assembly rate per hour* number of assembly hours

= 59.46* 87 + 72.90*37 + 4.15* 491

= 5173.02 + 2697.3 + 2037.65

= 9,907.97 dollars

Therefore, correct answer is option a. that is dollars 9,907.97.

Add a comment
Know the answer?
Add Answer to:
Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...

    Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Activity Cost Pool Activity Rate Setting up batches $ 59.91 per batch Processing customer orders $ 73.17 per customer order Assembling products $ 4.60 per assembly hour Data concerning two products appear below: Product K91B Product F65O Number of batches 96 67 Number of customer orders 46 60 Number of assembly hours 500 907 How much overhead cost would be assigned to Product...

  • Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...

    Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Activity Cost Pool Activity Rate Setting up batches $ 59.11 per batch Processing customer orders $ 72.69 per customer order Assembling products $ 3.80 per assembly hour Data concerning two products appear below: Product K91B Product F65O Number of batches 80 51 Number of customer orders 30 44 Number of assembly hours 484 891 How much overhead cost would be assigned to Product...

  • Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...

    Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Activity Cost Pool Activity Rate Setting up batches $ 60.06 per batch Processing customer orders $ 73.26 per customer order Assembling products $ 4.75 per assembly hour Data concerning two products appear below: Product K91B Product F65O Number of batches 99 70 Number of customer orders 49 63 Number of assembly hours 503 910 How much overhead cost would be assigned to Product...

  • Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...

    Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Activity Cost Pool Activity Rate Setting up batches Processing customer orders Assembling products $59.71 per batch $73.05 per customer order $ 4.40 per assembly hour Data concerning two products appear below: Product Product K91B F650 Number of batches 92 63 Number of customer orders 42 56 Number of assembly hours 496 903 How much overhead cost would be assigned to Product K91B using...

  • Doles Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...

    Doles Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products. Activity Cost Pools Activity Rate Setting up batches $ 72.02 per batch Processing customer orders $ 29.08 per customer order Assembling products $ 13.51 per assembly hour Data concerning two products appear below: Product K52W Product X94T Number of batches 67 54 Number of customer orders 47 32 Number of assembly hours 420 163 Required: How much overhead cost would be assigned to...

  • Ekmark Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...

    Ekmark Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Assembling products.................. $6.56 per assembling hour Processing customer orders......... $65.38 per customer order Setting up batches...................... $82.84 per batch Data for one of the company's products follow: Product P59G Number of Assembly Hours.............240 Number of Customer Orders...........48 Number of Batches.......................64 How much overhead cost would be allocated to Product P59G in the 2nd stage using activity based costing system? a. $54,482.56 b. $5,301.76...

  • 18) Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs t...

    18) Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: 18) Activity Cost Pool Setting up batches Processing customer orders Assembling products Activity Rate 59.96 per batch $ S 73.20 per customer order S 4.65 per assembly hour Data concerning two products appear below: Product Product K91B F650 Number of batches Number of customer orders 97 68 47 61 Number of assembly hours 501 908 How much overhead cost would be assigned...

  • Senff Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...

    Senff Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Activity Cost Pools Setting up batches Processing customer orders Assembling products Activity Rate $86.75 per batch $77.49 per customer order $12.41 per assembly hour Data concerning two products appear below. Number of batches Number of customer orders Number of assembly hours Product V912 70 21 493 Product V211 13 10 698 How much overhead cost would be assigned to Product V91Z using the...

  • Doles Corporation uses the following activity rates from Its activity-based costing to assign overhead costs to...

    Doles Corporation uses the following activity rates from Its activity-based costing to assign overhead costs to products. Activity Cost Pools Setting up batches Processing customer orders Assembling products Activity Rate $70.62 per batch $27.68 per customer order $12.81 per assembly hour Data concerning two products appear below. Product K52W Product X94T Number of batches 68 55 Number of customer orders 48 33 Number of assembly hours 421 164 Required: How much overhead cost would be assigned to each of the...

  • Doles Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...

    Doles Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products. Activity Cost Pools Setting up batches Processing customer orders Assembling products Activity Rate $66.52 per batch $23.58 per customer order $10.71 per assembly hour Data concerning two products appear below: Number of batches Number of customer orders Number of assembly hours Product K52W 65 45 Product X94T 52 30 418 161 Required: How much overhead cost would be assigned to each of the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT