Question

The project you started and planned to move your accounts office from location A to location...

The project you started and planned to move your accounts office from location A to location B which is about 10 kilometers from your current location as shown below is going well.

  1. WORK BREAK DOWN STRUCTURE

S. NO.

WORK BREAK DOWN STRUCTURE

1

Office Location Move Plan

1.1

The detail move plan is made and reviewed with all employees

1.2

Employee readiness against the move plan.

2

Office Location Communication

2.1

Email communication to all employees

2.2

Notice board displayed with move plan

3

Office Move Execution

3.1

Employee executed their movement

3.2

Equipment, material, records etc moved to new location

4

Preparation at New Location

4.1

Employee readiness preparation at new location

4.2

All equipment, material, records etc set at new office

  1. PROJECT MANAGEMENT PLAN   

Project Stage

Time

Responsible person(s)

Planning

1st January, 2020

Change Leader

Communication

1st January, 2020

Office Leader

Wrapping off at Old office

5th January, 2020

All employees

Moving to new Location

6th January, 2020

All employees

Readiness at New Location

7th January,2020

All employees

You now need to give a project update to your management. During this time the cost of fuel has gone up, your office manager has resigned and the project sponsor has said you need to cut back on your budget by 15%. Prepare an updated Risk Register and an updated Project Plan.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans. It is given in the question that cost of fuel has increased, the office manager has resigned and budget needs to be cut down by 15%.

Updated Risk Register

Risk Description Likelihood of occurring Impact Severity Responsible Person Action Taken
Rise in cost of fuel High Increase in overall cost of the shifting process High Project Manager Efficiency in consumption of fuel
Resignation of Office Manager High Delay in completion of project along with mismanagement Medium Office Manager Immediate recruitment of experienced manager
Reduction in budget by 15% High Entire planning process may have to be reiterated High Change Leader Reduce the budget to an optimal level
Updated Project Management Plan

Project Stage

Time

Responsible person(s)

Planning

1st January, 2020

Change Leader

Communication

1st January, 2020

Project Manager/ New Office Leader

Wrapping off at Old office

5th January, 2020

All employees

Moving to new Location

6th January, 2020

All employees

Readiness at New Location

7th January,2020

All employees

Add a comment
Know the answer?
Add Answer to:
The project you started and planned to move your accounts office from location A to location...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The project you started and planned to move your accounts office from location A to location...

    The project you started and planned to move your accounts office from location A to location B which is about 10 kilometers from your current location as shown below is going well. WORK BREAK DOWN STRUCTURE S. NO. WORK BREAK DOWN STRUCTURE 1 Office Location Move Plan 1.1 The detail move plan is made and reviewed with all employees 1.2 Employee readiness against the move plan. 2 Office Location Communication 2.1 Email communication to all employees 2.2 Notice board displayed...

  • ou are moving your accounts office from location A to location B. Your role is to...

    ou are moving your accounts office from location A to location B. Your role is to move staff and equipment into the building. You have a period of 1 month to do this. However, some of the staff are not happy with the organization of the office. In addition, the Chief Accountant is particularly belligerent about having his own office. In addition, some of the IT equipment was damaged during transportation – the heavy-duty office printer was damaged. In addition,...

  • You had been asked to move your accounts office from location A to location B which...

    You had been asked to move your accounts office from location A to location B which is about 10 kilometers from your current location. At last you are in your new office and everyone is happy. Prepare a Project Acceptance document and a Post-Project Review document for your project.

  • You had been asked to move your accounts office from location A to location B which...

    You had been asked to move your accounts office from location A to location B which is about 10 kilometers from your current location. At last you are in your new office and everyone is happy. Prepare a Project Acceptance document and a Post-Project Review document for your project.

  • Your organization is opening a new branch 150 kilometres north of the head office location and...

    Your organization is opening a new branch 150 kilometres north of the head office location and is anxious to attract skilled employees from the head office location to the new facility. In an attempt to attract interest, employees willing to permanently transfer to the new location are being offered a home purchase loan to assist with the costs of the move. The General Manager has asked you to prepare a memo explaining the the taxable benefit that could arise when...

  • Your organization is opening a new branch 150 kilometres north of the head office location and...

    Your organization is opening a new branch 150 kilometres north of the head office location and is anxious to attract skilled employees from the head office location to the new facility. In an attempt to attract interest, employees willing to permanently transfer to the new location are being offered a home purchase loan to assist with the costs of the move. The General Manager has asked you to prepare a memo explaining the the taxable benefit that could arise when...

  • Human Relations & Workforce Planning:For your final project, you need to write a 8-12 page.This project...

    Human Relations & Workforce Planning:For your final project, you need to write a 8-12 page.This project will require you to design a Human Relations Plan for an organization. The situation this company is facing and all facets you must consider will be in the assignments tab on Blackboard as well as the bottom of this syllabus. Your plan will use the major topics covered in this course to produce sound human relations practices. Keep in mind you will need to...

  • Project description: Your group has been approached by YESD Department to pack and move the offices...

    Project description: Your group has been approached by YESD Department to pack and move the offices of six YESD faculty/staff currently located in 3rd floor (Brand Hall) to the 4th floor (Brand Hall). Details of the project are as follows: Items include books, computers, printers and other miscellaneous items. Note that furniture i.e. desks, cabinets, bookshelves etc. do not have to be moved. Exact number of boxes of material to be packed/moved is ten per office. Number of boxes available...

  • Performance Improvement programs and effective project management require an understanding of the four phases of the...

    Performance Improvement programs and effective project management require an understanding of the four phases of the project life-cycle: initiation, planning, execution/implementation, and closure. It is important to have each phase of the project mapped on a timeline and to be sure the project team has the appropriate members with the right skills to ensure a successful program. Using a case study from the text, students will demonstrate their ability to review and evaluate a performance improvement program by arranging the...

  • You have been hired by a company to help them diversify their workforce -- your choose...

    You have been hired by a company to help them diversify their workforce -- your choose the type of company. Write a proposal to present to the Senior Management staff that addresses how to begin this diversification. Assume the business that has hired you is committed to training and education of people who have the talent, but may need some professional development, coaching, mentoring, etc.   The CEO and Vice President for Human Resources have met with you and made it...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT