Question

9.09 points Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during Apri, but not sold. Job C was started during Apni, but not completed. The job cost sheets revealed the following costs for April: Job AJob Bob Cl 12,000$1,000ANS Cost of Jobs in Process, 4/1/2016 Direct Materials Used Direct Labor Applied Manufacturing Overhead 2,000 10,000 8,000 8,000 9,000 3,000 Required: If no other jobs were started, completed, or sold, determine the balance in each of the following accounts at the end of April: a. Work in Process b. Finished Goods C.|Cost of Goods Sold
0 0
Add a comment Improve this question Transcribed image text
Answer #1

calculation of manufacturing overhead

S.No.

Particulars

Job A Job B Job C
I Total direct labor $10000 $8000 $3000
II Labor hours (I/20) 500 400 150
III

Total Manufacturing overhead ($15*II)

$7500 $6000 $2250

Total Cost incurred till April on each job

S. No. Particulars Job A Job B Job C
1 Cost at the beginning 12000 1000 -
2 Direct Material 2000 8000 9000
3 Direct Labor 10000 8000 3000
4 Manufacturing overhead 7500 6000 2250
5 Total cost (1+2+3+4) 31500 23000

14250

  1. job A was completed and was delivered to the customer hence, the cost allocated to Job A will be transferred to cost of goods sold.
  2. Job B was completed but was not sold so the cost allocated to job B will be transferred to finished goods account
  3. Job C was not yet completed so the total cost will be transferred to work in process account

Cost allocated to each account

S.No. Particulars Amount
1 Work In Process 14250
2 Finished Goods 23000
3 Cost Of Goods Sold 31500
Add a comment
Know the answer?
Add Answer to:
9.09 points Jenkins Company uses a job order cost system with overhead applied to jobs on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Help Save & Exit Homework 2 Check Jenkins Company uses a job order cost system with...

    Help Save & Exit Homework 2 Check Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hout, and the predetermined overhead rate is $15 per direct labor hout. The company worked on three jobs during April Jobs A and B were in process at the beginning of April Job A was completed and delivered to the customer. Job B was completed during...

  • apter 21 E2-11 (Algo) Calculating Cost of Jobs in Work in Process, Finished Goods, and Cost...

    apter 21 E2-11 (Algo) Calculating Cost of Jobs in Work in Process, Finished Goods, and Cost of Goods Sold [LO 2- Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April Jobs A and B were in process at the beginning of April....

  • E2-11 (Algo) Calculating Cost of Jobs in Work in Process, Finished Goods, and Cost of Goods...

    E2-11 (Algo) Calculating Cost of Jobs in Work in Process, Finished Goods, and Cost of Goods Sold [LO 2- Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT