Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates:
Machining | Finishing | Total | ||||
Estimated total machine-hours (MHs) | 9,000 | 8,000 | 17,000 | |||
Estimated total fixed manufacturing overhead cost | $ | 18,000 | $ | 7,800 | $ | 25,800 |
Estimated variable manufacturing overhead cost per MH | $ | 2.70 | $ | 5.00 | ||
During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data concerning those two jobs follow:
Job B | Job K | |||||
Direct materials | $ | 21,200 | $ | 7,800 | ||
Direct labor cost | $ | 21,000 | $ | 2,500 | ||
Machining machine-hours |
5,000 | 4,000 | ||||
Finishing machine-hours | 1,000 | 7,000 | ||||
Required:
a. Assume that the company uses a plantwide predetermined manufacturing overhead rate based on machine-hours. Calculate that overhead rate. (Round your answer to 2 decimal places.)
b. Assume that the company uses a plantwide predetermined manufacturing overhead rate based on machine-hours. Calculate the amount of manufacturing overhead applied to Job B. (Do not round intermediate calculations.)
c. Assume that the company uses a plantwide predetermined manufacturing overhead rate based on machine-hours. Calculate the amount of manufacturing overhead applied to Job K. (Do not round intermediate calculations. Round your answer to the nearest whole dollar amount.)
d. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both departments. What is the departmental predetermined overhead rate in the Machining department? (Round your answer to 2 decimal places.)
e. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both production departments. What is the departmental predetermined overhead rate in the Finishing department? (Round your answer to 2 decimal places.)
f. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both production departments. How much manufacturing overhead will be applied to Job B? (Do not round intermediate calculations.)
g. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both production departments. How much manufacturing overhead will be applied to Job K?. (Do not round intermediate calculations.)
Predetermined overhead rate per MH
Manufacturing overhead applied Job B
Manufacturing overhead applied Job K
Machine predetermined overhead rate per MH
Finishing predetermined overhead rate per MH
Manufacturing overhead applied to job B
Manufacturing overhead applied to job K
Machine predetermined overhead rate
a. Assume that the company uses a plantwide predetermined manufacturing overhead rate based on machine-hours. Calculate that overhead rate.
Predetermined overhead rate= Total manufacturing overhead/Total machine hours
= ($25800+9000*$2.70+8000*$5.00)/17000
= $5.30 per MH
b. Assume that the company uses a plantwide predetermined manufacturing overhead rate based on machine-hours. Calculate the amount of manufacturing overhead applied to Job B.
Manufacturing overhead applied to Job B= (5000+1000)*$5.30= $31800
c. Assume that the company uses a plantwide predetermined manufacturing overhead rate based on machine-hours. Calculate the amount of manufacturing overhead applied to Job K.
Manufacturing overhead applied to Job K= (4000+7000)*$5.30= $58300
d. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both departments. What is the departmental predetermined overhead rate in the Machining department?
Machine predetermined overhead rate= Total manufacturing overhead/Total machine hours
= ($18000+9000*$2.70)/9000= $4.70 per MH
e. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both production departments. What is the departmental predetermined overhead rate in the Finishing department?
Finishing predetermined overhead rate= Total manufacturing overhead/Total machine hours
= ($7800+8000*$5.00)/8000= $5.98 MH
f. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both production departments. How much manufacturing overhead will be applied to Job B?
Manufacturing overhead applied to Job B= 5000*$4.70+1000*$5.98= $29480
g. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both production departments. How much manufacturing overhead will be applied to Job K?.
Manufacturing overhead applied to Job K= 4000*$4.70+7000*$5.98= $60660
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 4,000 6,000 $ 5,200 $ 20,400 $ 1.50 $ 6.00 Total 10,000 $ 25,600 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 9,000 8,000 17,000 Estimated total fixed manufacturing overhead cost $ 18,000 $ 7,800 $ 25,800 Estimated variable manufacturing overhead cost per MH $ 2.70 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 6,000 5,000 $ 5,100 $ 39,200 $ 1.40 $ 2.00 Total 11,000 $ 44,300 During the most recent month, the company started and completed two jobs Job B and Job K. There were no beginning inventories....
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining 2,000 $ 2,400 $ 2.10 Finishing 8,000 $ 64,000 $ 6.00 Total 10,000 $ 66,400 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MH) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 6,000 5,000 $ 5,100 $ 39,200 $ 1.40 $ 2.00 Total 11,000 $ 44,300 During the most recent month, the company started and completed two jobs-Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 7,000 3,000 10,000 Estimated total fixed manufacturing overhead cost $ 8,400 $ 11,700 $ 20,100 Estimated variable manufacturing overhead cost per MH $ 3.00 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 5,000 5,000 $ 6,500 $ 29,500 $ 2.00 $ 4.00 Total 10,000 $ 36,000 During the most recent month, the company started and completed two jobs-- Job B and Job K. There were no beginning inventories....
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 7,000 3,000 10,000 Estimated total fixed manufacturing overhead cost $ 8,400 $ 11,700 $ 20,100 Estimated variable manufacturing overhead cost per MH $ 3.00 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 7,000 3,000 10,000 Estimated total fixed manufacturing overhead cost $ 8,400 $ 11,700 $ 20,100 Estimated variable manufacturing overhead cost per MH $ 3.00 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Hultquist Corporation has two manufacturing departments--Forming and Customizing. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Forming Customizing Total Estimated total machine-hours (MHs) 2,000 8,000 10,000 Estimated total fixed manufacturing overhead cost $ 6,400 $ 20,800 $ 27,200 Estimated variable manufacturing overhead cost per MH $ 1.50 $ 3.00 During the period, the company started and completed two jobs--Job C and Job L. Data concerning those two jobs follow: Job C...