A) plant wide overhead rate calculation
Particulars | Amount |
Variable overhead | |
- machining(6000*$1.4) | $8400 |
- finishing (5000*$2) | $10000 |
Fixed overhead | $44,300 |
Total overhead | $62,700 |
÷ total hours | 11000 hours |
Plant wide overhead rate | $5.7 per hour |
B) overhead applied to job B
= Total machine hours * overhead rate
= (4000+1000)*$5.7
=$28,500
C) overhead applied to job K
= (2000+4000)*$5.7
= $34,200
D) department overhead rate machining department
Overhead = (6000*$1.4) +$5100 = $13500
Rate = $13500/6000
= $2.25 per machining machine hour
E) finishing department
Overhead = (5000*$2) + $39,200
= $49,200
Rate = $49200/5000 = $9.84
F) job B
Machining department overhead = 4000*$2.25 = $9000
Finishing department = 1000*$9.84 = $9840
Total overhead = $18840
G) Job K
Machining = 2000*$2.25 = $4500
Finishing = 4000*$9.840 = $39,360
Total overhead = $43,860
Feel free to ask any queries..
Also plz upvote it means a lot ... Thank you
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 4,000 6,000 $ 5,200 $ 20,400 $ 1.50 $ 6.00 Total 10,000 $ 25,600 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining 2,000 $ 2,400 $ 2.10 Finishing 8,000 $ 64,000 $ 6.00 Total 10,000 $ 66,400 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 9,000 8,000 17,000 Estimated total fixed manufacturing overhead cost $ 18,000 $ 7,800 $ 25,800 Estimated variable manufacturing overhead cost per MH $ 2.70 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MH) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 6,000 5,000 $ 5,100 $ 39,200 $ 1.40 $ 2.00 Total 11,000 $ 44,300 During the most recent month, the company started and completed two jobs-Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 7,000 3,000 10,000 Estimated total fixed manufacturing overhead cost $ 8,400 $ 11,700 $ 20,100 Estimated variable manufacturing overhead cost per MH $ 3.00 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 5,000 5,000 $ 6,500 $ 29,500 $ 2.00 $ 4.00 Total 10,000 $ 36,000 During the most recent month, the company started and completed two jobs-- Job B and Job K. There were no beginning inventories....
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 9,000 8,000 17,000 Estimated total fixed manufacturing overhead cost $ 18,000 $ 7,800 $ 25,800 Estimated variable manufacturing overhead cost per MH $ 2.70 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 7,000 3,000 10,000 Estimated total fixed manufacturing overhead cost $ 8,400 $ 11,700 $ 20,100 Estimated variable manufacturing overhead cost per MH $ 3.00 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 7,000 3,000 10,000 Estimated total fixed manufacturing overhead cost $ 8,400 $ 11,700 $ 20,100 Estimated variable manufacturing overhead cost per MH $ 3.00 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Hultquist Corporation has two manufacturing departments-Forming and Customizing. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Forming 5,000 $10,500 $ 2.00 Customizing 5,000 $15,000 $ 4.00 Total 10,000 $25,500 During the period, the company started and completed two jobs-Job C and Job L. Data concerning those twojobs follow: Direct materials Direct labor cost Forming...