Answer:
PW=PV of all future cashflow+PV of Salavge value- Initial investment (P)
PV for equal cash flow each year= A*(1-(1+r)^-n)/r
PV of Salvage value=S/(1+r)^n
r=rate of interest
n=number of period
A=Net cash flow each year
S= salvage value
Net Cash flow A=Annual Income-Annual operating cost-Annual repair cost-Annual Maintenance cost
Since all the project has different life cycles so the comparison will be made over a time period equal to the least common multiple of the life spans of the alternatives. In this case the least common multiple of the life spans is 72 years.
For Alternative X
Since it has life =8 years
so there will 72/8=9 cycles of cash flow
Here A=35000-10000-0-11300=$13700
r=10%
n=8 years
P=$100,000
So NPV for 1 cycle= 13700*(1-(1+10%)^-8)/10%+60000/(1+10%)^8-100000=$1078.93
So NPV for 9 cycles = NPV+NPV/(1+10%)^8+NPV/(1+10%)^16+NPV/(1+10%)^24+NPV/(1+10%)^32+NPV/(1+10%)^40+NPV/(1+10%)^48+NPV/(1+10%)^56+NPV/(1+10%)^64
NPV for 9 cycles=1078.93+1078.9/(1+10%)^8+1078.93/(1+10%)^16+1078.93/(1+10%)^24+1078.93/(1+10%)^32+1078.93/(1+10%)^40+1078.93/(1+10%)^48+1078.93/(1+10%)^56+1078.93/(1+10%)^64
NPV for 9 cycles=$2020.27 Eq 1
For Alternative Y
Since it has life =12 years
so there will 72/12=6 cycles of cash flow
Here A=57800-7000-8000-18000=$24800
r=10%
n=12 years
P=$200,000
So NPV for 1 cycle= 24800*(1-(1+10%)^-12)/10%+100000/(1+10%)^12-200000=$842.63
So NPV for 6 cycles = NPV+NPV/(1+10%)^12+NPV/(1+10%)^24+NPV/(1+10%)^36+NPV/(1+10%)^48+NPV/(1+10%)^60
NPV for 6 cycles=842.63+842.6/(1+10%)^12+842.63/(1+10%)^24+842.63/(1+10%)^36+842.63/(1+10%)^48+842.63/(1+10%)^60
NPV for 6 cycles=$1235.40 Eq 2
For Alternative Z
Since it has life =128 years
so there will 72/18=4 cycles of cash flow
Here A=89000-12000-8000-35000=$34000
r=10%
n=18 years
P=$300,000
So NPV for 1 cycle= 34000*(1-(1+10%)^-18)/10%+120000/(1+10%)^18-300000=$431.07
So NPV for 4 cycles = NPV+NPV/(1+10%)^18+NPV/(1+10%)^36+NPV/(1+10%)^54
NPV for 4 cycles=431.07+431.07/(1+10%)^18+431.07/(1+10%)^36+431.07/(1+10%)^54
NPV for 4 cycles=$525.04 Eq 3
From equation 1 ,2, and 3 we find that alternate x has highest PW.
a) Cmpare altematives shown below on the basis of preent worth analysis Ue n rate of...
dt Moving to another question will save this response. Question Question 12 15 points For alternatives shown n the table below you are trying to decide which alternative you should choose based on their capitalized costs use an interest rate of 10% per year Machine A Machine B First cost (AED) Ansual maintenance cost per year, AFD 5000 20,000 240,000 2,300 Periodic cost every 10 years,AED 10,000 Salvage cost 2000 Lide, years Match the closest correct answers for the below...