The direct materials budget shows: Units to be produced; 3,000 units Total pounds needed for production; 6,000 pounds Total materials required; 6,600 What are the direct materials per unit? (Hint: Don't make this hard!) |
1.08 pounds.
2.0 pounds.
2.2 pounds
Cannot be determined from
the data given.
The following information was taken from Sloan Company's cash
budget for the month of July:
Beginning Cash Balance; $90,000
Cash Receipts; $57,000
Cash Disbursements; $102,000
If the company has a policy of maintaining a minimum end of the
month cash balance of $75,000, the amount the company would have to
borrow is
$30,000.
$15,000.
$45,000.
$18,000
The following credit sales are budgeted by Roswell
Company:
January; $34,000
February; $50,000
March; $70,000
April; $60,000
The company's past experience indicates that 70% of the accounts
receivable are collected in the month of sale, 20% in the month
following the sale; and 8% in the second month following the sale.
The anticipated cash inflow for the month of April is
$61,720.
$56,000.
$60,000.
$58,800.
The direct materials budget shows: Desired ending direct materials; 12,000 pounds Total materials required; 18,000 pounds Direct materials purchases; 15,800 pounds The total direct materials needed for production is |
6,000 pounds.
2,200 pounds.
3,800 pounds.
33,800 pounds.
Solution:
1.) 2 pounds.
Direct materials per unit in pounds = Total pounds needed / Units to be produced.
Direct materials per unit in pounds = 6,000/3,000 = 2pounds.
2.) $30,000.
Borrowings = Cash required at the end of the month - Cash at the beginning - Cash receipts + Cash disbursements.
Borrowings = $75,000 - $90,000 - $57,000 + $102,000 = $30,000.
3.) $60,000.
Anticipated Cashflow in April = 8% of February Sales + 20% of March Sales + 70% of April Sales.
Anticipated Cashflow in April
= [(8%) * ($50,000)] + [(20%) * ($70,000)] + [(70%) * ($60,000)]
= $4,000 + $14,000 + $42,000
= $60,000.
The direct materials budget shows: Units to be produced; 3,000 units Total pounds needed for production;...
The direct materials budget shows: Desired ending direct materials 48,000 pounds Total materials required 72,000 pounds Direct materials purchases 63,200 pounds The total direct materials needed for production is Answer
zira Co Direct Materials budget Each finished unit requires five pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 1041 pounds. Assume direct materials cost $4 per pound Prepare a direct materials budget for April, May, and June (Round your intermediate calculations and final answers to the nearest whole dollar amount.) ZIRA CO. Direct Materials Budget For April,...
Exercise 07-4 Manufacturing: Direct materials budget LO P1 Zira Co. reports the following production budget for the next four months. April May 615 June July 587 Production (units) 574 607 Each finished unit requires five pounds of raw materials and the company wants to end each month with raw materials inventory equal to 40% of next month's production needs. Beginning raw materials inventory for April was 1,148 pounds. Assume direct materials cost $4 per pound. Prepare a direct materials budget...
Direct Labor Budget Evans Company produces asphalt roofing materials. The production budget in bundles for Evans' most popular weight of asphalt shingle is shown for the following months: Units March 6,000 April 19,500 May 21,600 25,500 June Each bundle produced requires (on average) 0.40 direct labor hours. The average cost of direct labor is $30 per hour. Required: Prepare a direct labor budget for March, April, and May, showing the hours needed and the direct labor cost for each month...
Exercise 07-4 Manufacturing: Direct materials budget LO P1 Zira Co. reports the following production budget for the next four months April 536 Production (units) May 590 June 568 July 548 Each finished unit requires six pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 965 pounds. Assume direct materials cost $4 per pound Prepare a direct materials budget...
Zira Co. reports the following production budget for the next four months. Production (units) April 455 May 570 June 560 July 540 Each finished unit requires five pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 663 pounds. Assume direct materials cost $4 per pound. Prepare a direct materials budget for April, May, and June. ZIRA CO. Direct...
Zira Co. reports the following production budget for the next four months. Production (units) April 632 May 662 June 666 July 646 Each finished unit requires four pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 758 pounds. Assume direct materials cost $4 per pound Prepare a direct materials budget for April, May, and June (Round your intermediate...
Zira Co. reports the following production budget for the next four months. Production (units) April 584 May 625 June 617 July 597 Each finished unit requires five pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 876 pounds. Assume direct materials cost $5 per pound Prepare a direct materials budget for April, May, and June. (Round your intermediate...
Tableau DA 20-1: Quick Study, Direct materials budget LO P1 Delray Manufacturing needs to better budget and analyze costs. While Delray has experienced high sales growth, it has struggled to effectively manage costs and inventories. Delray aims to end each month with direct materials inventory equal to 40% of next month's production needs. Each finished unit requires 4 pounds of direct materials and 2 hours of direct labor. Delray budgets $12,000 of fixed overhead costs per month. A Tableau Dashboard...
Zira Co. reports the following production budget for the next four months. Production (units) April 624 May 665 June 657 July 637 Each finished unit requires four pounds of raw materials and the company wants to end each month with raw materials inventory equal to 30% of next month's production needs. Beginning raw materials inventory for April was 749 pounds. Assume direct materials cost $3 per pound. Prepare a direct materials budget for April, May, and June. (Round your intermediate...