Question

0.33/1 Question 6 View Policies Show Attempt History Current Attempt in Progress Whispering Corporation accumulates the follo
List of Accounts Attempts: 2 of 15 used (6) Compute the total overhead variance. Total overhead variance $ e Textbook and Med
0 0
Add a comment Improve this question Transcribed image text
Answer #1

total overhead variance = manufacturing overhead incurred - manufacturing overhead applied

= $211720 - $214320

= $2600 Favorable

Add a comment
Know the answer?
Add Answer to:
0.33/1 Question 6 View Policies Show Attempt History Current Attempt in Progress Whispering Corporation accumulates the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the...

    Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard $2.10 11,400 $169,860 14,900 $211,720 $2.00 11,000 $165,680 15,200 Raw materials unit cost Raw materials units Direct labor payroll Direct labor hours Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.10 $1.90 Raw materials units used 11,300 10,700 Direct labor payroll $175,500 $171,360 Direct labor hours worked 15,000 15,300 Manufacturing overhead incurred $212,930 Manufacturing overhead applied $215,730 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $73,950 Variable overhead rate per machine hour $3.00 Fixed overhead...

  • Sarasota Corporation accumulates the following data relative to jobs started and finished during the month of...

    Sarasota Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.15 Raw materials units used 11,400 10,500 Direct labor payroll $172,840 $168,720 Direct labor hours worked 14,900 15,200 Manufacturing overhead incurred $223,276 Manufacturing overhead applied $226,176 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $73,950 Variable overhead rate per machine hour $3.10 Fixed overhead...

  • Sarasota Corporation accumulates the following data relative to jobs started and finished during the month of...

    Sarasota Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.15 Raw materials units used 11,400 10,500 Direct labor payroll $172,840 $168,720 Direct labor hours worked 14,900 15,200 Manufacturing overhead incurred $223,276 Manufacturing overhead applied $226,176 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $73,950 Variable overhead rate per machine hour $3.10 Fixed overhead...

  • Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of...

    Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.20 Raw materials units 11,100 10,300 Direct labor payroll $170,200 $164,160 15,200 Direct labor hours 14,800 $202.600 Manufacturing overhead incurred $205,200 Manufacturing overhead applied Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

  • Problem 23-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and...

    Problem 23-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017 CALCULATOR PRINTER VERSION Standard Costs and Production Data Raw materials unit cost Raw materials units used Direct labor payroll Direct labor hours worked Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour Actual $2.20...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.20 $2.00 Raw materials units used 11,200 10,300 Direct labor payroll $175,820 $169,830 Direct labor hours worked 14,900 15,300 Manufacturing overhead incurred $202,750 Manufacturing overhead applied $206,550 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017 Costs and Production Data Raw materials unit cost Raw materials units used Direct labor payroll Direct labor hours worked Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour Actual Standard $2.10 $1.90 11,300 10,700 $175,500 $171,360 15.000 15.300 $212,930...

  • Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the...

    Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Raw materials unit cost Raw materials units Direct labor payroll Direct labor hours Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour Actual $2.20 11,300 $166,500 15,000 $210,420 Standard $2.10 10,900 $159,600 15,200...

  • Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of...

    Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.20 Raw materials units 11,100 10,300 Direct labor payroll $170,200 $164,160 Direct labor hours 14,800 15,200 Manufacturing overhead incurred $202,600 Manufacturing overhead applied $205,200 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT