Question

Exercise 14-12 a-b (Video) Marigold Corporation has the following cost records for June 2020. Indirect factory labor Direct mTotal Manufacturing Overhead 16060 Total Manufacturing Costs 80440 Total Cost of Work in Process 83690 Less . Work in Process Please show work on how to calculate Cost of Goods Available for Sale and Cost of Goods Manufactured!

0 0
Add a comment Improve this question Transcribed image text
Answer #1
MARIGOLD CORPORATION
Cost of Goods Manufactured Schedule
Fot the Month Ended June 30, 2020
Work in process inventory, June 1 $3,250
Direct Materials used $21,980
Direct labor $42,400
Manufacturing Overhead:
        Indirect labor                                                              $5,490
        Indirect material $2,930
        Factory manager's salary $3,770
        Maintenance, Factory equipment $1,880
        Depreciation, Factory equipment $1,500
        Factory utilities             $490
    Total manufacturing overhead $16,060
Total manufacturing costs                          [$21,980 + $42,400 + $16,060] $80,440
Total Cost of work in Process                    [$3,250 + $80,440] $83,690
Less: Work in process inventory, June 30 $4,400
Cost of Goods Manufactured $79,290

.

.

MARIGOLD CORPORATION
Income Statment
Fot the Month Ended June 30, 2020
Sales revenue. $89,230
Cost of goods sold:
   Finished goods inventory, June 1 $5,550
   Cost of Goods Manufactured                       [Refer Cost of Goods Manufactured schedule] $79,290
   Cost of Goods Available for Sale               [$5,550 + $79,290] $84,840
   Less: Finished goods inventory, June 30 $7,830
Cost of goods sold $77,010
Gross profit on sales                                       [$89,230 - $77,010] $12,220
Add a comment
Know the answer?
Add Answer to:
Please show work on how to calculate Cost of Goods Available for Sale and Cost of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 4 View Policies Current Attempt in Progress Cepeda Corporation has the following cost records for...

    Question 4 View Policies Current Attempt in Progress Cepeda Corporation has the following cost records for June 2020. $4,690 Factory utilities $430 Indirect factory labor Direct materials used 22,410 Depreciation, factory equipment 1,770 Work in process, 6/1/20 3,970 Direct labor 42,100 Work in process, 6/30/20 1.910 4.410 5,650 Maintenance, factory equipment Indirect materials Finished goods, 6/1/20 2,810 Finished goods, 6/30/20 8,030 Factory manager's salary 3,930 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods...

  • Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct materials used...

    Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct materials used Work in process, 6/1/20 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 $4,750 21,330 3,400 4,540 6,090 8,470 Factory utilities Depreciation, factory equipment Direct labor Maintenance, factory equipment Indirect materials Factory manager's salary $440 1,590 42,300 1,900 2,140 3,360 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule For the Year Ended June 30,...

  • part B) Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,690...

    part B) Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,690 Factory utilities $430 Direct materials used 22,410 Depreciation factory equipment 1,770 Work in process, 6/1/20 3,970 Direct labor 42,100 Work in process, 6/30/20 4,410 Maintenance, factory equipment 1,910 2,810 Finished goods, 6/1/20 Finished goods, 6/30/20 5,650 Indirect materials 8,030 Factory manager's salary 3,930 Your Answer Correct Answer Your answer is correct. Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost...

  • Exercise 19-12 a-b (Part Level Submission) Lily Corporation has the following cost records for June 2020. Indirect fa...

    Exercise 19-12 a-b (Part Level Submission) Lily Corporation has the following cost records for June 2020. Indirect factory labor $5,490 Factory utilities $490 Direct materials used 21,980 Depreciation, factory equipment 1,500 Work in process, 6/1/20 3,250 Direct labor 42,400 Work in process, 6/30/20 4,400 Maintenance, factory equipment 1,880 Finished goods, 6/1/20 5,550 Indirect materials 2,930 Finished goods, 6/30/20 7,830 Factory manager’s salary 3,770 Prepare a cost of goods manufactured schedule for June 2020. LILY CORPORATION Cost of Goods Manufactured Schedule...

  • Please assist with part B. The red boxes are wrong. Thank you! Current Attempt in Progress...

    Please assist with part B. The red boxes are wrong. Thank you! Current Attempt in Progress Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $5,420 Factory utilities $410 Direct materials used 22,300 Depreciation, factory equipment 1,560 Work in process, 6/1/20 3,620 Direct labor 42,630 Work in process, 6/30/20 4,630 Maintenance, factory equipment 1,990 Finished goods, 6/1/20 5,310 Indirect materials 2,120 Finished goods, 6/30/20 8 ,420 Factory manager's salary 3,150 CEPEDA CORPORATION Cost of Goods Manufactured...

  • Blue Corporation has the following cost records for June 2017. Indirect factory labor Direct materials used...

    Blue Corporation has the following cost records for June 2017. Indirect factory labor Direct materials used Work in process, 6/1/17 Work in process, 6/30/17 Finished goods, 6/1/17 Finished goods, 6/30/17 $5,220 Factory utilities 22,500 Depreciation, factory equipment 3,820 Direct labor 4,360 Maintenance, factory equipment 5,420 Indirect materials 8,300 Factory manager's salary $510 1,720 42,400 1,960 2,430 3,980 Prepare a cost of goods manufactured schedule for June 2017 BLUE CORPORATION Cost of Goods Manufactured Schedule For the Year Ended June 30,...

  • pt. B *Exercise 19-12 a-b (Part Level Submission) Sunland Corporation has the following cost records for...

    pt. B *Exercise 19-12 a-b (Part Level Submission) Sunland Corporation has the following cost records for June 2020. Indirect factory labor $5,420 Factory utilities Direct materials used 22,300 Depreciation, factory equipment Work in process, 6/1/20 3,620 Direct labor Work in process, 6/30/20 4,630 Maintenance, factory equipment Finished goods, 6/1/20 5,310 Indirect materials Finished goods, 6/30/20 8,420 Factory manager's salary $410 1,560 42,630 1,990 2,120 3,150 *(a) Your answer is correct. Prepare a cost of goods manufactured schedule for June 2020....

  • Question 7 Unitas Corporation has the following cost records for June 2020: Indirect factory labour $5,000...

    Question 7 Unitas Corporation has the following cost records for June 2020: Indirect factory labour $5,000 Factory utilities Direct materials used 25,200 Depreciation, factory equipment Work in process (6/1/20) 3,350 Direct labeur Work in process (6/30/20) 3,300 Maintenance, factory equipment Finished goods (6/1/20) 5,400 Indirect materials Finished goods (6/30/20) 8,850 Factory manager's salary $600 1,700 30,000 1,800 2,400 3,300 • Question 7 500g Your answer is correct. Prepare a cost of goods manufactured schedule for June 2020. UNITAS CORPORATION Cost...

  • Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,600 Factory utilities...

    Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,600 Factory utilities $410 1.500 Direct materials used 21,000 Depreciation, factory equipment 41,000 Work in process. 6/1/20 Work in process, 6/30/20 3,100 Direct labor 3.900 Maintenance, factory equipment 1.810 Finished goods, 6/1/20 Finished goods, 6/30/20 5.100 7,600 Indirect materials Factory manager's salary 2,100 3,100 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule

  • Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $5.330 Factory utilities...

    Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $5.330 Factory utilities $440 Direct materials used Work in process, 6/1/20 22,580 3,910 Depreciation, factory equipment Direct labor 1,640 42,770 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 4,680 5,510 ,270 Maintenance, factory equipment Indirect materials Factory manager's salary 1,940 2.430 3.210 8 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT