Question

Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $260,000, and...

Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $260,000, and budgeted direct labor hours were 20,000. The average wage rate for direct labor is expected to be $25 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow:

Job 39 Job 40 Job 41 Job 42
Beginning balance $23,700 $34,600 $17,000 $0
Materials requisitioned 18,900 21,400 8,350 12,000
Direct labor cost 10,000 18,500 3,000 2,900

Overhead is assigned as a percentage of direct labor cost. During June, Jobs 39 and 40 were completed; Job 39 was sold at 130 percent of cost. (Naranjo had originally developed Job 40 to order for a customer; however, that customer was near bankruptcy and the chance of Naranjo being paid was growing dimmer. Naranjo decided to hold Job 40 in inventory while the customer worked out its financial difficulties. Job 40 is the only job in Finished Goods Inventory.) Jobs 41 and 42 remain unfinished at the end of the month.

Required:

1. Calculate the overhead rate based on direct labor cost.

% of direct labor cost

2. Set up a simple job-order cost sheet for all jobs in process during June. If an amount is zero, enter "0".

Naranjo Company
Job-Order Cost Sheets
Job 39 Job 40 Job 41 Job 42
Balance, June 1 $ $ $ $
Total $ $ $ $

3. What if the expected direct labor rate at the beginning of the year was $20 instead of $25? What would the overhead rate be?

New budgeted direct labor cost = $

New overhead rate = % of direct labor cost

How would the cost of the jobs be affected?

1 0
Add a comment Improve this question Transcribed image text
Answer #1

PART-1) Solution: 0.52

Working: Budgeted direct labor cost = average wage rate for direct labor x budgeted direct labor hours 25*20,000

Overhead rate = budgeted overhead costs ÷ budgeted direct labor cost = 260,000 / 500,000 = 0.52

PART-2)

Job 39

Job 40

Job 41

Job 42

Beginning balance

$23,700

$34,600

$17,000

$0

Material requisitioned

$18,900

$21,400

$8,350

$12,000

Direct labor cost

$10,000

$18,500

$3,000

$2,900

Applied Overhead

$5,200

$9,620

$1,560

$1,508

Total cost

$57,800

$84,120

$29,910

$16,408

Part-3) What would the overhead rate be? $1

Working: =260000/(20*20000)

Add a comment
Answer #2

3. What if the expected direct labor rate at the beginning of the year was $20 instead of $25? What would the overhead rate be?

New budgeted direct labor cost = $

New overhead rate = % of direct labor cost

How would the cost of the jobs be affected?

Applied overhead would increase 

Workout: 

New budgeted direct labor cost= 20*200,000

New overhead rate= 260,000/(20*200,000)
source: Notes
answered by: Stephanie
Add a comment
Know the answer?
Add Answer to:
Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $260,000, and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $260,000, and budgeted direct labor hours were 20,000. The average wage rate for direct labor is expected to be $25 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $23,700 $34,600 $17,000 $0 Materials requisitioned 18,900 21,400 8,350 12,000 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $260,000, and budgeted direct labor hours were 20,000. The average wage rate for direct labor is expected to be $25 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $23,700 $34,600 $17,000 $0 12,000 Materials requisitioned 8,350 18,900 10,000 21,400 18,000...

  • Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $280,000, and...

    Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $280,000, and budgeted direct labor hours were 15,000. The average wage rate for direct labor is expected to be $35 per hour. During June, Naranjo Compa four jobs, Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance Materials requisitioned Direct labor cost Overhead is assigned as a percentage of direct labor cost. During June, Jobs 39 and 40...

  • Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $490,000, and...

    Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $490,000, and budgeted direct labor hours were 28,000. The average wage rate for direct labor is expected to be $35 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 $0 Beginning balance Materials requisitioned Direct labor cost 24,600 $35,500 $15,000 20,300 22,000 11,300 15,500 11,400 19,100 5,90 6,400 Overhead is...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $280,000, and budgeted direct labor hours were 16,000. The average wage rate for direct labor is expected to be $35 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $22,700 $35,500 $15,800 $1,700 Materials requisitioned 20,100 21,000 10,300 15,600 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $385,000, and budgeted direct labor hours were 22,000. The average wage rate for direct labor is expected to be $35 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $26,200 $36,000 $15,900 $1,200 Materials requisitioned 16,600 21,400 8,700 14,400 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $180,000, and budgeted direct labor hours were 18,000. The average wage rate for direct labor is expected to be $20 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $26,600 $34,200 $15,600 $1,700 Materials requisitioned 16,700 23,400 10,800 12,100 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $367,500, and budgeted direct labor hours were 21,000. The average wage rate for direct labor is expected to be $35 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $25,300 $34,300 $15,500 $1,100 Materials requisitioned 20,100 23,800 8,300 12,400 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $390,000, and budgeted direct labor hours were 26,000. The average wage rate for direct labor is expected to be $30 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $23,300 $34,800 $19,700 $500 Materials requisitioned 19,800 20,400 10,600 12,600 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $360,000, and budgeted direct labor hours were 24,000. The average wage rate for direct labor is expected to be $30 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $25,500 $32,900 $16,800 $1,400 Materials requisitioned 19,400 23,400 8,700 15,700 Direct labor...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT