Question

C&A uses two steps to make a toy. Step 1 takes 20 seconds. Step 2 takes...

C&A uses two steps to make a toy. Step 1 takes 20 seconds. Step 2 takes 15 seconds. Each step is staffed by one worker, for a total of two workers. Each worker is paid $15 per hour. Each toy is sold for $20. Material costs are $5 per toy and fixed costs are $500 per hour. Assume demand is unlimited. What will be the impact on C&A’s profit per hour if the processing time of step 2 is reduced to 10 seconds?

No impact on profit

124% decrease

Cannot be determined

124% increase

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Step 1 takes 20 seconds and is the bottleneck step with maximum time. This step determines the process capacity and how many toys will be produced.

Given the reduction happens in Step 2, there will be no impact on how much demand we can meet. Hence, there will be no impact on profit.

Add a comment
Know the answer?
Add Answer to:
C&A uses two steps to make a toy. Step 1 takes 20 seconds. Step 2 takes...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Atlas Inc. is a toy bicycle manufacturing company producing a five-inch small version of the bike...

    Atlas Inc. is a toy bicycle manufacturing company producing a five-inch small version of the bike that Lance Armstrong rode to win his first Tour de France. The assembly line at Atlas Inc. consists of seven work stations, each performing a single step. Stations and processing times are summarized here: Step 1 (30 sec.): The plastic tube for the frame is cut to size. Step 2 (20 sec.): The tube is put together. Step 3 (35 sec.): The frame is...

  • Help Save Saw Homework Asas Inc. is a toy bicycle manufacturing company producing a five-inch small...

    Help Save Saw Homework Asas Inc. is a toy bicycle manufacturing company producing a five-inch small version of the bike that Lance Armstrong rode to win his first Tour de France. The assembly line at Atlas Inc. consists of seven workstations, each performing a single step. Stations and processing times are summarized here: • Step 1 (30 sec.) The plastic tube for the frame is cut to size. . Step 2 125 sec.) The tube is put together Step 3...

  • Atlas Inc. is a toy bicycle manufacturing company producing a five-inch small version of the bike...

    Atlas Inc. is a toy bicycle manufacturing company producing a five-inch small version of the bike that Lance Armstrong rode to win his first Tour de France. The assembly line at Atlas Inc. consists of seven work stations, each performing a single step. Stations and processing times are summarized here:             • Step 1 (25 sec.): The plastic tube for the frame is cut to size.                    • Step 2 (25 sec.): The tube is put together.                                      • Step 3 (20 sec.):...

  • Atlas Inc. is a toy bicycle manufacturing company producing a five inch small version of the...

    Atlas Inc. is a toy bicycle manufacturing company producing a five inch small version of the bike that Lance Armstrong rode to win his first Tour de France. The assembly line at Atlas Inc. consists of seven work stations, each performing a single step. Stations and processing times are summarized here: Step 1 (50 sec.): The plastic tube for the frame is cut to size. Step 2 (40 sec.): The tube is put together. Step 3 (55 sec.): The frame...

  • 2. Consider the following batch flow process consisting of three process steps performed by three machines: Step 1 Step...

    2. Consider the following batch flow process consisting of three process steps performed by three machines: Step 1 Step 3 Step 2 Processing time 1 minute/part Processing time 1.5 minute/part Processing time 2 minute/part Setup time No Setup No Setup 20 minutes Work is processed in batch at each step. Before a batch is processed at step 1, the machine has to be set up. During There are no inventory buffers between steps. a setup, the machine is unable to...

  • Modern Toy Company produces two models of toy cars, Top car and Juu car. Important information...

    Modern Toy Company produces two models of toy cars, Top car and Juu car. Important information is given as follows:-                                                                                                 Top car                        Juu car Selling price per unit                                                                    100                               70 Costs per unit: Direct material costs                                                                      28                               13 Direct manufacturing labour costs                                                 15                               25 Variable manufacturing overhead*                                                25                               12 Fixed manufacturing overhead*                                                    10                                 5 Marketing costs (all variable)                                                         14                               10 Total costs                                                                                     92                        ...

  • Two-step Process Utilization: A two- used to finish a product: painting and drying. There are 5 workers and each one ta...

    Two-step Process Utilization: A two- used to finish a product: painting and drying. There are 5 workers and each one takes an average of 60 minutes to paint each unit. Drying takes place in an oven that can hold up to 100 units and it takes 5 minutes to load each unit. Once all the units are loaded into the oven, it takes 6 hours to dry each load. Assume that the process is capacity constrained (so the demand rate...

  • Problem 4 Frank’s Fine Furniture makes tables, desks, bookcases, and other office furniture. At the North...

    Problem 4 Frank’s Fine Furniture makes tables, desks, bookcases, and other office furniture. At the North California facility, they make tables. All parts of the table are purchased except for the tabletop that is fabricated at the plant. Tables are made to order for dealers who FAX orders into the sales department. Orders are processed from the order database on FIFO basis. The first step in the process is to cut the top ¾ pressboard. It takes one worker 20...

  • Fresh out of school, you take a job with a small injection-molding shop with two machines...

    Fresh out of school, you take a job with a small injection-molding shop with two machines (25 ton and 250 ton. On any given shift, there are two workers assigned to each machine one is concerned with setting/loading and unloading while the other packages the final product for shipping. You have been asked to investigate whether you can improve the process, potentially with automation. Having recently re-read The Goal, you are quite aware that adding robots does not necessarily mean...

  • j Canine Kennels Company (CKC) manufactures two different types of dog chew toys (A and B,...

    j Canine Kennels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see the figure below). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product's price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT