Question

Direct labor or machine hours may not be the appropriate cost driver for overhead in all areas of manufacturing due to the coUsing the following information, determine the overhead rates and the actual cost assigned for each of the activity cost poolHow would you classify each of the following activities by level-unit level, batch level, product level, or facility level? T

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER

Statement showing Overhead rates and the actual cost assigned under ABC Costing

Activity Cost Pools

Cost Drivers

Estimated Overhead

Expected Cost Drivers

Activity based overhead rates

Actual No. Of Cost Drivers involved

Actual cost assigned

A

B

C = B/A

D

E = C x D

Irrigation Installation

Labor cost

1,928,440

13,030

148

13,010

1,925,480

Machining

Machine Hours

1,668,750

33,375,000

0

33,376,000

1,668,800

Customers orders

Number of orders

28,600

2,600

11

2,562

28,182

Shipping

none

NA

NA

NA

NA

NA

Design

Cost per design

763

7

109

6

654

Selling

number of sales calls

306,000

20,400

15

20,610

309,150

Under ABC costing there are 4 types of activities, namely

  1. Unit level activities: - These are incurred each and every time a product is performed.
  2. Batch level activities:- These are incurred on the basis of batch designated for the production of product or provision of services.
  3. Product level activities:- These costs are differentiated on the basis of different products. In other words, there costs are product specific.
  4. Facility level activities:- These are not product specific, rather these are the actions taken to maintain the operations of business

Based on the above definition, activities have been classified as: -

Activities

Level of activity

Testing of products (if all items are tested)

Unit Level

Testing of products (if all items are not tested)

Batch Level

Designing new products

Product Level

Packaging

Facility Level

Molding

Product Level

Assembling

Product Level

Depreciation

Facility Level

Machine Maintenance

Facility Level

Advertising

Facility Level

Equipment Setups

Batch Level

Electricity required to run equipment

Facility Level

Requisitioning Materials

Unit Level

Note: - Classification may change subject to difference in opinion and assumption supporting the classification.

Add a comment
Know the answer?
Add Answer to:
Direct labor or machine hours may not be the appropriate cost driver for overhead in all...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Direct labor or machine hours may not be the appropriate cost driver for overhead in all...

    Direct labor or machine hours may not be the appropriate cost driver for overhead in all areas of manufacturing due to the complexities of many manufacturing processes. Many companies use activity-based costing (ABC) which uses multiple drivers (items that consume resources) rather than just one driver to apply overhead to their activities. With ABC, a company can use a cost driver that has a direct cause/effect relationship in its applied overhead costs. Waterways looked into ABC as a method of...

  • Direct labor or machine hours may not be the appropriate cost driver for overhead in all...

    Direct labor or machine hours may not be the appropriate cost driver for overhead in all areas of manufacturing due to the complexities of many manufacturing processes. Many companies use activity-based costing (ABC) which uses multiple drivers (items that consume resources) rather than just one driver to apply overhead to their activities. With ABC, a company can use a cost driver that has a direct cause/effect relationship in its applied overhead costs. Waterways looked into ABC as a method of...

  • QUESTION 19 Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are...

    QUESTION 19 Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100,000 for the year Activity Cost Cost Driver Pool Ordering and Orders Receiving Machine Setup Setups Machining Assembly Inspection Cost Driver Activity Est. Overhead $120,000 500 orders 450 setups 1,500,000 125,000 MH 1,200,000 1,000,000 parts 500 inspections 297,000 Machine hours Parts |Inspections 300,000 If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $1.20 per direct...

  • Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at...

    Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year.     Activity Cost Pool         Cost Driver         Est. Overhead         Cost Driver Activity     Ordering and Receiving Orders $   65000 500 orders Machine Setup Setups 247500 450 setups Machining Machine hours 1362500 125000 MH Assembly Parts 1090000 1000000 parts Inspection Inspections 245000 500 inspections If overhead is applied using traditional costing based on direct labor hours, the overhead application rate is a. $8. b. $30....

  • Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at...

    Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100,000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $ 120,000 500 orders Machine Setup Setups 297,000 450 setups Machining Machine hours 1,500,000 125,000 MH Assembly Parts 1,200,000 1,000,000 parts Inspection Inspections 300,000 500 inspections If overhead is applied using traditional costing based on direct labor hours, the overhead application rate is $15.00. $34.17. $9.60....

  • Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at...

    Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $   95000 500 orders Machine Setup Setups 274500 450 setups Machining Machine hours 1437500 125000 MH Assembly Parts 1150000 1000000 parts Inspection Inspections 275000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $0.10 per part. $6464 per...

  • Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at...

    Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $   135000 500 orders Machine Setup Setups 310500 450 setups Machining Machine hours 1550000 125000 MH Assembly Parts 1230000 1000000 parts Inspection Inspections 315000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $7081 per order. $0.14 per...

  • Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at...

    Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $   110000 500 orders Machine Setup Setups 288000 450 setups Machining Machine hours 1475000 125000 MH Assembly Parts 1180000 1000000 parts Inspection Inspections 290000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $220 per order. $6686 per...

  • x Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated...

    x Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100,000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $ 120,000 500 orders Machine Setup Setups 297,000 450 setups Machining Machine hours 1,500,000 125,000 MH Assembly Parts 1,200,000 1,000,000 parts Inspection Inspections 300,000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is Selected Answer: A....

  • Current Attempt in Progress Tidwell Industries has the following overhead costs and cost drivers. Direct labor...

    Current Attempt in Progress Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Cost Driver Cost Driver Activity Est. Overhead $ 150000 Orders 500 orders Activity Cost Pool Ordering and Receiving Machine Setup Machining Assembly Inspection Setups Machine hours Parts Inspections 324000 1587500 1260000 330000 450 setups 125000 MH 1000000 parts 500 inspections If overhead is applied using traditional costing based on direct labor hours, the overhead application rate...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT