Answer:
Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction...
Required information (The following information applies to the questions displayed below. In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 2,044,000 5,256,000 2,170,000 1,885,000 2022 2023 $2,628,000 $2,890,800 2,628,000 2,502,0005 , 328,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,044,000 5, 256,000 2,170,000 1,885,000 2022 2023 $2,628,000 $2,890, 800 2,628,000 2,502,0005, 328,000 2,600,0005,515,000 Westgate recognizes revenue over time according to percentage of completion....
Required information
[The following information applies to the questions
displayed below.]
In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
2021
2022
2023
Cost incurred during the year
$
2,604,000
$
4,032,000
$
1,940,400
Estimated costs to complete as of year-end
5,796,000
1,764,000
0
Billings during the year
2,040,000
4,596,000
3,364,000
Cash collections during the...
Required information
[The following information applies to the questions
displayed below.]
In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
2021
2022
2023
Cost incurred during the year
$
2,604,000
$
4,032,000
$
1,940,400
Estimated costs to complete as of year-end
5,796,000
1,764,000
0
Billings during the year
2,040,000
4,596,000
3,364,000
Cash collections during the...
Required information
[The following information applies to the questions
displayed below.]
In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
2021
2022
2023
Cost incurred during the year
$
2,604,000
$
4,032,000
$
1,940,400
Estimated costs to complete as of year-end
5,796,000
1,764,000
0
Billings during the year
2,040,000
4,596,000
3,364,000
Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,175,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,580,000 6,020,000 2,060,000 1,830,000 2022 $4,042,000 1,978,000 4,562,000 4,200,000 3,378,000 3,970,000...
Required information [The following information applies to the
questions displayed below.] In 2021, the Westgate Construction
Company entered into a contract to construct a road for Santa Clara
County for $10,000,000. The road was completed in 2023. Information
related to the contract is as follows: 2021 2022 2023 Cost incurred
during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs
to complete as of year-end 5,184,000 2,376,000 0 Billings during
the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
Required information (The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 2023 $3,600,000 $2,200,000 2,000,000 0 4,000,000 4,000,000 3,600,000...