It is required to fine grade the base of a roadway before proceeding to construct the pavement section. Use an efficiency factor of 0.65. The grader will be operated in second gear (3.4 mph) for this work. The effective blade width per pass is 8 ft. To meet the 10mm/m specification it will be necessary to make four passes on an area. Estimate the production rate for these conditions.