Problem

Computing Predetermined Overhead Rates and Job CostsKody Corporation uses a job-order cost...

Computing Predetermined Overhead Rates and Job Costs

Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates:

Machine-hours required to support estimated production

150,000

Fixed manufacturing overhead cost

$750,000

Variable manufacturing overhead cost per machine-hour

$4.00

Required:

1. Compute the predetermined overhead rate.

2. During the year Job 500 was started and completed. The following information was available with respect to this job:

Direct materials requisitioned

$350

Direct labor cost

$230

Machine-hours used

30

Compute the total manufacturing cost assigned to Job 500.

3. During the year the company worked a total of 147,000 machine-hours on all jobs and incurred actual manufacturing overhead costs of $1,325,000. What is the amount of underapplied or overapplied overhead for the year? If this amount were closed out entirely to Cost of Goods Sold, would the journal entry increase or decrease net operating income?

Step-by-Step Solution

Request Professional Solution

Request Solution!

We need at least 10 more requests to produce the solution.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the solution will be notified once they are available.