Problem

Low Ball Construction Co. has determined that the heaviest load to be lifted on one of the...

Low Ball Construction Co. has determined that the heaviest load to be lifted on one of their projects weighs 22,000 lb. From the tower crane location on the building site, the required reach for this lift will be 100 ft. The crane is equipped with a L7 jib and a four-part hoist line (see the Table 17.3 load chart). This critical lift is of a piece of mechanical equipment and will require a 1,000-lb spreader bar attached to a 200-lb set of slings. If assembled in the proposed configuration, can the crane safely make the pick?

Load:

22,000 lb

Spreader bar:

1,000 lb

Slings:

200 lb

 

23,200 lb

Safety factor

× 1.05

Required lift capability

24,360 lb

From Table 7.3, at 100 ft – 9 inches reach with a four-part line and a L7 jib configuration the tower crane has a 22,600 lb capacity.

Step-by-Step Solution

Request Professional Solution

Request Solution!

We need at least 10 more requests to produce the solution.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the solution will be notified once they are available.
Add your Solution
Textbook Solutions and Answers Search
Solutions For Problems in Chapter 17