Assigning Costs Using Traditional System, ABC SystemLarkspur Corp. manufactures bird feede...

Assigning Costs Using Traditional System, ABC System

Larkspur Corp. manufactures bird feeders. It currently has two product lines, the standard and the deluxe. Larkspur has a total of $137,250 in overhead.

The company has identified the following information about its overhead activity pools and the two product lines:

 

 

Cost Assigned to Pool

Qty Consumed by Standard

Qty Consumed by Deluxe

Activity Pools

Cost Driver

Material handling

Number of moves

$ 3,500

20 moves

50 moves

Quality control

Number of inspections

$ 33,750

250 inspections

125 inspections

Machine

Number of

$100,000

5,000 machine

5,000 machine

maintenance

machine hrs

 

hours

hours

Required:

1.Suppose Larkspur used a traditional costing system with machine hours as the cost driver. Determine the amount of overhead assigned to each product line.


2. Calculate the activity rates for each cost pool in Larkspur's ABC system.


3. Calculate the amount of overhead that Larkspur will assign to the standard line if it uses an ABC system.


4. Determine the amount of overhead Larkspur will assign to the deluxe line if it uses an ABC system.


5. Compare the results for a traditional system with that of an ABC system. Which do you think is more accurate and why?

Step-by-Step Solution

Request Professional Solution

Request Solution!

We need at least 10 more requests to produce the solution.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the solution will be notified once they are available.
Add your Solution
Textbook Solutions and Answers Search