The following table lists the times required to complete the tasks of a particular project and the dependency among these tasks. Draw a PERT diagram for this project.
Task | Days Required | Preceding Tasks |
A | 3 | None |
B | 4 | A |
C | 6 | A |
D | 2 | A, B, C |
E | 5 | A, B, C, D |
F | 7 | A, B, C, D, E |