Lincoln Estates manufactures log homes to customers’ specifications and uses job order costing. A predetermined overhead rate is used In applying manufacturing overhead to individual jobs. In the Cutting Department, overhead is applied on the basis of machine-hours. In the Assembly Department overhead is applied on the basis of direct labor hours. At the beginning of the current year, management made the following estimates, to assist in determining the overhead application rates:
Annual Estimates | Cutting Department | Assembly Department |
Direct labor cost | $800,000 | $960,000 |
Direct labor hours | 40,000 | 32,000 |
Manufacturing overhead | 5600,000 | $480,000 |
Machine-hours | 30,000 | 15,000 |
Production of a home ordered by Cliff Newton ( job no. 80) was started early in the year and completed at the end of the first quarter, on March 31. The records for this job show the following cost information:
| Cutting Department | Assembly Department |
Job order for Cliff Newton (job no. 80): | ||
Direct materials cost | $100,000 | $150,000 |
Direct labor cost | $10,000 | $108,000 |
Direct labor hours | 500 | 3,600 |
Machine-hours | 400 | 300 |
Selected additional information for the first quarter is as follows:
| Cutting Department | Assembly Department |
Direct labor hours—first quarter | 8,000 | 6,000 |
Machine-hours—first quarter | 7,000 | 3,000 |
Manufacturing overhead incurred in first quarter | $142,000 | $87,000 |
Instructions
a. Compute the predetermined overhead rate for each department.
b. What is the total cost of the home produced for Cliff Newton?
c. Prepare the entries required to record the sale (on account of the home to Cliff Newton. The sales price of the order was- $602,000.
d. Determine the over- or undcrapplied overhead for each department at the end of the first’ quarter.