Jeff Heun, president of Whispering Always, agrees to construct a concrete cart path at Dakota Golf Club. Whispering Always enters into a contract with Dakota to construct the path for $174,000. In addition, as part of the contract, a performance bonus of $43,200 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $10,800 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 50% probability that he will complete the project on time, a 25% probability that he will be 1 week late, and a 25% probability that he will be 2 weeks late.
Determine the transaction price that Whispering Always should compute for this agreement.
Transaction Price | $enter the transaction price that Whispering Always should compute for this agreement |
eTextbook and Media
Assume that Jeff Heun has reviewed his work schedule and decided that it makes sense to complete this project on time. Assuming that he now believes that the probability for completing the project on time is 90% and otherwise it will be finished 1 week late, determine the transaction price.
Transaction price | $enter the transaction price in dollars |
a)
Particulars | Probability | Workings | Amount | Estimated amount |
Project completed on time | 50% | 43200 | 43200 | 21600 |
1 week late | 25% | 43200-(10800*1) | 32400 | 8100 |
2 week late | 25% | 43200-(10800*2) | 21600 | 5400 |
Total estimated performace bonus | 35100 |
Transactionprice = Cotract price + Estimated performance bonus
= 174000+35100
= $209100
b)
Particulars | Probability | Workings | Amount | Estimated amount |
Project completed on time | 90% | 43200 | 43200 | 38880 |
1week late | 10% | 43200-(10800*1) | 32400 | 3240 |
Total estimated performance bonus | 42120 |
Transaction price = Contract price + estimate performance bonus
= 174000+42120
= $216120
Jeff Heun, president of Whispering Always, agrees to construct a concrete cart path at Dakota Golf...
Jeff Heun, president of Pina Always, agrees to construct a concrete cart path at Dakota Golf Club. Pina Always enters into a contract with Dakota to construct the path for $161,000. In addition, as part of the contract, a performance bonus of $34,800 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,700 per week for every week beyond the agreed-upon completion...
Jeff Heun, president of Nash Always, agrees to construct a concrete cart path at Dakota Golf Club. Nash Always enters into a contract with Dakota to construct the path for $183,000. In addition, as part of the contract, a performance bonus of $38,800 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $9,700 per week for every week beyond the agreed-upon completion...
Jeff Heun, president of Coronado Always, agrees to construct a concrete cart path at Dakota Golf Club. Coronado Always enters into a contract with Dakota to construct the path for $223,000. In addition, as part of the contract, a performance bonus of $34,400 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,600 per week for every week beyond the agreed-upon completion...
Jeff Heun, president of Pina Always, agrees to construct a concrete cart path at Dakota Golf Club. Pina Always enters into a contract with Dakota to construct the path for $222,000. In addition, as part of the contract, a performance bonus of $38,800 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $9,700 per week for every week beyond the agreed-upon completion...
Jeff Heun, president of Pearl Always, agrees to construct a concrete cart path at Dakota Golf Club. Pearl Always enters into a contract with Dakota to construct the path for $215,000. In addition, as part of the contract, a performance bonus of $32,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,000 per week for every week beyond the agreed-upon completion...
Exercise 18-05 Jeff Heun, president of Concrete Always, agrees to construct a concrete cart path at Dakota Golf Club. Concrete Always enters into a contract with Dakota to construct the path for $200,000. In addition, as part of the contract, a performance bonus of $40,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $10,000 per week for every week beyond the...
Exercise 18-5 Jeff Heun, president of Marigold Always, agrees to construct a concrete cart path at Dakota Golf Club. Marigold Always enters into a contract with Dakota to construct the path for $161,000. In addition, as part of the contract, a performance bonus of $34,800 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,700 per week for every week beyond the...
E18.5 (LO 2) (Determine Transaction Price) Jeff Heun, president of Concrete Always, agrees to construct a concrete cart path at Dakota Golf Club. Concrete Always enters into a contract with Dakota to construct the path for $200,000. In addition, as part of the contract, a performance bonus 1 0.00 will be paid based on the timing of completion. The performance bonus will be paid fully if competcu by the agreed-upon date. The performance bonus decreases by $10.000 per week for...
Concrete Company enters into a contract with a customer to build a warehouse for $200,000, with a performance bonus of $40,000 that will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agree-upon date. The performance bonus decreases by $10,000 per week for every week beyond the agreed-upon completion date. Management estimates that there is a 55% probability that he will complete the project on time, a 30% probability that...
look Princ Maried out of 5.00 PF Determining the Transaction Price for a Revenue Contract A contractor enters into a revenue correct with a customer to build customired equipment for $180.000 with a performance bonus of 199.000 that will be paid based on how quickly the equipment is completed. The amount of the performance bonus decreases by 15% of the original bonus per week for every week beyond the agreed upon completion date. The contractor has had experiences with similar...