Calculation of transaction price
transaction price = contract price+bonus
Calculation of performance bonus
probability(a) amount(b) eatimated bonus (a)*(b)
completed on time 55% 38800 21340
1 week later 25% 29100 7275
2 week later 20% 19400 3880
total estimated performance bonus 32495
Transaction price = 183000+32495 = 215495
b)
estimated performance bonus
probability(a) amount(b) eatimated bonus (a)*(b)
completed on tine 86% 38800 33368
1 week later 14% 29100 4074
total estimated performance bonus 37442
Transaction price = 183000+37442 = 220442
Add a comment
Know the answer?
Add Answer to:
Jeff Heun, president of Nash Always, agrees to construct a concrete cart path at Dakota Golf...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Jeff Heun, president of Pina Always, agrees to construct a concrete cart path at Dakota Golf...

    Jeff Heun, president of Pina Always, agrees to construct a concrete cart path at Dakota Golf Club. Pina Always enters into a contract with Dakota to construct the path for $161,000. In addition, as part of the contract, a performance bonus of $34,800 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,700 per week for every week beyond the agreed-upon completion...

  • Jeff Heun, president of Whispering Always, agrees to construct a concrete cart path at Dakota Golf...

    Jeff Heun, president of Whispering Always, agrees to construct a concrete cart path at Dakota Golf Club. Whispering Always enters into a contract with Dakota to construct the path for $174,000. In addition, as part of the contract, a performance bonus of $43,200 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $10,800 per week for every week beyond the agreed-upon completion...

  • Jeff Heun, president of Coronado Always, agrees to construct a concrete cart path at Dakota Golf...

    Jeff Heun, president of Coronado Always, agrees to construct a concrete cart path at Dakota Golf Club. Coronado Always enters into a contract with Dakota to construct the path for $223,000. In addition, as part of the contract, a performance bonus of $34,400 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,600 per week for every week beyond the agreed-upon completion...

  • Jeff Heun, president of Pina Always, agrees to construct a concrete cart path at Dakota Golf Club. Pina Always enters in...

    Jeff Heun, president of Pina Always, agrees to construct a concrete cart path at Dakota Golf Club. Pina Always enters into a contract with Dakota to construct the path for $222,000. In addition, as part of the contract, a performance bonus of $38,800 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $9,700 per week for every week beyond the agreed-upon completion...

  • Jeff Heun, president of Pearl Always, agrees to construct a concrete cart path at Dakota Golf Club. Pearl Always enters...

    Jeff Heun, president of Pearl Always, agrees to construct a concrete cart path at Dakota Golf Club. Pearl Always enters into a contract with Dakota to construct the path for $215,000. In addition, as part of the contract, a performance bonus of $32,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,000 per week for every week beyond the agreed-upon completion...

  • Exercise 18-05 Jeff Heun, president of Concrete Always, agrees to construct a concrete cart path at...

    Exercise 18-05 Jeff Heun, president of Concrete Always, agrees to construct a concrete cart path at Dakota Golf Club. Concrete Always enters into a contract with Dakota to construct the path for $200,000. In addition, as part of the contract, a performance bonus of $40,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $10,000 per week for every week beyond the...

  • Exercise 18-5 Jeff Heun, president of Marigold Always, agrees to construct a concrete cart path at...

    Exercise 18-5 Jeff Heun, president of Marigold Always, agrees to construct a concrete cart path at Dakota Golf Club. Marigold Always enters into a contract with Dakota to construct the path for $161,000. In addition, as part of the contract, a performance bonus of $34,800 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,700 per week for every week beyond the...

  • E18.5 (LO 2) (Determine Transaction Price) Jeff Heun, president of Concrete Always, agrees to construct a concrete...

    E18.5 (LO 2) (Determine Transaction Price) Jeff Heun, president of Concrete Always, agrees to construct a concrete cart path at Dakota Golf Club. Concrete Always enters into a contract with Dakota to construct the path for $200,000. In addition, as part of the contract, a performance bonus 1 0.00 will be paid based on the timing of completion. The performance bonus will be paid fully if competcu by the agreed-upon date. The performance bonus decreases by $10.000 per week for...

  • Concrete Company enters into a contract with a customer to build a warehouse for $200,000, with...

    Concrete Company enters into a contract with a customer to build a warehouse for $200,000, with a performance bonus of $40,000 that will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agree-upon date. The performance bonus decreases by $10,000 per week for every week beyond the agreed-upon completion date. Management estimates that there is a 55% probability that he will complete the project on time, a 30% probability that...

  • look Princ Maried out of 5.00 PF Determining the Transaction Price for a Revenue Contract A...

    look Princ Maried out of 5.00 PF Determining the Transaction Price for a Revenue Contract A contractor enters into a revenue correct with a customer to build customired equipment for $180.000 with a performance bonus of 199.000 that will be paid based on how quickly the equipment is completed. The amount of the performance bonus decreases by 15% of the original bonus per week for every week beyond the agreed upon completion date. The contractor has had experiences with similar...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT