Solution:

Consideration Bonus Amount Probability of Outcome Revenue Recognized
Bonus if completed on agreed upon date $99,000.00 60% $59,400.00
Bonus if completed one week late $84,150.00 35% $29,453.00
Bonus if completed two weeks late $69,300.00 5% $3,465.00
Variable consideration $92,318.00
Fixed consideration $180,000.00
Total transaction price $272,318.00
Add a comment
Know the answer?
Add Answer to:
look Princ Maried out of 5.00 PF Determining the Transaction Price for a Revenue Contract A...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Concrete Company enters into a contract with a customer to build a warehouse for $200,000, with...

    Concrete Company enters into a contract with a customer to build a warehouse for $200,000, with a performance bonus of $40,000 that will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agree-upon date. The performance bonus decreases by $10,000 per week for every week beyond the agreed-upon completion date. Management estimates that there is a 55% probability that he will complete the project on time, a 30% probability that...

  • Entity A enters into a construction contract (Contract C) with Entity B to build a factory...

    Entity A enters into a construction contract (Contract C) with Entity B to build a factory for $2,860,000 on 1 April 2020. To encourage completion on time, Entity B agreed to pay a performance bonus of $180,000 that would be paid based on the actual completion time. The amount of the performance bonus decreases by 8.00% per week for every week if the completion date beyond the agreed completion date. The requirements of the contract are similar to the contracts...

  • E18.5 (LO 2) (Determine Transaction Price) Jeff Heun, president of Concrete Always, agrees to construct a concrete...

    E18.5 (LO 2) (Determine Transaction Price) Jeff Heun, president of Concrete Always, agrees to construct a concrete cart path at Dakota Golf Club. Concrete Always enters into a contract with Dakota to construct the path for $200,000. In addition, as part of the contract, a performance bonus 1 0.00 will be paid based on the timing of completion. The performance bonus will be paid fully if competcu by the agreed-upon date. The performance bonus decreases by $10.000 per week for...

  • Went Wlowing samt apters 18, 7 and 8th stice test to help you id above. The...

    Went Wlowing samt apters 18, 7 and 8th stice test to help you id above. The sample ex 1. Revenue Recognition (20 points) REQUIRED: Provide answers for questions 1-4 in the space provided. 1. What is the five-step process for revenue recognition? 2. On March 1, 2003, the Star Printing Company received a $45.000 payment for annual magazine subscriptions (the subscriptions run from the March, 2003 edition through the February 2004 edition). Upon receipt of the payment, Star Printing credited...

  • Exercise 18-5 Jeff Heun, president of Marigold Always, agrees to construct a concrete cart path at...

    Exercise 18-5 Jeff Heun, president of Marigold Always, agrees to construct a concrete cart path at Dakota Golf Club. Marigold Always enters into a contract with Dakota to construct the path for $161,000. In addition, as part of the contract, a performance bonus of $34,800 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,700 per week for every week beyond the...

  • Jeff Heun, president of Pina Always, agrees to construct a concrete cart path at Dakota Golf...

    Jeff Heun, president of Pina Always, agrees to construct a concrete cart path at Dakota Golf Club. Pina Always enters into a contract with Dakota to construct the path for $161,000. In addition, as part of the contract, a performance bonus of $34,800 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,700 per week for every week beyond the agreed-upon completion...

  • Exercise 18-05 Jeff Heun, president of Concrete Always, agrees to construct a concrete cart path at...

    Exercise 18-05 Jeff Heun, president of Concrete Always, agrees to construct a concrete cart path at Dakota Golf Club. Concrete Always enters into a contract with Dakota to construct the path for $200,000. In addition, as part of the contract, a performance bonus of $40,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $10,000 per week for every week beyond the...

  • Jeff Heun, president of Nash Always, agrees to construct a concrete cart path at Dakota Golf...

    Jeff Heun, president of Nash Always, agrees to construct a concrete cart path at Dakota Golf Club. Nash Always enters into a contract with Dakota to construct the path for $183,000. In addition, as part of the contract, a performance bonus of $38,800 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $9,700 per week for every week beyond the agreed-upon completion...

  • Jeff Heun, president of Pearl Always, agrees to construct a concrete cart path at Dakota Golf Club. Pearl Always enters...

    Jeff Heun, president of Pearl Always, agrees to construct a concrete cart path at Dakota Golf Club. Pearl Always enters into a contract with Dakota to construct the path for $215,000. In addition, as part of the contract, a performance bonus of $32,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,000 per week for every week beyond the agreed-upon completion...

  • Jeff Heun, president of Coronado Always, agrees to construct a concrete cart path at Dakota Golf...

    Jeff Heun, president of Coronado Always, agrees to construct a concrete cart path at Dakota Golf Club. Coronado Always enters into a contract with Dakota to construct the path for $223,000. In addition, as part of the contract, a performance bonus of $34,400 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,600 per week for every week beyond the agreed-upon completion...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT