Solution:
We need to find out first Standard Variable Overhead and standard fixed overhead from the data of planned production.
Total budgeted manufacturing overhead = $124,500
Budgeted Fixed Manufacturing Overhead = $124,500 * 20% = $24,900
Standard Variable Manufacturing Overhead = $124,500 total – Fixed $24,900
= $99,600
Budgeted direct labor hours = Planned production 8,300 Units x Required labor hour each unit 2 = 16,600 Hours
Standard variable manufacturing overhead per direct labor hour = Total Std variable overhead $99,600 / Budgeted direct labor hour 16,600
= $6 per direct labor hour
Std fixed overhead rate per direct labor hour = Total Fixed Overhead $24,900 / Budgeted DLHs 16,600
= $1.50 per direct labor hour
Calculation of Variable Spending and Efficiency Variance
Variable Overhead Rate/Spending Variance |
||
Actual Hourly Variable Overhead Rate (Total actual $100,800 / Actual hours 16,290) |
6.19 |
Per Hour |
Standard Hourly Variable Overhead Rate |
6.00 |
Per Hour |
Variance or Difference in Rate |
0.19 |
Per Hour |
x Actual Hours Worked |
16290 |
Hours |
Variable Overhead Rate/Spending Variance |
$3,060 |
Unfavorable |
Variable Overhead Efficiency/Quantity Variance |
||
Standard Hours Allowed for actual production: |
||
Actual Production |
8,000 |
Pools |
x Allowed Standard Hours Per Unit |
2 |
Hours |
Total Standard Hours Allowed for actual production (SHAP) |
16000 |
Hours |
Actual Hours Worked (AH) |
16290 |
Hours |
Variance or Difference in Hours |
290 |
hours |
x Standard Hourly Variable Overhead Rate |
$6.00 |
per hour |
Variable Overhead Efficiency Variance |
$1,740 |
Unfavorable |
Calculation of fixed overhead spending and volume variance
Fixed Overhead Expenditure/Spending/Budget Variance |
||
Budgeted Fixed Overheads (BFOH) |
$24,900 |
|
Actual Fixed Overheads (AFOH) |
$28,400 |
|
Fixed Overhead Expenditure Variance |
$3,500 |
Unfavorable |
Fixed Overhead Volume Variance |
||
Budgeted Fixed Manufacturing Overheads |
$24,900 |
|
Fixed Overhead Cost Applied (Refer Note) |
$24,000 |
|
Fixed Overhead Volume Variance |
$900 |
Unfavorable |
Note: |
||
Std labor hours allowed for the actual output (8,000 Units * 2) |
16000 |
Direct labor hour |
Std Fixed Overhead Rate per labor hour |
$1.50 |
Per labor hour |
Applied Fixed Overhead Cost |
$24,000 |
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you
Question 26 Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,600 units. Manufacturing overhead is budgeted at $120,400 for the period (20% of this cost is fixed). The 16,500 hours worked during the period resulted in the production of 8,170 units. The variable manufacturing overhead cost incurred was $97,400 and the fixed manufacturing overhead cost was $28,900. Partially correct answer. ...
Derf Company allocates overhead on the basis of direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 9000 units. Manufacturing overhead is estimated at $135,000 for the period (20 per cent of this cost is fixed). The 17,200 hours worked during the period resulted in the production of 8500 units. Variable manufacturing overhead cost incurred was $108,500 and the fixed manufacturing overhead cost was $28,000. Required(a) Determine the...
Better Fitness Gear applies overhead on the basis of direct labor hours. Five direct labor hours are required for each unit produced. Planned production for the period was set at 8,000 units. Budgeted fixed manufacturing overhead for the period is budgeted at $20,000 and variable manufacturing overhead is budgeted at $100,000. The 48,500 hours worked during the period resulted in production of 9,500 units. Actual manufacturing overhead cost incurred was $156,000. Required: Calculate the three overhead variances: a. Total Spending...
ABC Manufacturing Company's costing system has two direct cost categories: direct materials and direct manufacturing labour. Manufacturing overhead (both variable and fixed) is allocated to products on the basis of standard DMLH At the beginning of 2018, ABC adopted the following standards for its manufacturing costs: Input Cost per Output Unit S 15 75 3 kg at $5 per kg 5 hours at $15 per hour Direct materials Direct manufacturing labour Manufacturing overhead: Variable Fixed Standard manufacturing cost per output...
Prado Company applies fixed manufacturing overhead costs to products based on direct labor hours. Information for the month of April appears below. Prado's expected to produce and sell 500 units for the month. Budgeted fixed overhead costs $240,000 Budgeted direct labor hours ÷ 12,000 Standard cost per direct labor hour $ 20 Standard direct labor hours per unit 18 Actual production 520 units Actual fixed overhead costs $210,000 Required: Calculate the fixed overhead spending variance and production volume variance. Clearly...
11.25Overhead variances: manufacturer LO5] standard manufacturing overhead costs per switch are based on direct 1abour hours and are a& follows Bright Spark Ltd is a manufacturer of electrical switches, and uses a standard costing system. The Variable overhead (5 hours$12 per hour) Fixed overhead (5 hours@$18 per hour)* Total overhead $ 60 90 $150 Based on capacity 300000 irect labour hours per month The following information is available for the month of October: 56000 switches were produced, although 60000 switches...
Franklin Glass Works uses a standard cost system in which manufacturing overhead is applied to units of product on the basis of direct labour-hours. Each unit requires two standard hours of labour for completion. The denominator activity for the year was based on budgeted production of 200,000 units. Total overhead was budgeted at £900,000 for the year, and the fixed overhead rate was £3.00 per unit. The actual data pertaining to the manufacturing overhead for the year are presented below:...
Calculate the fixed overhead production volume variance.Fixed overhead production volume variance$ Neither favourable nor unfavourableUnfavourableFavourableCalculate the variable overhead spending variance.Variable overhead spending variance$ FavourableUnfavourableNeither favourable nor unfavourableCalculate the variable overhead efficiency variance.Variable overhead efficiency variance$ Neither favourable nor unfavourableFavourableUnfavourableCalculate the over- or underapplied overhead.
10 material (day Direct labor Variable manufacturing overhead (based on direct labor hours) manufacturing overhead (5392,990.00 140,000.00 units 70 hrs. $ 1.1e per hr Barley Hopp had the following actual results last year 145,000 258,280 438,940 Number of units produced and sold Number of pounds of clay used Cost of clay Number of labor hours worked Direct labor COS Variable overhead cost Fixed Overhead cost 190,- Salad 410,000 Required: 1. Calculate the direct materiais price, quantity and total spending variances...
Question 24 Rondell Company uses standard cost system. Indirect costs were budgeted at $190,800 plus $13 per direct labour hour. The overhead rate is based on 10,600 hours. Actual results were: Standard direct labour hours allowed Actual direct labour hours Fixed overhead Variable overhead 9,070 10,600 $179,000 $174,400 Calculate the fixed overhead production volume variance. Fixed overhead production volume variance Calculate the variable overhead spending variance. Variable overhead spending variance $ Calculate the variable overhead efficiency variance. Variable overhead efficiency...