Question

Franklin Glass Works uses a standard cost system in which manufacturing overhead is applied to units...

Franklin Glass Works uses a standard cost system in which manufacturing overhead is applied to units of product on the basis of direct labour-hours. Each unit requires two standard hours of labour for completion. The denominator activity for the year was based on budgeted production of 200,000 units. Total overhead was budgeted at £900,000 for the year, and the fixed overhead rate was £3.00 per unit. The actual data pertaining to the manufacturing overhead for the year are presented below: Actual production 198,000 units. Actual direct labour-hours 440,000 direct labour-hours. Actual variable overhead £352,000. Actual fixed overhead £575,000.

The standard hours allowed for the actual production for the year is?

The fixed overhead applied to Franklin's production for the year is?

Franklin’s Total variable overhead cost variance is?

Franklin's variable overhead spending variance for the year is?

Franklin's variable overhead efficiency variance for the year is?

Franklin's Total Fixed overhead cost variance is?

Franklin's fixed overhead volume variance for the year is?

Franklin's fixed overhead budget variance for the year is?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
The standard hours allowed for the actual production for the year is?
396000
The fixed overhead applied to Franklin's production for the year is?
£ 5,94,000.00
Franklin’s Total variable overhead cost variance is?
£      55,000.00
Franklin's variable overhead spending variance for the year is?
£      22,000.00
Franklin's variable overhead efficiency variance for the year is?
£      33,000.00
Franklin's Total Fixed overhead cost variance is?
£      25,000.00 Favorable
Franklin's fixed overhead volume variance for the year is?
£        6,000.00 Unfavorable
Franklin's fixed overhead budget variance for the year is?
£      19,000.00 Favorable

Workings

Franklin’s Total variable overhead cost variance is?

Budgeted Fixed Overhead=200,000 units *  £3.00 per unit==£600,000

Budgeted Variable overhead for 200,000 units =£900,000-£600,000=£300,000

Standard overhead rate
Budgeted Variable overhead £300,000
Budgeted Direct Labor hour 200000 unit * 2hr per units 400000
Standard overhead rate =£300,000/400000 .75 per Hr
Standard hour for 198000 units =198000*2 396000
Overhead Applied based on standard hour 396000 hrs *.75 per hr (A) £ 2,97,000.00
Actual variable overhead (B) £ 3,52,000.00
Total variable overhead cost variance =A-B £      55,000.00

Franklin's variable overhead spending variance for the year is?

Actual Direct Labor 440000
Overhead Applied 440000*.75 A £ 3,30,000.00
Actual variable overhead (B) £ 3,52,000.00
variable overhead spending variance (A-B) £      22,000.00 Unfavorable
Overhead based on standard hour 396000 hrs *.75 per hr (A) £ 2,97,000.00
Overhead Applied 440000*.75 A £ 3,30,000.00
variable overhead efficiency variance (A-B) £      33,000.00 Unfavorable
Franklin's Total Fixed overhead cost variance is?
Budgeted Fixed overhead variance (A) £ 6,00,000.00
Actual fixed overhead variance( B ) £ 5,75,000.00
Franklin's Total Fixed overhead cost variance is? (A-B) £      25,000.00 Favorable
Franklin's fixed overhead volume variance for the year is?
Absorbed fixed overheads 198000* £3.00 per unit £ 5,94,000.00
Budgeted Fixed overhead variance (A) £ 6,00,000.00
Franklin's fixed overhead volume variance for the year is? (A-B)
£        6,000.00 Unfavorable
Franklin's fixed overhead budget variance for the year is?
Absorbed fixed overheads 198000* £3.00 per unit £ 5,94,000.00
Actual Fixed Overhead £ 5,75,000.00
Franklin's fixed overhead budget variance for the year is? £      19,000.00 Favorable
Add a comment
Know the answer?
Add Answer to:
Franklin Glass Works uses a standard cost system in which manufacturing overhead is applied to units...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cyberdyne Systems Corporation uses a standard-costing system. The production budget for the fiscal year (FY) ended...

    Cyberdyne Systems Corporation uses a standard-costing system. The production budget for the fiscal year (FY) ended 30 November 2018 was based on 200,000 units of output. Each unit requires two standard hours of manufacturing labor for completion. Total overhead was budgeted at $900,000 for the year, and the budgeted fixed overhead rate was $3 per unit of output. Both fixed and variable overhead are allocated to the product on the basis of direct manufacturing labor-hours. The actual data for the...

  • Cyberdyne Systems Corporation uses a standard-costing system. The production budget for the fiscal year (FY) ended...

    Cyberdyne Systems Corporation uses a standard-costing system. The production budget for the fiscal year (FY) ended 30 November 2018 was based on 200,000 units of output. Each unit requires two standard hours of manufacturing labor for completion. Total overhead was budgeted at $900,000 for the year, and the budgeted fixed overhead rate was $3 per unit of output. Both fixed and variable overhead are allocated to the product on the basis of direct manufacturing labor-hours. The actual data for the...

  • Cyberdyne Systems Corporation uses a standard-costing system. The production budget for the fiscal year (FY) ended...

    Cyberdyne Systems Corporation uses a standard-costing system. The production budget for the fiscal year (FY) ended 30 November 2018 was based on 200,000 units of output. Each unit requires two standard hours of manufacturing labor for completion. Total overhead was budgeted at $900,000 for the year, and the budgeted fixed overhead rate was $3 per unit of output. Both fixed and variable overhead are allocated to the product on the basis of direct manufacturing labor-hours. The actual data for the...

  • Soriano Manufacturing Company uses a standard cost accounting system to account for the manufacturing of exhaust...

    Soriano Manufacturing Company uses a standard cost accounting system to account for the manufacturing of exhaust fans. In July 2020, it accumulates the following data for 1,500 units started and finished: Cost and Production Data Actual Standard Raw materials Units purchased 21,000 Units used 21,000 22,000 Unit cost $3.40 $3.00 Direct labour Hours worked 3,450 3,600 Hourly rate $11.80 $12.50 Manufacturing overhead Incurred $101,500 Applied $108,000 Manufacturing overhead was applied based on direct labour hours. Normal capacity for the month...

  • MA Company uses a standard cost system in which manufacturing overhead costs are applied to units...

    MA Company uses a standard cost system in which manufacturing overhead costs are applied to units of the company's single product on the basis of direct laborhours (DLHs). The cost information for the product is as follows: Standard Cost per unit of product: Direct Materials, 2 metres at $4 per metre ....................................... $ 8 Direct Labor, 2 DLHs at $10 per DLH .................................................. $20 Variable Manufacturing Overhead, 2 DLHs at $2 per DLH ............ $ 4 Fixed ManufacturingOverhead, 2 DLHs...

  • MA Company uses a standard cost system in which manufacturing overhead costs are applied to units of the company's s...

    MA Company uses a standard cost system in which manufacturing overhead costs are applied to units of the company's single product on the basis of direct laborhours (DLHs). The cost information for the product is as follows: Standard Cost per unit of product: Direct Materials, 2 metres at $4 per metre ....................................... $ 8 Direct Labor, 2 DLHs at $10 per DLH .................................................. $20 Variable Manufacturing Overhead, 2 DLHs at $2 per DLH ............ $ 4 Fixed ManufacturingOverhead, 2 DLHs...

  • Derf Corporation uses a standard cost system in which it applies manufacturing overhead on the basis...

    Derf Corporation uses a standard cost system in which it applies manufacturing overhead on the basis of standard direct labor-hours. Two direct labor-hours are required for each unit produced. The denominator activity was set at 6,400 units. Manufacturing overhead was budgeted at $102,400 for the period; 20 percent of this cost was fixed. The 11,670 hours worked during the period resulted in production of 5,710 units. Variable manufacturing overhead cost incurred was $82,420 and fixed manufacturing overhead cost was $22,230....

  • 1. Lee Manufacturing uses a standard cost system with overhead applied based on direct labor hours....

    1. Lee Manufacturing uses a standard cost system with overhead applied based on direct labor hours. The manufacturing budget for the production of 5,000 units for the month of May included the following information. Direct labor (10,000 hours at $15 per hour) $150,000 Variable overhead                                          $30,000 Fixed overhead                                                $80,000 During May, 6,000 units were produced and the direct labor efficiency variance was $1,500 unfavorable. Based on this information, the actual number of direct labor hours used in...

  • Primara Corporation has a standard cost system in which it applies overhead to products based on...

    Primara Corporation has a standard cost system in which it applies overhead to products based on the standard direct labor-hours allowed for the actual output of the period. Data concerning the most recent year appear below: Total budgeted fixed overhead cost for the year Actual fixed overhead cost for the year Budgeted direct labor-hours (denominator level of activity) Actual direct labor-hours Standard direct labor-hours allowed for the actual output $ 473,600 $ 467,000 64,000 65,000 62,000 Required: 1. Compute the...

  • Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...

    Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 52,200 machine hours per year, which represents 26,100 units of output. Annual budgeted fixed factory overhead costs are $261,000 and the budgeted variable factory overhead cost rate is $2.70 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT